Davis v. Southern Cal. Edison Co. CA3/7

236 Cal. App. 4th 619, 186 Cal. Rptr. 3d 587, 2015 Cal. App. LEXIS 374
CourtCalifornia Court of Appeal
DecidedApril 7, 2015
DocketB256737
StatusUnpublished
Cited by27 cases

This text of 236 Cal. App. 4th 619 (Davis v. Southern Cal. Edison Co. CA3/7) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Davis v. Southern Cal. Edison Co. CA3/7, 236 Cal. App. 4th 619, 186 Cal. Rptr. 3d 587, 2015 Cal. App. LEXIS 374 (Cal. Ct. App. 2015).

Opinion

Opinion

FEUER, J. *

INTRODUCTION

This action arises from plaintiff David Davis’s applications to Southern California Edison Company (SCE) to interconnect solar generating systems on property he owned to the SCE electricity distribution system (electricity grid) to generate electricity for use on those properties and to sell to SCE. Davis contends that SCE, in processing his applications, violated SCE’s tariff rule 21 (Rule 21), tariff rule 16 (Rule 16), the California Renewable Energy Small Tariff (CREST) program, and the net energy metering (NEM) program. 1

SCE filed a demurrer on the ground that California’s Public Utilities Commission (PUC) had exclusive jurisdiction to resolve the dispute and, therefore, the superior court lacked jurisdiction to hear Davis’s claims. At issue on appeal is the potential conflict between Public Utilities Code section 1759, 2 which limits jurisdiction to review an order of the PUC to the Court of Appeal and the Supreme Court, and section 2106, which grants jurisdiction to the superior court to hear actions for damages against a public utility that violates California law. The trial court sustained SCE’s demurrer without leave to amend, entered judgment against Davis, and dismissed the case without prejudice. 3

*623 We conclude that the trial court correctly held that the PUC had exclusive jurisdiction over Davis’s claims under our Supreme Court’s holding in San Diego Gas & Electric Co. v. Superior Court (1996) 13 Cal.4th 893, 917-918 [55 Cal.Rptr.2d 724, 920 P.2d 669] (Covalt) 4 because adjudication of Davis’s claims would “ ‘hinder or frustrate the commission’s declared supervisory and regulatory policies’ ” with respect to interconnection of solar generating facilities under Rule 21, Rule 16 and the CREST and NEM programs.

While Davis’s remedies before the PUC may be more limited than those available in the trial court, to the extent Davis has viable damage claims following the PUC’s adjudication of his administrative complaints currently pending before the PUC, those claims will only become ripe for filing in the trial court once the PUC reaches a final decision. (See Schell v. Southern Cal. Edison Co. (1988) 204 Cal.App.3d 1039, 1047 [251 Cal.Rptr. 667].)

We affirm.

FACTUAL AND PROCEDURAL BACKGROUND 5

A. SCE’s Tariffs Governing Solar Generating Facilities 6

1. SCE’s Tariff Rule 21

*624 All residential solar generating facilities seeking to interconnect to SCE’s electricity grid must comply with Rule 21. 7 Rule 21 governs all aspects of interconnection, including the interconnection application submission process, the process for reviewing interconnection applications, the assignment of a generator’s position in the interconnection queue, the engineering review details, the cost responsibilities of the generators and SCE, and the design and operation requirements for the generating facility. Rule 21 applies both to solar generators that intend to sell power to SCE under the CREST program and to solar generators that intend to use their generation to offset their own electricity usage under the NEM program.

Rule 21 provides deadlines for the interconnection approval process. A threshold determination must be made as to whether the project is eligible for the “fast track.” Under section E.2.b.i, Rule 21 provides that “[n]on-Exporting and Net Energy Metered [(NEM)] Generating Facilities are eligible for Fast Track evaluation regardless of the Gross Nameplate Rating of the proposed Generating Facility.” For an “Exporting Generating Facility,” fast track is available under certain conditions set forth in section E.2.b.i. Section F.l.b provides for a “Fast Track Review” for projects “that do not require Detailed Study.”

