Debreceni v. Merchants Terminal Corp.

740 F. Supp. 894, 1989 U.S. Dist. LEXIS 17083, 1989 WL 222472
CourtDistrict Court, D. Massachusetts
DecidedFebruary 23, 1989
DocketCiv. A. 87-0692-WD
StatusPublished
Cited by8 cases

This text of 740 F. Supp. 894 (Debreceni v. Merchants Terminal Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Debreceni v. Merchants Terminal Corp., 740 F. Supp. 894, 1989 U.S. Dist. LEXIS 17083, 1989 WL 222472 (D. Mass. 1989).

Opinion

MEMORANDUM AND ORDER

WOODLOCK, District Judge.

I.

In this case the parties have come belatedly to court to effect implementation of the relatively mechanical procedures Congress established to expedite resolution of claims concerning withdrawal liability under multiemployer pension plans.

Before this action began, the plaintiff pension fund manager chose for over three years not to demand prompt judicial enforcement of her fund’s rights to interim payments of that liability. For their part the defendants did not seek to compel prompt arbitration of their dispute concerning the extent of withdrawal liability until they filed a counterclaim in this action.

I will grant the parties’ respective belated requests in a manner calibrated to reflect the consequences of the leisurely approach they have taken to enforcement proceedings.

II.

The plaintiff, Helen • Debreeeni, is the manager of the New England Teamsters & Trucking Industry Pension Fund (“the Fund”), and defendants and counterclaim plaintiffs, Merchants Terminal Corporation and Terminal Refrigeration & Warehousing, Inc., (collectively “Merchants”), are participating employers in the Fund, a multiemployer pension plan within the meaning of the Multiemployer Pension Plan Amendments Act of 1980 (“MPPAA”), codified at 29 U.S.C. §§ 1381-1461 (1982).

Prior to November, 1982, Motor Freight, a company in which Merchants owned almost all the voting stock, was obligated under the MPPAA to contribute to the Fund on behalf of its employees. On November 12, 1982, Motor Freight ceased its operations and withdrew from the Fund. On June 30, 1983, the Fund notified Merchants that their withdrawal liability under the MPPAA amounted to $341,283.00, if paid in a lump sum, and $404,361.00, if paid in installments. The notification set forth a schedule of payments in accordance with which the first payment was due on September 1, 1983.

Merchants then sent a letter to the Fund asking that it review its determination of liability, pursuant to 29 U.S.C. § 1399(b)(2)(A), and requesting the Fund to supply them with information relevant to its claim, pursuant to 29 U.S.C. § 1401(e). In January, 1984, in accordance with 29 U.S.C. § 1401(a)(1), Merchants requested that the Fund participate in arbitration of the validity and amount of the Fund’s claim. 1 Merchants, however, did not seek *897 to compel arbitration, as was their right under the Federal Arbitration Act, 9 U.S.C. § 4, until it filed its counterclaim on January 6, 1988. Ultimately, nearly four and one-half years after Merchants’ request, the Fund formally initiated arbitration on May 19, 1988.

To date, Merchants have made no payments to the Fund. In this action, the Fund seeks payment of the delinquent withdrawal liability payments and interest. It also asks for liquidated damages and attorneys’ fees under 29 U.S.C. §§ 1451(e) and 1132(g)(2). In addition, the Fund seeks a declaratory judgment to the effect that Merchants’ requests for review and arbitration were not in accordance with the MPPAA.

As noted, Merchants, as counterclaim-ants, initially sought an order compelling the Fund to begin arbitration and in addition an order to make available to Merchants all the requested information. Merchants also seek attorneys’ fees and costs.

The pendency of arbitration renders the counterclaim prayer for an order to compel arbitration moot. Instead, Merchants now seek to have all remaining issues between the parties submitted to the arbitrator, including the scope of the arbitrable issues and the question whether Merchants must make interim payments.

III. RIGHT TO INTERIM PAYMENTS

Multiemployer pension plans are managed by boards of trustees who, under the MPPAA, unilaterally determine the withdrawal liability of an employer. 29 U.S.C. §§ 1382, 1391, and 1399(b)(1). The MPPAA further provides that an employer may, within ninety days of receiving notice of a withdrawal liability claim, request that the plan conduct an internal review of the claim. 29 U.S.C. § 1399(b)(2)(A).

Merchants contend they have not made interim payments because of the Fund’s refusal to respond to their requests for review and information, and “because there is strong reason to believe that the Fund’s ... claim is invalid.” The Fund, however, maintains that interim payments must be made by the employer regardless of any challenge to the validity or amount of the claim.

The weight of statutory and judicial authority supports the Fund’s position. Interim payments are mandated by the language of the MPPAA. The statute unequivocally requires that

Withdrawal liability shall be payable in accordance with the schedule set forth by the plan sponsor ... beginning no later than 60 days after the date of the demand notwithstanding any request for review or appeal of determinations of the amount of such liability or of the schedule.

29 U.S.C. § 1399(c)(2) (emphasis supplied).

The cases, in this District addressing the question of interim payments have held the statutory language to be an unambiguous mandate. See, e.g., Debreceni v. George Lamoureux & Co., 629 F.Supp. 598, 600-01 (D.Mass.1986) (Caffrey, J.) (notwithstanding employer’s request for review, it must begin payment of its withdrawal liability within sixty days); Debreceni v. Farer Transportation Co., No. 86-2622-S, slip op. at 2 (D.Mass. Jan. 8, 1987) (Skinner, J.) (ERISA requires an employer to make scheduled withdrawal payments when due “even if the employer disputes the Fund’s determination of withdrawal liability.”); Debreceni v. Barry & Foley Motor Transp., Inc., No. 86-2185-S, slip op. at 7 (D.Mass. Nov. 6, 1986) (Skinner, J.) (language of MPPAA is clear; it “unequivocally establishes the Company’s duty to make interim payments to the Fund pending resolution of the dispute.”-).

Moreover, there is considerable support for this position in the law of other Circuits. See, e.g., Marvin Hayes Lines, Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
740 F. Supp. 894, 1989 U.S. Dist. LEXIS 17083, 1989 WL 222472, Counsel Stack Legal Research, https://law.counselstack.com/opinion/debreceni-v-merchants-terminal-corp-mad-1989.