This text of 374 A.2d 1081 (Darien Education Assn. v. Board of Education) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Darien Education Assn. v. Board of Education, 374 A.2d 1081, 172 Conn. 434, 1977 Conn. LEXIS 912 (Colo. 1977).

Opinion

Loiselle, J.

This is an. appeal from a judgment of the Superior Court vacating an arbitration award on the ground that the arbitrator exceeded his power in rendering the award.

The controversy arose when Coleman Alexa, a teacher in the Darien school system, received an evaluation of “4” on a scale of a possible “5” for the 1973-74 school year. 1 He appealed from this rating in a procedure provided for in agreements between the defendant Darien board of education, hereinafter the board, and the plaintiff Darien Education Association, hereinafter the association. The grievance went to arbitration. With the consent of the parties, the arbitrator formulated the question submitted thus: “Was Coleman Alexa properly evaluated in Level 4 on June 11, 1974? If not, to what remedy is he entitled?” The arbitrator’s award stated: “Coleman Alexa was properly evaluated in Level 4 on June 11, 1974. The grievance is denied.”

The court found that an agreement between the board and the association, which was made on March 1, 1974, required that a form “B” be filled out as part of the teacher evaluation procedure, and *436 that one was not filled ont for Alexa. The board and the association waived the nse of another form because of the shortage of time to complete the 1973-74 evaluations, but they did not waive form B. The court found that the arbitrator had excused the failure of the evaluator to make out a form B for Alexa because the evaluation had to be completed in such a short time, and that the arbitrator was without authority to alter or modify the terms of the contract. The court vacated the award on the ground that the arbitrator had exceeded his power in rendering the award.

The award made no mention of form B; it is clear that the court must have examined the arbitrator’s opinion in order to have discovered that the arbitrator excused its absence. The defendant claims that this was error, that a court may examine a memorandum by the arbitrator only when there is some question raised by the lack of conformity between the question submitted to arbitration and the arbitrator’s award, as in Costello Construction Co. v. Teamsters Local 559,167 Conn. 315, 355 A.2d 279; International Union v. Fafnir Bearing Co., 151 Conn. 650, 201 A.2d 656; and Niles-Bement-Pond Co. v. Amalgamated Local 405, 140 Conn. 32, 97 A.2d 898.

The defendant relies on the language in United Electrical Radio & Machine Workers v. Union Mfg. Co., 145 Conn. 285, 289, 141 A.2d 479: “The law does not recognize the right to question an award made clearly within the terms of the submission . . . on the ground that the . . . [arbitrator was] powerless to make it.” That ruling was superseded, insofar as arbitration involving industry affecting interstate commerce is concerned, by United Steel *437 workers v. Enterprise Wheel & Car Corporation, 363 U.S. 593, 80 S. Ct. 1358, 4 L. Ed. 2d 1424, as recognized by this court in Hudson Wire Co. v. Winsted Brass Workers Union, 150 Conn. 546, 553, 191 A.2d 557. 2

The Enterprise Wheel & Car decision concerned a case in which the arbitrator’s opinion was ambiguous. The award might have been based either solely on legislation, in which case the arbitrator would have exceeded his authority, or on the agreement between the parties, as interpreted with the aid of law. The United States Supreme Court held (p. 598) that “[a] mere ambiguity in the opinion . . . which permits the inference that the arbitrator may have exceeded his authority, is not a reason for refusing to enforce the award.” In dictum, however, the court stated that an arbitrator’s “award is legitimate only so long as it draws its essence from the collective bargaining agreement. When the arbitrator’s words manifest an infidelity to this obligation, courts have no choice but to refuse enforcement of this award.” Id., 597.

Whether or not the award concerns an industry affecting interstate commerce, it is appropriate to follow the lead of Enterprise Wheel & Car. If the memorandum of an arbitrator revealed that he had reached his decision by consulting a ourja board, *438 snrely it should not suffice that the award conformed to the submission. It, however, defeats the purpose of arbitration, which is to avoid litigation, to permit awards to be set aside for mere errors on the ground that errors are “outside the powers” of the arbitrators. “[U]nless his memorandum patently shows an infidelity to his obligation, the result reached by the award, and not the memorandum, controls.” Hudson Wire Co. v. Winsted Brass Workers Union, supra, 553.