Rule 21 provides deadlines for (1) determination of whether an application is complete, (2) completion of an initial engineering review once the application is complete, and (3) completion of SCE’s review of the application. We discuss these deadlines in more detail below.

Rule 21 provides in section K.1 for resolution of disputes: “In addition to the informal procedures for timeline-related disputes set out in Section F. 1 .d, the following procedures will apply for disputes arising from this Rule: [¶] . . . [¶] The Commission shall have initial jurisdiction to interpret, add, delete or modify any provision of this Rule or of any agreements entered into between Distribution Provider and Applicant or Producer to implement this tariff . . . and to resolve disputes regarding Distribution Provider’s [(SCE’s)] performance of its obligations under Commission-jurisdictional tariffs, the applicable agreements, and requirements related to the interconnection of Applicant’s or Producer’s Generating Facility or Interconnection Facilities pursuant to this Rule.” Section K.2.c provides procedures for parties to resolve disputes, including through mediation, and further, “[a]t any time, either Party may file a formal complaint before the Commission . . . .”

*625 2. The CREST Solar Generation Program

Section 399.20, subdivision (a), declares the “intent of the Legislature to encourage electrical generation from eligible renewable energy resources.” SCE filed the CREST program with the PUC pursuant to subdivision (c), which requires utilities, including SCE, to file with the PUC a standard tariff providing for the purchase of renewable energy from electric generating facilities. The PUC has approved the CREST program.

To be eligible for CREST, an SCE customer must own and operate an eligible solar generating facility that “[h]as an effective capacity of not more than 1.5 MW [(megawatts)] and is located on the premises owned or under the control of the customer.” Under section 399.20, subdivision (f), SCE was required to make CREST available to solar generating facilities “on a first-come-first-served basis,” assigning each generating facility a queue position based on the date it entered into a power purchase agreement with SCE. SCE was required to keep CREST open for eligible generators until SCE met its proportionate share of a statewide cap of 750 megawatts. Effective July 24, 2013, SCE met its obligation to purchase the required amount of eligible generation under CREST, and the CREST program closed to new customers.

3. The NEM Solar Generation Program

SCE established the NEM program pursuant to section 2827. NEM allows eligible customers who install renewable generation at their homes or businesses to offset their consumption of electricity by the amount of electricity they generate. (§ 2827, subd.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lenior v. Pacific Gas and Electric Co. CA3
California Court of Appeal, 2025
Hirdman v. Charter Communications, LLC
California Court of Appeal, 2025
Arax v. Thomas CA5
California Court of Appeal, 2024
Moreira v. New Rez CA4/1
California Court of Appeal, 2023
Johnson v. Johnson CA3
California Court of Appeal, 2023
L.A. Police Protective League v. City of L.A.
California Court of Appeal, 2022
McLeod v. BTIG CA1/1
California Court of Appeal, 2021
Bullseye Telecom, Inc. v. Cal. P.U.C.
California Court of Appeal, 2021
Coston v. Stanislaus County CA5
California Court of Appeal, 2021
In re SDG&E Consolidated Cases
S.D. California, 2021
Geveran Investments v. Irell & Manella CA4/3
California Court of Appeal, 2021
RGC Gaslamp v. Ehmcke Sheet Metal Co.
California Court of Appeal, 2020
Lane v. Bell
California Court of Appeal, 2018
Goncharov v. Uber Techs., Inc.
229 Cal. Rptr. 3d 3 (California Court of Appeals, 5th District, 2018)
Goncharov v. Uber Technologies, Inc.
California Court of Appeal, 2018
Panoche Energy Center, LLC v. Pacific Gas & Electric Co.
1 Cal. App. 5th 68 (California Court of Appeal, 2016)
Rosen v. Uber Technologies, Inc.
164 F. Supp. 3d 1165 (N.D. California, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
236 Cal. App. 4th 619, 186 Cal. Rptr. 3d 587, 2015 Cal. App. LEXIS 374, Counsel Stack Legal Research, https://law.counselstack.com/opinion/davis-v-southern-cal-edison-co-ca37-calctapp-2015.