CVN Group, Inc. v. Delgado

47 S.W.3d 157, 2001 WL 491150
CourtCourt of Appeals of Texas
DecidedJune 14, 2001
Docket03-00-00386-CV
StatusPublished
Cited by7 cases

This text of 47 S.W.3d 157 (CVN Group, Inc. v. Delgado) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CVN Group, Inc. v. Delgado, 47 S.W.3d 157, 2001 WL 491150 (Tex. Ct. App. 2001).

Opinion

KIDD, Justice.

Appellant, CVN Group, Inc. (“CVN”), brought an action seeking confirmation of an arbitration award, in which CVN was awarded damages and declared to have a valid mechanic’s and materialman’s lien on real property owned by Enrique and Marjorie Delgado. The trial court reduced the damages award and declared the lien invalid. On appeal, CVN challenges the trial court’s authority to modify the arbitrator’s damage award and vacate the granting of the hen. We will affirm the decision of the trial court declaring the hen invalid. We will reverse and render on that portion of the trial court’s judgment modifying the damages awarded by the arbitrator.

*160 BACKGROUND

In August 1997, CVN contracted to design a house for the Delgados that the Delgados intended to make their homestead. In October 1997, the parties contracted for CVN to oversee the construction of that house. The October 1997 agreement (the “construction contract”) contained numerous provisions detailing the parties’ rights and responsibilities, and concluded with a broad arbitration agreement. 1

On July 27, 1998, the Delgados requested that CVN cease work. Taking this to be a material breach of the construction contract, CVN demanded arbitration. The arbitration proceeded as a documents-only arbitration; neither side presented any oral testimony. At arbitration, the dispute between the parties focused on the various compensation clauses within the construction contract. The arbitrator returned a monetary-damages award in CVN’s favor and declared that CVN possessed constitutional and statutory mechanic’s and mate-rialman’s liens on the Delgados’ real property for the full amount due. 2 In the award, the arbitrator specifically listed the types of claims asserted and the corresponding amounts awarded, but no specific reasons were given explaining how the amounts were calculated. For example, the builder’s fee was set at $122,250, but the arbitrator did not disclose the formula by which he arrived at that amount. Nor did the arbitrator explain his reasons for determining that a valid lien existed on the Delgados’ homestead. Because this proceeding was a documents-only arbitration, we do not have a transcript of an arbitration hearing on which we may rely in examining the award. The builder’s fee, lien, post-award collection fees, and interest are all at issue here. The remainder of the award was confirmed by the trial court and is not challenged on appeal.

Clause 21.1 of the construction contract contains the following language: “The Owner shall pay to Project Manager a fee of eight percent (8%) multiplied by either (a) the cost of the work or (b) the appraisal value of the completed project as determined by the lender, whichever is higher.” A subsequent provision states that the Delgados acknowledge that the eight-percent fee was discounted from CVN’s full fee of fifteen percent. Following that acknowledgment, a penalty clause states that the fee shall be raised to fifteen percent if the Delgados are late on any of their interim payments. The arbitrator did not disclose the base amount or percentage he used in calculating the builder’s fee of $122,250. The arbitration clause gave the arbitrator broad authority to interpret the contract, using all the documentary evidence presented to him, and calculate the fees owed to CVN. Absent a mistake of fact or law that results in fraud or a great and manifest wrong and injustice, a court may not set aside an arbitrator’s award. Nuno v. Pulido, 946 S.W.2d 448, 452 (Tex.App.—Corpus Christi 1997, no writ).

*161 Both parties had the right to request findings of fact and conclusions of law from the arbitrator. Neither party did so. Therefore, the record lacks any indication of the arbitrator’s reasons or calculations. However, following the confirmation hearing, the trial court did make findings of fact and conclusions of law. As the trial court noted, it appears that the arbitrator used the appraised value of the Delgados’ home, rather than the cost of improvements, in determining the amount of the builder’s fee. 3 The trial court found no evidence had been produced at arbitration that demonstrated the appraisal value was “determined by the lender,” as the construction contract required. Accordingly, the trial court modified the award using the $425,000 cost of improvements as the basis for calculating the builder’s fee. The trial court also found that there was no evidence of any late interim payments by the Delgados. Accordingly, the trial court concluded that the arbitrator overstepped his authority in awarding the fifteen-percent builder’s fee. Additionally, the court found the penalty provision, which raised the builder’s fee from eight to fifteen percent, constituted a charge, or a contract for the forbearance or the detention of money in excess of the amount allowable by law and was, therefore, usurious and unenforceable.

Based on these findings, the trial court concluded the builder’s fee of $122,250 awarded by the arbitrator should be reduced to $34,000, which is eight percent of $425,000. The parties did not challenge the arbitrator’s findings regarding other fees owed to CVN or credits owed to the Delgados for payments previously made. Taking into account the unchallenged fees and credits and adding the reduced builder’s fee, the trial court entered a judgment for CVN in the amount of $22,775 plus $973 for arbitration costs.

DISCUSSION

CVN raises eight points of error. Points one and two complain of the trial court’s reduction of the damages awarded to CVN by the arbitrator. Points seven and eight seek post-award collection fees and interest. Points three through six advance CVN’s argument that the trial court erred in declaring that the Delgados had established the property as their homestead and that the lien claimed by CVN was invalid and not subject to foreclosure.

Grounds to Review Arbitration Award

We initially note that Texas law favors the arbitration of disputes. Brazoria County v. Knutson, 142 Tex. 172, 176 S.W.2d 740, 743 (1943). An arbitrator’s award is entitled to great deference in a court of law lest disappointed litigants seek to overturn every unfavorable arbitration award in court. Daniewicz v. Thermo Instrument Sys., Inc., 992 S.W.2d 713, 716 (Tex.App.—Austin 1999, pet. denied). Accordingly, every reasonable presumption will be indulged to uphold the arbitration proceeding. Id.

Arbitrators have traditionally enjoyed broad authority to fashion remedies *162 designed to fit the specific issues presented to them under an arbitration agreement. Id. at 718. A mere mistake of fact or law is insufficient to set aside the arbitration award. J.J. Gregory Gourmet Servs., Inc. v. Antone’s Import Co., 927 S.W.2d 31

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cavazos v. Munoz
305 B.R. 661 (S.D. Texas, 2004)
CVN Group, Inc. v. Delgado
95 S.W.3d 234 (Texas Supreme Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
47 S.W.3d 157, 2001 WL 491150, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cvn-group-inc-v-delgado-texapp-2001.