Clairol, Inc. v. Enertrac Corp.

690 A.2d 418, 44 Conn. App. 506, 1997 Conn. App. LEXIS 101
CourtConnecticut Appellate Court
DecidedMarch 18, 1997
Docket15402
StatusPublished
Cited by8 cases

This text of 690 A.2d 418 (Clairol, Inc. v. Enertrac Corp.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clairol, Inc. v. Enertrac Corp., 690 A.2d 418, 44 Conn. App. 506, 1997 Conn. App. LEXIS 101 (Colo. Ct. App. 1997).

Opinion

GLASS, J.

The principal issue in this case is whether it was improper for the trial court to grant the application of the plaintiff, Clairol, Inc. (Clairol), to vacate an arbitration award in favor of the defendant, Enertrac Corporation (Enertrac), pursuant to General Statutes § 52-418 (a) (3).1 The application was granted on the basis of a finding that Clairol had been denied a full and fair hearing before the arbitration panel. Enertrac claims (1) that the trial court did not correctly apply the presumption that arbitration awards should be sustained and that arbitration proceedings were properly conducted, and (2) that the trial court improperly failed to seek an articulation or explanation from the arbitration panel. We reverse the judgment of the trial court.

The facts relevant to the disposition of the issues are as follows. On December 7, 1988, Clairol entered into a written construction contract with Enertrac for Enertrac to design and construct a cogeneration facility for use by Clairol in its manufacturing business in Stamford. Disputes ensued concerning performance by both parties under the agreement. Pursuant to article 10.1 of the contract, “[c]laims, disputes and other matters [508]*508in question between the parties . . . shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association . . . .” Article 10.3 of the agreement provides that “[t]he award rendered by arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction.”

On November 19,1990, Clairol submitted the disputes between the parties to arbitration. Enertrac filed a counterclaim. The arbitration hearings commenced on May 4, 1992. Thereafter, more than twenty hearings were held or scheduled over a period in excess of two years.

During the arbitration hearings, Enertrac introduced the testimony of two witnesses. Enertrac’s first witness was Robert Reilly, Enertrac’s president who was involved with the business aspects of the project. A second witness for Enertrac was George Thompson, an engineer and Enertrac’s designated expert.

Thompson’s direct examination was concluded, but cross-examination was deferred to a later date. In a letter to the American Arbitration Association, counsel for Enertrac stated, inter alia: “Should Enertrac not be able to make Mr. Thompson available in order to conclude these hearings, then Mr. Thompson’s direct testimony should be stricken.”

Clairol requested that the arbitration panel strike the direct testimony of Thompson and dismiss the counterclaim of Enertrac, both of which requests the arbitration panel formally denied on January 10,1994. Additionally, on March 24, 1994, the panel decided that it would disallow Enertrac’s request to withdraw Thompson’s testimony voluntarily. The spokesperson for the panel stated: “With respect to the voluntary withdrawal of Mr. Thompson’s testimony, as you know in our arbitration proceedings here, we are the ultimate final decision [509]*509makers with respect to relevancy and materiality, and just how much [weight], if any, is given to any exhibits or oral documentary or oral testimony that comes before the panel. We are going to approach the testimony of Mr. Thompson in the same fashion. Whatever relevancy or whatever [weight] the direct examination may have; it may be zero, it may be negative. That is the way we are going to approach it. So we are going to deny your voluntary request to strike that testimony. And we will assign it our own [weight] or relevancy or materiality in our ultimate deliberations on a decision.”

At the hearing on May 16, 1994, Clairol renewed its requests to strike the direct testimony of Thompson and to dismiss Enertrac’s counterclaim. These requests were considered and the spokesperson for the panel stated that the panel would “take a very hard look at assigning the appropriate weight” to Thompson’s testimony, “ranging from no weight whatsoever to possibly negative weight.” The panel also indicated again that it was not going to dismiss Enertrac’s counterclaim. Clairol then decided to introduce testimony and exhibits to rebut Thompson’s testimony. Subsequently, the hearings closed.

