Davis v. Baugh Industrial Contractors, Inc.

150 P.3d 545, 159 Wash. 2d 413
CourtWashington Supreme Court
DecidedJanuary 18, 2007
DocketNo. 76696-7
StatusPublished
Cited by42 cases

This text of 150 P.3d 545 (Davis v. Baugh Industrial Contractors, Inc.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Davis v. Baugh Industrial Contractors, Inc., 150 P.3d 545, 159 Wash. 2d 413 (Wash. 2007).

Opinions

¶1 — We are asked whether the common law doctrine of completion and acceptance, which shields contractors from liability for negligent work after that work has been completed and accepted by the property owner, bars this suit against Baugh Industrial Contractors, Inc., for negligent construction of a pipeline. Finding that this doctrine is outmoded, incorrect, and harmful, we now join the 37 states that have abandoned it. We reverse the superior court order granting summary judgment and remand for further proceedings.

Chambers, J.

FACTS AND PROCEDURAL HISTORY

¶2 On October 12,1992, Baugh entered into a contract to build a network of subterranean pipes for a processing facility belonging to Glacier Northwest. In turn, Baugh hired E.J. Rody & Sons, Inc. (Rody), to install the on-site utilities and underground piping for the facility. In the [416]*416course of its work, Rody assembled and installed high density polyethylene pipes and buried the piping underground. Rody had exclusive control over the installation. The project was substantially completed in April 1997, and Glacier accepted the work. Shortly thereafter, Glacier began operating the facility.

¶3 In December 2000, after observing that a pond had formed, Glacier suspected a leak in one of the underground pipes. Alan Davis was the foreman of the crew assigned by Glacier to excavate the area and find the leak. While the pipeline was still covered with several feet of dirt, Davis entered the excavated hole to try to pinpoint the leak. Tragically, several cement blocks, weighing between 1,500 and 1,800 pounds each, fell into the hole when a nearby wall collapsed. One of the blocks crushed Davis’ chest and pinned him to the ground. Davis later died of his injuries. Evidence suggested that one of the high density polyethylene pipes, which had a useful life of up to 100 years, had failed. This might have been because of a gouge or dent in the pipe.

¶4 Tami Davis, Alan’s daughter and personal representative of his estate, filed this negligence suit against Baugh among others. The trial court granted summary judgment for Baugh on the ground that the completion and acceptance doctrine relieved Baugh of liability for negligence after the work was completed and accepted by the property owner. The trial court also struck portions of a declaration of Davis’ expert. On direct appeal from the superior court, Davis argues that the trial court erred. We agree and reverse.

STANDARD OF REVIEW

¶5 Trial court rulings in conjunction with a motion for summary judgment are reviewed de novo. Folsom v. Burger King, 135 Wn.2d 658, 663, 958 P.2d 301 (1998).

[417]*417ANALYSIS

|6 Under the completion and acceptance doctrine, once an independent contractor finishes work on a project and the work has been accepted by the owner, the contractor is no longer liable for injuries to third parties, even if the work was negligently performed. Historically, after completion and acceptance, the risk of liability for the project belonged solely to the property owner. This court has not addressed this doctrine in over 40 years and, in the meantime, 37 states have rejected it. See Emmanuel S. Tipon, Annotation, Modern Status of Rules Regarding Tort Liability of Building or Construction Contractor for Injury or Damage to Third Person Occurring After Completion and Acceptance of Work; “Completed and Accepted” Rule, 74 A.L.R.5th 523, 557-61 (1999); Peters v. Forster, 804 N.E.2d 736, 741 (Ind. 2004). Under the modern, Restatement approach, a builder or construction contractor is liable for injury or damage to a third person as a result of negligent work, even after completion and acceptance of that work, when it was reasonably foreseeable that a third person would be injured due to that negligence. Restatement (Second) of Torts §§ 385, 394, 396 (1965).1

