Riha v. Smulcer

843 S.W.2d 289, 1992 Tex. App. LEXIS 3041, 1992 WL 360630
CourtCourt of Appeals of Texas
DecidedDecember 10, 1992
DocketC14-91-01293-CV
StatusPublished
Cited by50 cases

This text of 843 S.W.2d 289 (Riha v. Smulcer) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Riha v. Smulcer, 843 S.W.2d 289, 1992 Tex. App. LEXIS 3041, 1992 WL 360630 (Tex. Ct. App. 1992).

Opinion

OPINION

JUNELL, Justice.

Appellant appeals from the trial court’s judgment modifying and correcting an Award of Arbitrator(s). We find the trial court erred by modifying the arbitrator’s award and reverse and render.

Appellant asserts nine points of error. In his first point of error, appellant argues the trial court erred by modifying and correcting the arbitrator’s award. In his fourth point of error, appellant complains the trial court erred by failing to confirm the award and enter judgment in accordance with the arbitrator’s award. In the remaining points of error, appellant attacks the trial court’s findings on grounds of no evidence, insufficient evidence and findings against the great weight and preponderance of the evidence. Because we agree with appellant’s first and fourth points of error and reverse and render on these grounds, we do not address appellant’s remaining points.

J.L. Riha, individually and d/b/a Riha Construction Co. (Riha), and Ronnie J. Smulcer and Janice S. Smulcer (Smulcers) entered into a construction contract whereby Riha, a general contractor, agreed to build a residential home for the Smulcers.

Disputes arose between the parties. The Smulcers brought suit against Riha for breach of contract, violation of trust fund doctrine and breach of fiduciary duty, conversion, fraud, negligent misrepresentation, negligence, statutory fraud, and breach of express and implied warranties. Riha filed a counter-claim against the Smulcers for the balance owing under the construction contract, payment for extra work performed, foreclosure on the mechanic’s lien Riha had placed on the property, damages for misrepresentations and legal fraud, attorney’s fees, and interest. As required by the terms of the construction contract, the district court submitted the case to arbitration.

After three days of hearings, the arbitrator made the following award:

Ronnie J. Smulcer and Janice S. Smulcer (“SMULCERS”) shall pay to J.L. Riha, individually and d/b/a Riha Construction Company (RIHA) the sum total of THIRTY-FIVE THOUSAND ONE HUNDRED TWENTY-FIVE DOLLARS AND SIXTY-FIVE CENTS ($35,125.65) BROKEN DOWN AS FOLLOWS:
REMAINDER OF CONTRACT .$10,125.65 CHANGES TO CONTRACT, ADDITIONAL MATERIALS & LABOR. 25,000.00
TOTAL $35,125.65
*291 Payment of the $35,125.65 shall be made to RIHA no later than thirty (30) days from the date of the arbitrator’s signature on this award.
“RIHA” shall release lien against the property upon payment of said monies; and shall pay amount due to Wicke Electric; and shall pay for saw blade.
The “RIHA” claim for rental payments is denied. The “SMULCERS” claim for interest rate damages is denied. Claims for slander, liable (sic), legal fraud, or deceptive business practices are denied. Stenographic record shall be paid by party who hired the stenographer. Each party shall be responsible for their own legal fees.
This award is in full settlement of all claims and counterclaims brought before this arbitration.

The Smulcers filed an application to Modify or Correct Arbitration Award, or Alternatively, to Vacate Award in the district court. After hearing arguments and reviewing the transcript from the arbitration hearings, the trial court entered the following judgment:

Remainder of Contract.$10,125.65 Changes to contract, additional materials and labor.25,000.00
Total $35,125.65
Payments and/or credits as stipulated by Riha.$36,715.07
Ronnie J. Smulcer and Janice S. Smulcer (Smulcers) shall have and recover from J.L. Riha, individually and D/B/A Riha Construction Company (Riha) the sum total of ONE THOUSAND FIVE HUNDRED AND EIGHTY-NINE AND 42/100 DOLLARS ($1,589.42) payable within thirty (30) days from entry of judgment by the Court in this cause. IT IS THEREFORE ORDERED, ADJUDGED AND DECREED THAT the Award of Arbitrator(s), as modified and corrected, is hereby CONFIRMED and judgment is entered thereon as follows:
I. Smulcer shall have judgment against J.L. Riha, individually, and D/B/A Riha Construction Company in the amount of ONE THOUSAND FIVE HUNDRED
AND EIGHTY-NINE AND 42/100 DOLr LARS ($1,589.42).
2. Riha shall release the lien against the property within thirty (30) days from the date of this judgment.
3. Riha shall pay any and all sums due Wicke Electric and shall pay for the saw blade for Wicke Electric.
4. Riha’s claims for rental payments is denied.
5. Smulcer’s claim for interest rate damages is denied.
6. All claims by both parties for slander, libel, legal fraud, and/or deceptive business practices are denied.
7. Cost of stenographic record shall be paid by the party incurring same.
8. Each party shall.pay their own costs and attorney’s fees.
9. Any other claim not expressly granted is denied.

In effect, the arbitrator awarded Riha judgment for $35,125.65. The trial court’s modification and correction judgment ordered Riha to pay the Smulcers $1,589.42. The trial court, in entering its judgment concentrated on credits totalling $36,-715.07. The Smulcers contend the credits eoflsist of off-sets and monies they paid to Riha or to his sub-contractors. The trial court subtracted the total amount of the credits from Riha’s award of $35,125.65. The Smulcers argue the arbitrator did not subtract the credits from the judgment he awarded Riha because the credits were never contested by the parties.

The Smulcers advanced this same argument to the arbitrator after he rendered his award on October 19, 1990. On November 2, 1990, the Smulcers filed an Application for Clarification of Arbitration Award with the American Arbitration Association. The Smulcers detailed the credits in the application. They also stated in the application that the arbitrator’s award was silent as to the credits, the credits should be added to the amounts previously paid by the Smul-cers, the amounts paid by the Smulcers exceeded the entire amount awarded Riha and therefore, Riha owed the Smulcers $2,817.07. The application requested the arbitrator’s award be clarified and Riha be *292 ordered to pay the Smulcers $2,817.07. Riha countered the award was clear and the Smulcers were seeking additional credits as the credits had already been considered by the arbitrator in making his award. On November 19, 1990, the arbitrator responded by letter to the American Arbitration Association:

I find no reason to change or explain the findings in this matter. They stand as previously disclosed.

On December 2, 1990, the Regional Director for the American Arbitration Association notified the parties that:

Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sutey Oil v. Monroe's High Country
2022 MT 50 (Montana Supreme Court, 2022)
Mary E. Ewing v. ACT Catastrophe-Texas L.C.
375 S.W.3d 545 (Court of Appeals of Texas, 2012)
Barton v. FASHION GLASS AND MIRROR, LTD.
321 S.W.3d 641 (Court of Appeals of Texas, 2010)
East Texas Salt Water Disposal Co. v. Werline
307 S.W.3d 267 (Texas Supreme Court, 2010)
Werline v. East Texas Salt Water Disposal Co.
209 S.W.3d 888 (Court of Appeals of Texas, 2007)
Baker Hughes Oilfield Operations, Inc. v. Hennig Production Co., Inc.
164 S.W.3d 438 (Court of Appeals of Texas, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
843 S.W.2d 289, 1992 Tex. App. LEXIS 3041, 1992 WL 360630, Counsel Stack Legal Research, https://law.counselstack.com/opinion/riha-v-smulcer-texapp-1992.