De Witt v. Liberty Leasing Company of Alaska

499 P.2d 599, 1972 Alas. LEXIS 276
CourtAlaska Supreme Court
DecidedJuly 28, 1972
Docket1638
StatusPublished
Cited by41 cases

This text of 499 P.2d 599 (De Witt v. Liberty Leasing Company of Alaska) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
De Witt v. Liberty Leasing Company of Alaska, 499 P.2d 599, 1972 Alas. LEXIS 276 (Ala. 1972).

Opinion

*600 OPINION

ERWIN, Justice.

This is an appeal from a denial of costs and attorney’s fees.

On Novermber 7, 1969, a construction contract was executed by the parties to this appeal under which appellant constructed a warehouse for appellee in Anchorage. After notification that the construction had been completed, appellee refused to tender final payment and, on May 19, 1970, filed suit against appellant seeking damages in excess of $3,000 for allegedly defective and incomplete performance. Appellant filed an answer denying any failure of performance on his part and counterclaimed for $23,649.71, an amount which represented the final payment due under the contract and compensation for certain extra work allegedly done at the request of appellee. In its answer to appellant’s counterclaim, appellee denied liability for extra work.

Lawsuits filed by several subcontractors were consolidated with the above suit. On the first day of trial it was stipulated that the sums claimed due by the subcontractors were valid and unpaid debts; thus the subcontractors did not participate further in the trial. Judgments, including awards for costs and attorney’s fees, were entered in favor of the subcontractors and against appellant.

Following a four-day nonjury trial, the trial court rendered a written opinion which contained its findings of fact and conclusions of law; almost all the disputed claims were resolved favorably to appellant. The court found that defects in the warehouse were the result of unsuitable fill provided by appellee and that appellant had repeatedly warned appellee of possible problems. The court therefore denied ap-pellee’s claim for damages and awarded appellant the amount owing under the contract ($8,627). The court also found that appellee had agreed to additional work made necessary by a change in the site of the warehouse. With the exception of two expenses totaling $4,800, which the court concluded would have also been incurred under the construction as originally planned, the court found that appellant was entitled to compensation for the extras claimed ($9,109.11). Finally,'with the exception of a $93.64 electric bill, the court rejected appellee’s claims for various bills it allegedly paid on behalf of appellant.

In summary, the court rendered judgment in favor of appellant for $17,736.11 plus interest while granting an offset to appellee for the $93.64 electric bill.

Regarding costs and attorney’s fees, the court stated in its opinion:

Under the circumstances here existing I am of the opinion that neither party should be entitled to costs or attorney’s fees, and I allow no costs or áttorney’s fees on either side.

Appellant subsequently filed a motion with the court for an award of costs and attorney’s fees. Appellee opposed the motion and a hearing was held. During the course of the hearing the court stated that neither party prevailed in the lawsuit, that appellee was wrong in not paying appellant and that appellant was wrong in not paying his subcontractors.

Under AS 09.60.010 1 and Civil Rule 54(d), 2 the prevailing party is entitled *601 to costs, including an award for attorney’s fees. 3 The determination of which party prevailed is committed to the discretion of the trial court 4 and is reviewable on appeal only for abuse. 5 In this case we have concluded that the trial court’s determination that neither party prevailed was “manifestly unreasonable;" 6 and as a result, its dis-allowance of costs and attorney’s fees constituted error.

In Buza v. Columbia Lumber Company, 395 P.2d 511, 514 (Alaska 1964), this court discussed the meaning of the term “prevailing party”:

The dictionary states that ‘Prevailing applies esp. to that which is predominant,’ and it has been established by case law that the prevailing party to a suit is the one who successfully prosecutes the action or successfully defends against it, prevailing on the main issue, even though not to the extent of the original contention. He is the one in whose favor the decision or verdict is rendered and the judgment entered, (footnotes omitted) 7

Applying this standard to the case at bar, appellant clearly prevailed in the litigation below. Appellant received a $17,736.11 judgment against appellee while suffering an offset of only $93.64. As we stated in Nordin Construction Company v. City of Nome, 489 P.2d 455, 474 (Alaska 1971), “[a] simple balancing of the recovery in favor of each party makes it clear that [appellant] was the prevailing party in this lawsuit . . . .” Moreover, appellant prevailed on most of the issues disputed at trial. 8

