Norwich Roman Catholic Diocesan Corp. v. Southern New England Contracting Co.

325 A.2d 274, 164 Conn. 472, 1973 Conn. LEXIS 946
CourtSupreme Court of Connecticut
DecidedMarch 8, 1973
StatusPublished
Cited by29 cases

This text of 325 A.2d 274 (Norwich Roman Catholic Diocesan Corp. v. Southern New England Contracting Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Norwich Roman Catholic Diocesan Corp. v. Southern New England Contracting Co., 325 A.2d 274, 164 Conn. 472, 1973 Conn. LEXIS 946 (Colo. 1973).

Opinion

Bogdanski, J.

On April 4, 1966, the defendant Southern New England Contracting Company, hereinafter called the contractor, entered into a written contract with the plaintiff, Norwich Roman Catholic Diocesan Corporation, hereinafter called the diocese, for the construction of a school building, including site work and a sanitary system. The contract provided for arbitration of any claims or disputes in accordance with the “Standard Form of Arbitration Procedure of the American Institute of Architects.” That procedure specified that a party wishing to arbitrate should designate whether the arbitration should be administered under the above quoted authority and, if administered by the American Arbitration Association, that its rules should govern. The contractor applied to the American Arbitration Association for arbitration. Accordingly, three arbitrators were appointed and they held extensive hearings on the matters submitted.

The following dispute was submitted for arbitration: (1) The diocese refused to classify as “mass rock” 23,372 cubic yards of excavated material which *474 was “in fact” mass rock and to pay for it at the agreed unit cost of $6.60 per cubic yard, for which the contractor claimed $154,255.20; (2) the diocese refused to pay for extra costs, labor, and materials necessitated, by undisclosed and excessive water conditions, for which the contractor claimed $23,822.70; and (3) the diocese failed to make a final payment under the contract, exclusive of extra work, in the amount of $58,589.35. In addition, the contractor sought interest of 6 percent on the amount found due. Item three was abandoned in the arbitration proceedings. The arbitrators awarded the contractor (1) $134,607 for the excavation of 20,395 cubic yards of mass rock at $6.60 per cubic yard; (2) $20,577.77 for undisclosed and excessive water conditions; and (3) interest of 6 percent on the $20,577.77 award from November 13, 1967, to the date of the award. The diocese applied to the Superior Court in New London County to vacate the award. The contractor, in turn, applied for confirmation of the award. The referee to whom the case was referred, acting as the court, rendered judgment confirming the award. From that judgment the diocese has appealed to this court.

The diocese’s first assignment of error, challenging the finding, has not been briefed and is treated as abandoned. State v. Grayton, 163 Conn. 104, 109, 302 A.2d 246, cert. denied, 409 U.S. 1045, 93 S. Ct. 542, 34 L. Ed. 2d 495; State v. Benson, 153 Conn. 209, 217, 214 A.2d 903. Its remaining assignments of error are directed to the referee’s conclusions and his rulings on evidence and claims of law.

The referee found that the arbitrators were given broad powers under the rules of the American Arbitration Association, that § 30 of the rules provided that the arbitrators should be the judges of the ad *475 missibility of evidence and that conformity to the legal rules of evidence was not necessary, and that § 42 of the rules provided that the arbitrators might grant any remedy or relief which they deem just and equitable and within the terms of the parties’ agreement.

The referee concluded that the submission defined the authority of the arbitrators, that the arbitrators were not asked to interpret the contract, that the award conformed to the submission, and that it was not the function of the referee to review the evidence considered by the arbitrators to determine the validity of the award.

Our courts favor arbitration as a means of settling differences and uphold the finality of arbitration awards except where an award clearly falls within the proscriptions of § 52-418 of the General Statutes. International Union v. Fafnir Bearing Co., 151 Conn. 650, 653, 201 A.2d 656; United Electrical Radio & Machine Workers v. Union Mfg. Co., 145 Conn. 285, 288, 141 A.2d 479. That section provides as follows: “Vacating award. In any of the following eases the superior court ... or, when said court is not in session, any judge thereof, shall make an order vacating the award upon the application of any party to the arbitration: (a) If the award has been procured by corruption, fraud or undue means; (b) if there has been evident partiality or corruption on the part of the arbitrators or either of them; (e) if the arbitrators have been guilty of misconduct in refusing to postpone the hearing upon sufficient cause shown or in refusing to hear evidence pertinent and material to the controversy or of any other action by which the rights of any party have been prejudiced; (d) if the arbitrators have exceeded their powers or so imper *476 fectly executed them that a mutual, final and definite award upon the subject matter submitted was not made.”

