DCK North America, LLC v. Burns & Roe Services Corp.

218 F. Supp. 3d 465, 2016 WL 6441574, 2016 U.S. Dist. LEXIS 150223
CourtDistrict Court, W.D. Pennsylvania
DecidedOctober 31, 2016
DocketCivil Action No. 2:16-cv-00994
StatusPublished
Cited by4 cases

This text of 218 F. Supp. 3d 465 (DCK North America, LLC v. Burns & Roe Services Corp.) is published on Counsel Stack Legal Research, covering District Court, W.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DCK North America, LLC v. Burns & Roe Services Corp., 218 F. Supp. 3d 465, 2016 WL 6441574, 2016 U.S. Dist. LEXIS 150223 (W.D. Pa. 2016).

Opinion

OPINION

Mark R. Hornak, United States District Judge

This is an arbitration dispute in which the parties are currently litigating the question of where they should be litigating—in court or in arbitration. The parties agreed in writing to arbitrate certain disputes. DCK now takes the position that the parties’ arbitration provision does not apply to the claims in this case. For the following reasons, Burns and Roe’s Motion to Dismiss or Stay Pending Arbitration or Mediation (ECF No. 5) will be granted, this case will be stayed pending arbitration, and the parties will be ordered to arbitration in the manner they have agreed.

I. BACKGROUND

Plaintiff DCK North America, LLC (“DCK”) filed this action alleging, among other things, that Defendant Burns and Roe Services Corporation (“Burns and Roe”) breached its contractual obligation to compensate DCK for over eight million dollars ($8,000,000) of unpaid costs incurred during joint construction projects in Guantanamo Bay, Cuba. ECF No. 1-2. Burns and Roe timely removed the case to this Court from the Court of Common Pleas of Allegheny County, Pennsylvania on the basis of diversity jurisdiction. ECF No. 1. Before the Court is Burns and Roe’s Motion to Dismiss or Stay Pending Arbitration or Mediation. ECF No. 5. The parties fully briefed the issues and the Court heard oral argument on September 6, 2016. ECF Nos. 6, 6, 12, 13, 14, 20, 21, 22, 23.

The basic facts are undisputed. Eight years ago, DCK and Burns and Roe entered into a Joint Venture Agreement (“Agreement”) to bid on construction project contracts for the United States Navy at Guantanamo Bay, Cuba, and to perform such contracts should they be awarded the bids.1 ECF No. 1-2 at 4, 25. The Agreement essentially provides that DCK and Burns and Roe would front capital for the construction projects in equal amounts, with each holding a fifty percent interest, and likewise split any losses, costs, and liabilities down the middle. Id. If, for example, one joint venturer contributed capital or incurred losses in excess of fifty percent, the other joint venturer would then contribute additional capital to maintain the equal division of interests. Id.

DCK now alleges Burns and Roe shorted it over eight million dollars. Id. The shortfall, according to DCK, is based upon the parties’ respective monetary contributions for labor, manpower, and equipment. Id. DCK filed suit, and Burns and Roe subsequently filed its Motion to Compel Arbitration (ECF No. 5).

The parties’ Agreement contains the following arbitration provision:

Any controversy or claim arising out of or relating to this Agreement or the breach thereof which cannot be resolved in accordance with the foregoing processes while in the course of performance of the Contract(s) shall be settled by arbitration in accordance with the Construction Industry Arbitration Rules [469]*469of the American Arbitration Association and any award tendered shall be final and binding upon the parties hereto, and judgment on the award rendered by the Arbitrator or Arbitrators may be entered in any Court having jurisdiction thereof. Any controversy or claim arising after the completion of the Construction Contract has been performed shall be resolved in a court of law.

ECF No. 1-2 at 23-24. Neither party disputes the validity or the binding nature, generally speaking, of the arbitration provision.

The plain language of the Agreement appears to draw a line between disputes referable to arbitration and disputes that should be settled in court: Those disputes arising during performance of the Contracts) shall be settled by arbitration and those arising after completion of performance of the Construction Contract shall be settled in court. But at oral argument on Burns and Roe’s motion, it became quite clear that the parties have logical and reasonable positions in support of their differing views as to whether performance on the Contraet(s) or the Construction Contract is complete. The parties agree that physical construction of the projects—the labor—is complete. The parties also agree, though, that they have not submitted a certificate of completion to the Navy, nor has the Navy approved all of their construction work. Thus, it would appear that the arbitrability of the parties’ dispute thus turns on a mixed question of fact and contractual interpretation: whether performance of the Contract(s) and/or the Construction Contract was ‘complete’ when this dispute arose.

Upon closer scrutiny of the parties’ Agreement, the line of demarcation as to contract completion is anything but sharp. The Agreement defines the term “Contract(s)” to include several of the Navy contracts the parties bid on as part of their joint venture. ECF No. 1-2 at 10. It does not, however, provide a definition for what the parties refer to as “the Construction Contract.” Nor does it make clear what goalpost the parties contemplated for completion of performance on the Construction Contract such that arbitration would no longer be appropriate. The parties might, for example, have contemplated Contract completion as having occurred once the physical labor had been performed. They might have contemplated completion when the Navy approved the final buildouts. They might have contemplated completion when all outstanding payments had been received. Or the parties might not have contemplated this question at all, at least in terms of providing any definitional language in the Contract documents.

At the Court’s request, the parties submitted supplemental briefing addressing who must decide the question of when “after completion of the Construction Contract has been performed” occurs. ECF Nos. 22, 23. The parties also addressed whether a reference in the parties’ arbitration provision to the Construction Industry Arbitration Rules of the American Arbitration Association (hereinafter “AAA Rules” or “Rules”) incorporates those Rules into the provision, and, if so, whether such incorporation requires that the dispute be arbitrated in and of itself. Id. DCK contends this Court must decide the question presented here and argues (seemingly as a matter of law) that the parties’ dispute is not arbitrable under the Agreement. ECF No. 23. Burns and Roe contends an arbitrator must determine the issue of Contract completion and, beyond that, the dispute in any event falls within the arbitration provision. ECF No. 22.

II. LEGAL STANDARD

The United States Court of Appeals for the Third Circuit recently clarified the standards to be applied to motions to compel arbitration, identifying the circum[470]*470stances under which district courts should apply the standard for a motion to dismiss, as provided by Rule 12(b)(6) of the Federal Rules of Civil Procedure, and those under which they should apply the summary judgment standard found in Rule 56. See Guidotti v. Legal Helpers Debt Resolution, L.L.C., 716 F.3d 764, 773-76 (3d Cir. 2013). With respect to the Rule 12(b)(6) standard, the court held:

Where the affirmative defense of arbi-trability of claims is apparent on the face of a complaint (or documents relied upon in the complaint), the FAA would favor resolving a motion to compel arbitration under a motion to dismiss standard without the inherent delay of discovery.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
218 F. Supp. 3d 465, 2016 WL 6441574, 2016 U.S. Dist. LEXIS 150223, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dck-north-america-llc-v-burns-roe-services-corp-pawd-2016.