In this case, the opinion of the arbitrator shows that he considered the association’s claim that “the failure to make out a Form B - Report of Formal Observation - for Alexa, constitutes a failure of due process, and this in itself is justification for granting him a 5 rating.” He then gave three reasons for not adopting this argument: (1) There was no showing that the omission of the form was harmful to Alexa; (2) Alexa waived any procedural defect by not raising the issue in a timely fashion; and (3) the pressure of time excused the absence of the form in this case.

An arbitrator need not even make specific mention of the claim of a party, and may find that certain requirements of a contract may be waived. Von Langendorff v. Riordan, 147 Conn. 524, 163 A.2d 100; see also Waterbury Board of Education v. Waterbury Teachers Assn., 168 Conn. 54, 62, 357 A.2d 466; Gary Excavating, Inc. v. North Haven, 164 Conn. 119, 123-24, 318 A.2d 84.

This court has held that it is error to vacate an award even when it is shown that the arbitrators considered matters outside the contract, if it is not also shown that they relied on those matters in making the award. New Britain Machine Co. v. *439 Lodge 1021, 143 Conn.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCann v. Department of Environmental Protection
952 A.2d 43 (Supreme Court of Connecticut, 2008)
Alexson v. Foss
887 A.2d 872 (Supreme Court of Connecticut, 2006)
Blakeslee Arpaia Chapman, Inc. v. Department of Transportation
873 A.2d 155 (Supreme Court of Connecticut, 2005)
Industrial Risk Insurers v. Hartford Steam Boiler Inspection & Insurance
868 A.2d 47 (Supreme Court of Connecticut, 2005)
Local 391, Council 4, AFSCME v. Department of Correction
817 A.2d 1279 (Connecticut Appellate Court, 2003)
Afscme, Council 4, Local 1566 v. Milford, No. Cv01-0073138s (Dec. 16, 2002)
2002 Conn. Super. Ct. 16136 (Connecticut Superior Court, 2002)
Griffin Hospital v. Teamsters, Local 677, No. Cv 01-0076382 (Dec. 6, 2002)
2002 Conn. Super. Ct. 15438 (Connecticut Superior Court, 2002)
Stratford Police Un. v. Town of Stratford, No. Cv 01 0453114 (Nov. 7, 2001)
2001 Conn. Super. Ct. 14993 (Connecticut Superior Court, 2001)
Seymour B. of E. v. Seymour Ed. Assn., No. Cv00 07 10 43s (Jan. 18, 2001)
2001 Conn. Super. Ct. 1276 (Connecticut Superior Court, 2001)
Tunxis Recylcing Opt. v. Automated Cont., No. Cv 98-0486403s (Sep. 11, 1998)
1998 Conn. Super. Ct. 10178 (Connecticut Superior Court, 1998)
Afscme, Council 4 v. City of Bridgeport, No. Cv-96-0563092 S (Dec. 4, 1997)
1997 Conn. Super. Ct. 13896 (Connecticut Superior Court, 1997)
Garrity v. McCaskey
612 A.2d 742 (Supreme Court of Connecticut, 1992)
Bennett v. Meader
545 A.2d 553 (Supreme Court of Connecticut, 1988)
Board of Education v. Local 818, Council 4
502 A.2d 426 (Connecticut Appellate Court, 1985)
City of New Britain v. Connecticut State Board of Mediation & Arbitration
424 A.2d 263 (Supreme Court of Connecticut, 1979)
Ramos Iron Works, Inc. v. Franklin Construction Co.
392 A.2d 461 (Supreme Court of Connecticut, 1978)
Meyers v. Lakeridge Development Co.
376 A.2d 1105 (Supreme Court of Connecticut, 1977)
Conte v. City of Norwalk
376 A.2d 412 (Supreme Court of Connecticut, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
374 A.2d 1081, 172 Conn. 434, 1977 Conn. LEXIS 912, Counsel Stack Legal Research, https://law.counselstack.com/opinion/darien-education-assn-v-board-of-education-conn-1977.