On March 27, 1995, the arbitration panel issued a unanimous written award. The panel awarded each party a small portion of its claim and assigned nearly all of the administrative costs of the arbitration to Clairol. The award also provided that Clairol would be liable to Enertrac for all costs that Enertrac owed to the manufacturer of the cogeneration equipment.

On March 31, 1995, counsel for Clairol sent a letter to the arbitration association requesting a clarification by the arbitrators as to the basis for their decision, including an explanation of the underlying award and how the arbitrators reached their decision on Clairol’s claim and Enertrac’s counterclaim. The arbitration [510]*510association responded by letter dated April 4, 1995, in which it refused Clairors request to provide clarification without first obtaining the consent of both parties to reinstate the authority of the arbitrators. The letter also indicated that “[a]n arbitration award is considered final when rendered and the arbitrator’s authority ceases thereafter.” In a letter to the arbitration association dated April 10, 1995, Reilly, Enertrac’s president, refused to consent to the reinstatement of the authority of the arbitrators.

On April 24, 1995, Clairol filed an application in the trial court to vacate the award based on the claims that the arbitrators had denied Clairol’s right to cross-examine Thompson, had refused to vacate or deny Enertrac’s counterclaim because of Enertrac’s failure to produce Thompson for cross-examination, and had issued an award not supported by the complete testimony of Thompson, which testimony was pertinent and material to the resolution of the parties’ controversy. On October 25,1995, the trial court granted the application to vacate the award. The trial court found that Enertrac “does not contest that Thompson was not made available for cross-examination. Furthermore, [Clairol] has provided a ruling of the arbitrators denying [Clairol’s] motion to strike Thompson’s direct testimony. [Clairol] was deprived of its absolute right of cross-examination and a full and fair hearing.”

Enertrac filed a motion for articulation on January 18, 1996. This motion was denied. A motion for review was filed with the Appellate Court on February 23,1996. This court granted the motion for review, but denied the relief requested.

Enertrac first claims that the trial court did not correctly apply the presumption that arbitration awards should be sustained and that the arbitration proceedings were properly conducted. We have been loath to [511]*511intervene judicially and to interfere with the parties’ voluntary agreement to settle their disputes by arbitration. O & G/O’Connell Joint Venture v. Chase Family Ltd. Partnership No. 3, 203 Conn. 133, 145, 523 A.2d 1271 (1987). Because arbitration is such a valuable and commendable tool in alternative dispute resolution, judicial intervention is the exception rather than the rule. See id.

“We have stated repeatedly that judicial review of arbitration awards is limited in scope .... Metropolitan District Commission v. AFSCME, Council 4, 35 Conn. App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stutz v. Shepard
901 A.2d 33 (Supreme Court of Connecticut, 2006)
Scalzi v. Hesse, No. Cv96 0056386s (Feb. 21, 2002)
2002 Conn. Super. Ct. 1911 (Connecticut Superior Court, 2002)
Greenwich Oper. Fund v. Crompton Corp., No. Cv 01 0186067 S (Jan. 18, 2002)
2002 Conn. Super. Ct. 680 (Connecticut Superior Court, 2002)
Town of South Windsor v. South Windsor Police Union Local 1480
750 A.2d 465 (Connecticut Appellate Court, 2000)
McCann v. Abrahamson, No. Cv 97 63721 S (Sep. 2, 1997)
1997 Conn. Super. Ct. 9379 (Connecticut Superior Court, 1997)
Town of Wallingford v. Wallingford Police Union Local 1570
696 A.2d 1030 (Connecticut Appellate Court, 1997)
Clairol, Inc. v. Enertrac Corp.
695 A.2d 537 (Supreme Court of Connecticut, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
690 A.2d 418, 44 Conn. App. 506, 1997 Conn. App. LEXIS 101, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clairol-inc-v-enertrac-corp-connappct-1997.