First Baptist Church v. Barber Contracting Co.

377 S.E.2d 717, 189 Ga. App. 804, 1989 Ga. App. LEXIS 25
CourtCourt of Appeals of Georgia
DecidedJanuary 9, 1989
Docket77340, 77341
StatusPublished
Cited by11 cases

This text of 377 S.E.2d 717 (First Baptist Church v. Barber Contracting Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
First Baptist Church v. Barber Contracting Co., 377 S.E.2d 717, 189 Ga. App. 804, 1989 Ga. App. LEXIS 25 (Ga. Ct. App. 1989).

Opinion

McMurray, Presiding Judge.

The First Baptist Church of Moultrie, Georgia, invited bids for the construction of a music, education and recreation building. The bids were to be opened on May 15, 1986. They were to be accompanied by a bid bond in the amount of 5 percent of the base bid. The bidding instructions provided, in pertinent part: “Negligence on the part of the bidder in preparing the bid confers no right for the withdrawal of the bid after it has been opened.”

Barber Contracting Company (“Barber”) submitted a bid for the project in the amount of $1,860,000. The bid provided, in pertinent part: “For and in consideration of the sum of $1.00, the receipt of which is hereby acknowledged, the undersigned agrees that this proposal may not be revoked or withdrawn after the time set for the opening of bids but shall remain open for acceptance for a period of thirty-five (35) days following such time.” The bid also provided that if it was accepted within 35 days of the opening of bids, Barber would execute a contract for the construction of the project within 10 days of the acceptance of the bid.

A bid bond in the amount of 5 percent of Barber’s bid ($93,000) was issued by The American Insurance Company to cover Barber’s bid. With regard to the bid bond, the bid submitted by Barber provided: “If this proposal is accepted within thirty-five (35) days after the date set for the opening of bids and the undersigned [Barber] fails to execute the contract within ten (10) days after written notice *805 of such acceptance . . . the obligation of the bid bond will remain in full force and effect and the money payable thereon shall be paid into the funds of the Owner as liquidated damages for such failure ...”

The bids were opened by the church on May 15, 1986, as planned. Barber submitted the lowest bid. The second lowest bid, in the amount of $1,975,000 was submitted by H & H Construction and Supply Company, Inc. (“H & H”).

Barber’s president, Albert W. Barber, was present when the bids were opened, and of course, he was informed that Barber was the low bidder. Members of the church building committee informally asked President Barber if changes could be made in the contract to reduce the amount of the bid. He replied that he was sure such changes could be made.

On May 16, 1986, Albert W. Barber informed the architect for the project, William Frank McCall, Jr., that the amount of the bid was in error — the bid should have been $143,120 higher. In Mr. Barber’s words: “[T]he mistake in Barber’s bid was caused by an error in totaling the material costs on page 3 of Barber’s estimate work sheets. The subtotal of the material cost listed on that page is actually $137,990. The total listed on Barber’s summary sheet for the material cost subtotal was $19,214. The net error in addition was $118,776. After adding in mark-ups for sales tax (4 percent), overhead and profit (15 percent), and bond procurement costs (.75 percent), the error was compounded to a total of $143,120 . . .” The architect immediately telephoned Billy G. Fallin, co-chairman of the church building committee, and relayed the information which he received from President Barber.

On May 20, 1986, Barber delivered letters to the architect and the church. In the letter to the architect, Barber enclosed copies of its estimate sheets and requested that it be permitted to withdraw its bid. In the letter to the church, Barber stated that it was withdrawing its bid on account of “an error in adding certain estimated material costs.” In addition, Barber sought the return of the bid bond from the church.

On May 29, 1986, the church forwarded a construction contract, based upon Barber’s bid, to Barber. The contract had been prepared by the architect and executed by the church. The next day, Barber returned the contract to the church without executing it. In so doing, Barber pointed out that its bid had been withdrawn previously.

On July 25, 1986, the church entered into a construction contract for the project with H & H, the second lowest bidder. Through deletions and design changes, the church was able to secure a contract with H & H for $1,919,272.

In the meantime, the church demanded that Barber and The American Insurance Company pay it $93,000 pursuant to the bid *806 bond. The demand was refused.

On May 26, 1987, the church brought suit against Barber and The American Insurance Company seeking to recover the amount of the bid bond. Answering the complaint, defendants denied they were liable to plaintiff.

Thereafter, defendants moved for summary judgment and so did the plaintiff. In support of their summary judgment motions, defendants submitted the affidavit of Albert W. Barber. He averred that in preparing its bid, Barber exercised the level of care ordinarily exercised by contractors submitting sealed bids. In support of its summary judgment motion, the church submitted the affidavit of a building contractor who averred that he would never submit a bid of any magnitude without obtaining assistance in verification and computation.

The trial court denied the summary judgment motions, certified its rulings for immediate review and we granted these interlocutory appeals. Held:

The question for decision is whether Barber was entitled to rescind its bid upon discovering that it was based upon a miscalculation or whether Barber should forfeit its bond because it refused to execute the contract following the acceptance of its bid by the church. We hold that Barber was entitled to rescind its bid.

That equity will rescind a contract upon a unilateral mistake is a generally accepted principle. See Corbin on Contracts, § 609 (1960). As it is said: “Where a mistake of one party at the time a contract was made as to a basic assumption on which he made the contract has a material effect on the agreed exchange of performances that is adverse to him, the contract is voidable by him if he does not bear the risk of the mistake . . . and (a) the effect of the mistake is such that enforcement of the contract would be unconscionable, or (b) the other party had reason to know of the mistake or his fault caused the mistake.” Restatement (2d) of Contracts, § 153 (1979).

The following illustration demonstrates the rule: “In response to B’s invitation for bids on the construction of a building according to stated specifications, A submits an offer to do the work for $150,000. A believes that this is the total of a column of figures, but he has made an error by inadvertently omitting a $50,000 item, and in fact the total is $200,000. B, having no reason to know of A’s mistake, accepts A’s bid. If A performs for $150,000, he will sustain a loss of $20,000 instead of making an expected profit of $30,000. If the court determines that enforcement of the contract would be unconscionable, it is voidable by A.” Restatement (2d) of Contracts, § 153 (1979) (Illustration 1).

Corbin explains: “Suppose ... a bidding contractor makes an offer to supply specified goods or to do specified work for a definitely *807 named price, and that he was caused to name this price by an antecedent error of computation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jan Miller v. John H. Evans
Court of Appeals of Georgia, 2023
Super98, LLC v. Delta Air Lines, Inc.
309 F. Supp. 3d 1368 (N.D. Georgia, 2018)
Decision One Mortgage Co. v. Victor Warren Properties, Inc.
696 S.E.2d 145 (Court of Appeals of Georgia, 2010)
DeGolyer v. Green Tree Servicing, LLC
662 S.E.2d 141 (Court of Appeals of Georgia, 2008)
Jenkins v. Sallie Mae, Inc.
649 S.E.2d 802 (Court of Appeals of Georgia, 2007)
Department of Transportation v. American Insurance
491 S.E.2d 328 (Supreme Court of Georgia, 1997)
LPS Construction Co. v. Georgia Department of Defense
491 S.E.2d 920 (Court of Appeals of Georgia, 1997)
National Fire Insurance v. Brown & Martin Co.
726 F. Supp. 1036 (D. South Carolina, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
377 S.E.2d 717, 189 Ga. App. 804, 1989 Ga. App. LEXIS 25, Counsel Stack Legal Research, https://law.counselstack.com/opinion/first-baptist-church-v-barber-contracting-co-gactapp-1989.