Dart Mechanical Corp. v. XL Specialty Insurance

593 F. Supp. 2d 464, 2008 U.S. Dist. LEXIS 106614
CourtDistrict Court, E.D. New York
DecidedSeptember 30, 2008
Docket1:06-cv-02457
StatusPublished

This text of 593 F. Supp. 2d 464 (Dart Mechanical Corp. v. XL Specialty Insurance) is published on Counsel Stack Legal Research, covering District Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dart Mechanical Corp. v. XL Specialty Insurance, 593 F. Supp. 2d 464, 2008 U.S. Dist. LEXIS 106614 (E.D.N.Y. 2008).

Opinion

MEMORANDUM AND ORDER

VITALIANO, District Judge.

Plaintiffs Dart Mechanical Corporation (“Dart”) and Franco Belli Plumbing and Heating & Sons, Inc. (“Franco Belli”) (together the “plaintiffs”) brought these actions against Defendant XL Specialty Insurance (“XL”) to assert claims arising out of construction contracts. XL has now moved for partial summary judgment pursuant to Federal Rule of Civil Procedure 56, seeking dismissal of Dart’s third and sixth causes of action and Franco Belli’s fourth and fifth causes of action. For the reasons set forth below, XL’s motions are granted.

Background

XL’s summary judgment motions target the claims of Dart and Franco Belli for *466 “impact and delay” 1 and unjust enrichment. Unless otherwise noted, the facts relevant to those claims are, in material part, undisputed.

On November 12, 1999, the New York City Transit Authority (“NYCTA”) entered into a contract with Lipco Electrical Corporation (“Lipco”), as general contractor, to construct the Coliseum Bus Depot Superstructure in the Bronx (hereinafter the “General Contract”). The General Contract specified a start date of November 12, 1999 and a “substantial completion” date of July 12, 2001. In turn, Lip-co subcontracted with Dart and Franco Belli, both New York corporations, to perform mechanical and plumbing work. Lipco’s written agreement with Dart for $6.7 million covered heating, ventilation, and air conditioning work. Franco Belli entered into a written agreement with Lipco to perform domestic water, drainage, piping, gas, and fuel piping work for the sum of $8,968,500. These written agreements (together the “Subcontracts”), while obviously differing in their respective work specifications, contained identical language incorporation and dispute resolution provisions and also required plaintiffs to complete their work in accordance with the July 12, 2001 deadline.

On September 30, 1999, Lipco obtained a performance and payment bond from a surety, CGU Insurance Company (“CGU”). In January 2002, Lipco assigned its interests and rights under the General Contract to CGU, with CGU assuming Lipco’s performance obligations. During the course of the project, XL, a Delaware corporation, became the successor in interest to CGU, thereby assuming CGU’s rights and obligations under the General Contract.

As work progressed, plaintiffs received partial payment for their performance. Critically, in order to receive payment, plaintiffs were required to provide to XL signed “Affidavits and Releases”. These documents contained clauses “releasing] Lipco, Lipco’s sureties and the Owners of the Project from all claims whatsoever arising out of or relating to the subcontractor or purchase order, up to the date of this payment.” It is undisputed that on some, but not all, of these releases, plaintiffs crossed out this language before signing and submitting the payment documentation to XL.

On December 27, 2001, NYCTA notified Lipco that it would be held in default for (1) “unnecessarily and unreasonably delaying the performance of the project by consistently undermanning the project,” (2) “failing to allocate sufficient financial resources to complete the project,” and (3) “lack of adherence to the [project] schedule” unless such default was rectified to NYCTA’s satisfaction by January 8, 2002. On January 11, 2002, counsel for the NYC-TA informed counsel both for XL and Lip-co that NYCTA would no longer accept Lipco as the general contractor for the project and that Lipco must either “assign” the General Contract to XL or the NYCTA would terminate the General Contract for default and insist on completion by XL.