¶7 We join the vast majority of our sister states and abandon the ancient completion and acceptance doctrine. See In re Rights to Use of Waters of Stranger Creek, 77 Wn.2d 649, 653, 466 P.2d 508 (1970). We find it does not accord with currently accepted principles of liability because it was grounded in the long abandoned privity rule that a negligent builder or seller of an article was liable to [418]*418no one but the purchaser. See, e.g., Thornton v. Dow, 60 Wash. 622, 635-36, 111 P. 899 (1910) (explaining that a contractor is liable only under the contract); MacPherson v. Buick Motor Co., 217 N.Y. 382, 397, 111 N.E. 1050 (1916). This approach to analyzing liability was first rejected in MacPherson. There, Judge (and later Justice) Benjamin N. Cardozo’s watershed opinion explained that

[w]e have put aside the notion that the duty to safeguard life and limb, when the consequences of negligence may be foreseen, grows out of contract and nothing else. We have put the source of the obligation where it ought to be. We have put its source in the law.

MacPherson, 217 N.Y. at 390. Cardozo has prevailed, and the privity requirement in tort law has been abandoned not just in Washington but in all United States jurisdictions in the decades since MacPherson. See Stuart v. Coldwell Banker Commercial Group, Inc., 109 Wn.2d 406, 418, 745 P.2d 1284 (1987).

¶8 A second, oft-cited rationale for this doctrine is the theory that the owner’s negligence in failing to remedy a dangerous condition upon the land is an intervening cause, which breaks the chain of causation and cuts off the contractor’s liability. Thornton, 60 Wash, at 636. This rationale fails as well because Washington has long since abandoned this theory of proximate cause, sometimes called the “last wrongdoer” rule. See, e.g.,Maltman v. Sauer, 84 Wn.2d 975, 982, 530 P.2d 254 (1975); Olson v. Gill Home Inv. Co., 58 Wash. 151, 157-58, 108 P. 140 (1910); see also Prosser and Keeton on the Law of Torts 304 (W. Page Keeton ed., 5th ed. 1984) (“The risk created by the defendant may include the intervention of the foreseeable negligence of others.”). An intervening cause breaks the chain of causation only if the intervening event is so unexpected that it falls outside the realm of the reasonably foreseeable. Maltman, 84 Wn.2d at 982. Whether an intervening act breaks the chain of causation is a question for the trier of fact. Id.

[419]*419¶9 The completion and acceptance doctrine is also grounded in the assumption that if owners of land inspect and accept the work, the owner should be responsible for any defects in that accepted work. See Pierce v. ALSO Architects, PS, 270 Mont. 97, 890 P.2d 1254, 1262 (1995). While this assumption may have been well founded in the mists of history, it can no longer be justified. Id. Today, wood and metal have been replaced with laminates, composites, and aggregates. Glue has been replaced with molecularly altered adhesives.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. City of Sunnyside
Washington Supreme Court, 2024
Animal Legal Def. Fund v. Olympic Game Farm, Inc.
533 P.3d 1170 (Washington Supreme Court, 2023)
Linda Welch, V. Air & Liquid Systems Corporation
Court of Appeals of Washington, 2023
Erin Bayne, V. Carleton Farm Inc.
Court of Appeals of Washington, 2023
Pacheco v. United States
Washington Supreme Court, 2022
Bangerter v. Hat Island Cmty. Ass'n
504 P.3d 813 (Washington Supreme Court, 2022)
Fischer v. United States
E.D. Michigan, 2022
State v. Anderson
498 P.3d 903 (Washington Supreme Court, 2021)
John Frederick Flynn, Iii v. Pierce County
Court of Appeals of Washington, 2021
Keodalah v. Allstate Ins. Co.
449 P.3d 1040 (Washington Supreme Court, 2019)
Swank v. Valley Christian School
Washington Supreme Court, 2017
State of Washington v. Dennis Wayne Jussila
392 P.3d 1108 (Court of Appeals of Washington, 2017)
Carrera Ex Rel. Department of Labor & Industries v. Olmstead
383 P.3d 563 (Court of Appeals of Washington, 2016)
State v. Otton
374 P.3d 1108 (Washington Supreme Court, 2016)
Angel Garcia-titla, Flores, V Sfc Homes Llc
Court of Appeals of Washington, 2016

Cite This Page — Counsel Stack

Bluebook (online)
150 P.3d 545, 159 Wash. 2d 413, Counsel Stack Legal Research, https://law.counselstack.com/opinion/davis-v-baugh-industrial-contractors-inc-wash-2007.