In seeking to vacate the award in this case under subsection (d) of the statute, the diocese contends that the arbitrators exceeded their powers in refusing to interpret paragraphs of the contract specifications concerning definitions of “mass rock” and “cross sectioning.” The diocese also asserts that when it offered these documents as exhibits the referee improperly sustained the contractor’s objection to them.

Charges that arbitrators have acted fraudulently or corruptly, or have been guilty of misconduct in refusing to hear pertinent evidence or of any other action prejudicial to the rights of any party are not cognizable under § 52-418 (d) and are properly brought under other subsections of § 52-418. As the diocese has made no claim under any subsection of § 52-418 other than § 52-418 (d), our review must be limited to the question whether the arbitrators exceeded their powers. “Every reasonable presumption and intendment will be made in favor of the award and of the arbitrators’ acts and proceedings. Hence, the burden rests on the party attacking the award to produce evidence sufficient to invalidate or avoid it.” Gary Excavating Co. v. North Haven, 160 Conn. 411, 413, 279 A.2d 543. We do not believe that the diocese has met its burden of proving that the arbitrators have exceeded their powers within the meaning of § 52-418 (d), nor do we believe that the referee, in determining whether they exceeded their powers, erroneously excluded the contract specifications from evidence.

Arbitration is a creature of contract and the parties themselves, by the agreement of submission, *477 define the powers of the arbitrators. Connecticut Union of Telephone Workers, Inc. v. Southern New England Telephone Co., 148 Conn. 192, 197, 169 A.2d 646; Niles-Bement-Pond Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gerald Metals, LLC v. Davidson
D. Connecticut, 2021
Seymour B. of E. v. Seymour Ed. Assn., No. Cv00 07 10 43s (Jan. 18, 2001)
2001 Conn. Super. Ct. 1276 (Connecticut Superior Court, 2001)
Town of South Windsor v. South Windsor Police Union Local 1480
750 A.2d 465 (Connecticut Appellate Court, 2000)
Clairol, Inc. v. Enertrac Corp.
690 A.2d 418 (Connecticut Appellate Court, 1997)
Metropolitan District Commission v. American Federation of State
654 A.2d 384 (Connecticut Appellate Court, 1995)
Cashman v. Sullivan & Donegan P.C.
578 A.2d 167 (Connecticut Appellate Court, 1990)
North Haven Ass'n of Educational Support Staff v. Board of Education
550 A.2d 1077 (Supreme Court of Connecticut, 1988)
Town of East Hartford v. East Hartford Municipal Employees Union, Inc.
525 A.2d 112 (Connecticut Appellate Court, 1987)
O & G/O'Connell Joint Venture v. Chase Family Ltd. Partnership No. 3
523 A.2d 1271 (Supreme Court of Connecticut, 1987)
Board of Education v. Local 818, Council 4
502 A.2d 426 (Connecticut Appellate Court, 1985)
Bic Pen Corporation v. Local No. 134
440 A.2d 774 (Supreme Court of Connecticut, 1981)
City of Bridgeport v. Bridgeport Police Local 1159
438 A.2d 1171 (Supreme Court of Connecticut, 1981)
Milford Employees Ass'n v. City of Milford
427 A.2d 859 (Supreme Court of Connecticut, 1980)
Eder Bros., Inc. v. International Brotherhood
416 A.2d 702 (Connecticut Superior Court, 1980)
Allstate Insurance v. Semple
416 A.2d 1211 (Connecticut Superior Court, 1979)
State v. Onofrio
425 A.2d 560 (Supreme Court of Connecticut, 1979)
City of New Britain v. Connecticut State Board of Mediation & Arbitration
424 A.2d 263 (Supreme Court of Connecticut, 1979)
Saphir v. Neustadt
413 A.2d 843 (Supreme Court of Connecticut, 1979)
City of Waterbury v. Waterbury Police Union
407 A.2d 1013 (Supreme Court of Connecticut, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
325 A.2d 274, 164 Conn. 472, 1973 Conn. LEXIS 946, Counsel Stack Legal Research, https://law.counselstack.com/opinion/norwich-roman-catholic-diocesan-corp-v-southern-new-england-contracting-conn-1973.