In less than three weeks, through an assignment agreement, XL assumed the role of General Contractor with respect to *467 all relevant contracts. In executing the assignment, Lipco and XL released NYC-TA from all prior claims arising out of the general contract, including the pending claims alleged by plaintiffs. Dart and Franco Belli contend that this release was executed without their knowledge or consent.

In attempting to complete the job, XL retained Tishman Construction Corporation (“Tishman”) as construction manager on March 11, 2002. XL also re-hired Lip-co to perform the electrical work necessary for the project. The NYCTA declared “substantial completion” on August 27, 2003. This was over two years after the July 12, 2001 date specified in the General Contract.

Plaintiffs allege that this substantial delay in completion was caused by XL’s subsequent re-hiring of Lipco and the hiring of Tishman. Plaintiffs further assert that Lipco’s improper performance of electrical work and Tishman’s gross mismanagement of the project caused increased costs and damages amounting to $846,081.82 for Dart and $2,552,206 for Franco Belli. Furthermore, plaintiffs claim that they relied upon the completion date specified in the General Contract in entering into the Subcontracts. Obversely, Dart claims XL was unjustly enriched by its valuable labor, material, and/or equipment to the tune of $1,511,721.88; Franco Belli similarly asserts it is owed $3,378,673.69 by XL.

Dart and XL met on several occasions between March 2003 and February 2006, to negotiate a settlement of Dart’s claims for “impact and delay” and for unpaid extra work. Dart communicated its intent to file these claims in a letter to XL’s agent, Cashin, Spinelli, Heller, & Feretti Corp. (“Cashin”), dated March 19, 2003. In a letter to Dart’s attorney, XL’s attorney acknowledged that Dart had “advised XL that it has a ‘large dollar’ delay claim against XL which XL disputes.” Additionally, XL and Dart met on July 29, 2004, where “Dart indicated that it was in the process of preparing and submitting a delay damage claim.” XL’s attorneys advised Dart not to submit delay claims since such claims were barred by the “Affidavits and Releases” that Dart had executed upon receiving past payments from the surety.

On April 17, 2006, plaintiffs filed separate actions against XL, asserting claims for 1) breach of contract, 2) unjust enrichment; 3) impact and delay costs and 4) extra costs of equipment rental and warranties. XL filed the instant motions for partial summary judgment, seeking only to dismiss the claims for impact and delay and unjust enrichment on the grounds that 1) plaintiffs failed to comply with notice obligations set forth in the General Contract that were incorporated by reference into the Subcontracts, 2) other incorporated provisions of the General Contract barred recovery of damages for delay claims 3) all the relevant contracts provide for a dispute resolution procedure with which plaintiffs failed to comply and 4) plaintiffs released their claims when they signed the “Affidavits and Releases”. XL also argues that each unjust enrichment claim should be dismissed because plaintiffs’ claims arise out of valid contracts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Anthony Sutera v. Schering Corporation
73 F.3d 13 (Second Circuit, 1995)
Jeffreys v. City of New York
426 F.3d 549 (Second Circuit, 2005)
Cox v. NAP Constr. Co., Inc.
891 N.E.2d 271 (New York Court of Appeals, 2008)
Thomas Crimmins Contracting Co. v. City of New York
542 N.E.2d 1097 (New York Court of Appeals, 1989)
Corinno Civetta Construction Corp. v. City of New York
493 N.E.2d 905 (New York Court of Appeals, 1986)
Clark-Fitzpatrick, Inc. v. Long Island Rail Road
516 N.E.2d 190 (New York Court of Appeals, 1987)
Westinghouse Electric Corp. v. New York City Transit Authority
623 N.E.2d 531 (New York Court of Appeals, 1993)
Bussanich v. 310 East 55th Street Tenants
282 A.D.2d 243 (Appellate Division of the Supreme Court of New York, 2001)
Scotto v. Almenas
143 F.3d 105 (Second Circuit, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
593 F. Supp. 2d 464, 2008 U.S. Dist. LEXIS 106614, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dart-mechanical-corp-v-xl-specialty-insurance-nyed-2008.