Appellee argues that even if appellant was the prevailing party, the trial court had discretion to disallow costs and attorney’s fees in order to “penalize” appellant. As previously noted, the apparent reason for the trial court’s ruling was that appellant had acted wrongfully in not paying his subcontractors. 9 In addition, appel-lee suggests that the court was motivated by a desire to encourage settlements where litigation is unreasonable. 10 As indicated above, the dispute with the subcontractors was resolved on the first day of the trial and could have been settled at any time by appellee including the subcontractors as co-payees on checks made payable to appellant. As long as appellee, however, contended that there were no sums due appellant, there was no means by which appellant could settle the litigation and secure the amounts to which he was justly entitled. Thus, neither line of argument advanced by appellee offers a legitimate basis for withholding costs and attorney’s fees in the case at bar. 11 In Preferred General *602 Agency of Alaska, Inc. v. Raffetto, 391 P. 2d 951, 954 (Alaska 1964), we stated:

The purpose of Civil Rule 82 in providing for the allowance of attorney’s fees is to partially compensate a prevailing party for the costs to which he has been put in the litigation in which he was involved. The rule was not designed to be used capriciously or arbitrarily, or as a vehicle for accomplishing any purpose other than providing compensation where it is justified. 12

This discussion is equally applicable to the award of other costs under Civil Rule 54(d). 13

Free access — add to your briefcase to read the full text and ask questions with AI

Related

RBG Bush Planes, LLC v. Alaska Public Offices Commission
361 P.3d 886 (Alaska Supreme Court, 2015)
Miller v. Clough
165 P.3d 594 (Alaska Supreme Court, 2007)
City of Kenai v. Friends of the Recreation Center, Inc.
129 P.3d 452 (Alaska Supreme Court, 2006)
Halloran v. State, Division of Elections
115 P.3d 547 (Alaska Supreme Court, 2005)
Monzingo v. Alaska Air Group, Inc.
112 P.3d 655 (Alaska Supreme Court, 2005)
Fletcher Hill, Inc. v. Crosbie
2005 VT 1 (Supreme Court of Vermont, 2005)
Matanuska Electric Ass'n v. Rewire the Board
36 P.3d 685 (Alaska Supreme Court, 2001)
State v. Johnson
958 P.2d 440 (Alaska Supreme Court, 1998)
Shepherd v. State, Department of Fish & Game
897 P.2d 33 (Alaska Supreme Court, 1995)
Feichtinger v. Conant
893 P.2d 1266 (Alaska Supreme Court, 1995)
Dennis I. Spencer Contractor, Inc. v. City of Aurora
884 P.2d 326 (Supreme Court of Colorado, 1994)
Knight v. American Guard & Alert, Inc.
714 P.2d 788 (Alaska Supreme Court, 1986)
Isaacson Structural Steel Co. v. Armco Steel Corp.
640 P.2d 812 (Alaska Supreme Court, 1982)
Lamoureaux v. Totem Ocean Trailer Express, Inc.
632 P.2d 539 (Alaska Supreme Court, 1981)
Ocean West Contractors, Inc. v. Halec Construction Co.
600 P.2d 1102 (Arizona Supreme Court, 1979)
Ferdinand v. City of Fairbanks
599 P.2d 122 (Alaska Supreme Court, 1979)
Tobeluk Ex Rel. Tobeluk v. Lind
589 P.2d 873 (Alaska Supreme Court, 1979)
Alaska State Bank v. General Insurance Co. of America
579 P.2d 1362 (Alaska Supreme Court, 1978)
Food Pantry, Ltd. v. Waikiki Business Plaza, Inc.
575 P.2d 869 (Hawaii Supreme Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
499 P.2d 599, 1972 Alas. LEXIS 276, Counsel Stack Legal Research, https://law.counselstack.com/opinion/de-witt-v-liberty-leasing-company-of-alaska-alaska-1972.