Casa Del Mar Association, Inc. v. Williams & Thomas, L.P. D/B/A Jamail Construction

476 S.W.3d 96, 2015 Tex. App. LEXIS 9227, 2015 WL 5109746
Court of Appeals of Texas·Decided August 31, 2015·No. NO. 14-14-00046-CV·Published·Cited by 8 cases

Opinion

OPINION

Kem Thompson Frost, Chief Justice

A landowner appeals the confirmation of an arbitration award issued after the arbitration of its claims agaihst a construction contractor. According to the landowner, the trial court should have vacated the award based on the arbitration panel’s gross mistake and manifest disregard of the law. We conclude that manifest disregard of the law is not a potential basis for vacating the award and that the landowner did not show that the award is tainted with such gross mistake as would imply bad faith and failure to exercise honest judgment. We affirm the trial court’s order.

*98 I. Factual and PROCEDURAL BACKGROUND

Appellant Casa del Mar Association, Inc. (“Casa del Mar”) contracted with appellee Williams & Thomas, L.P. d/b/a Jamail Construction (“Jamail”) for‘the construction of certain improvements at a condominium complex owned by Casa del Mar. Disputes arose between the parties regarding alleged defects' in Jamail’s work. Casa del Mar initiated an arbitration proceeding and asserted claims against Ja-mail. When the'arbitration panel conducted the arbitration hearing in Houston, Casa del Mar was asserting claims against Jamail for (1) breach of contract, (2) breach of express warranty, (3) breach of the “implied warranty of good" and workmanlike conduct,” (4) negligence, and (5) negligent misrepresentation.

The arbitration panel issued a “reasoned award,” in which it explained the reasons for its rulings. According to the award, Casa del Mar complained of “staining on the Hardi-Plank exterior of the building,” and all parties agreed that this staining “is being caused by minerals contained in water that is leaking from the balconies behind the Hardi-Plank wall exterior and then between the horizontal planks onto the surface ... thereby causing efflorescent stains.” In the award,- the panel also stated as follows:

Casa sought and obtained opinions from at least three ‘experts’ as to what was causing the staining, an appropriate repair methodology, and the cost to implement a repair protocol. As a part of this investigation destructive testing was performed on 3 balconies out of the 234. Expert reports along with photographs and exhibits were issued. Mainly based on Expert reports, Casa contends that the following conditions found by the experts- are ■ construction defects and therefore breaches of the contract:
1. “Fishmouths” in the waterproofing membrane
2. “Reverse laps” in the waterproofing membrane
3. Lack of sealant at door thresholds
4. One ply of waterproofing as opposed to two
Even assuming that each of the four items were found on a[t] least one occasion during the destructive testing, the Panel finds that none of the conditions were shown as causing.br contributing to the staining of the walls. .Farther the Panel finds that these conditions may ■ well evidence a failure to perform the work in a good and workmanlike manner; however, taken all together they do not arise to a “material breach of contract” as that term is used under Texas construction law (which would therefore not afford Casa a monetary remedy).

After explaining why the panel concluded that Casa del Mar could not recover the $1,395,216 in damages ■ sought, the panel explained the reasons why it was awarding $24,490.20 to Casa del Mar:

After consideration of all the credible evidence and the legal doctrines of betterment and economic waste, the Panel is. of the opinion that the proper “fix” should be to clean the outside of the wall and to apply an elastrometric paint. The best estimate of the cost to perform this work is an estimate [that] includes a total amount of $81,634 for painting.
Unfortunately for this Panel the allocation of responsibility between the designer/Owner and the contractor is a major issue. Both testifying experts stated that the cause of the -stains were both construction and design problems. Complicating the matter- further is the fact that the balconies were constructed based on a mock up that was approved by the Owner’s representative. The Panel believes that the main sources of *99 water leaving the balconies is thru areas in which there are no eiid dams and thru the outside galvanized metal frame that evidently was not caulked.
The Panel ascribes 30% of the damage amount to Jamail for failure to caulk the seams in the outside' metal frame and 70% to the Owner who agreed to construction per the mock up and presumably received a price reduction.

The panel awarded Casa del Mar $24,490.20, thirty percent of $81,634, and concluded that each party should bear its own attorney’s fees and costs. The panel also stated that all claims sounding in tort were denied based on the economic loss rule. Casa del Mar filed -a “motion to correct” in the arbitration proceeding, arguing that the panel erred because (1) the panel awarded Casa del Mar a recovery on the breach-of-contract claim, but did not award Casa del Mar any attorney’s fees or costs under Chapter 38 of the Texas Civil Practice and Remedies Code; and (2) the panel applied percentages of responsibility under Chapter 33 of the Texas Civil Practice and Remedies Code to Casa del Mar’s breach-of-contract claim (hereinafter collectively “Alleged Legal Errors”). Casa del Mar asserted that it should recover its attorney’s fees, costs, and all of the $81,634. The arbitration panel denied Casa del Mar’s motion.

Casa del Mar filed a motion to vacate the arbitration award in Galveston County District Court. The district court signed an agreed order transferring venue to Harris County, and the case was transferred to the trial court below. Jamail filed a response in opposition to the motion to vacate, and moved to confirm the award. The trial court granted the motion to confirm and denied the motion to vacate. Casa del Mar now challenges those rulings.

II. Issues and Analysis.

Á. Did the trial court err in denying Casa del Mar’s motion to vacate and granting the motion to confirm?

In its first issue, Casa del Mar asserts that the trial court erred in denying Casa del Mar’s motion to vacate and granting Jamail’s motion to confirm. Casa del Mar argues that the arbitration panel’s Alleged Legal Errors constitute gross mistake and manifest disregard of the law and that the trial court erred in not vacating the award on these grounds.

Jamail asserts a number of reasons why it contends we' should affirm the trial court’s order. For the purposes of this appeal we presume, without, deciding, as follows: (1) the motion to vacate was timely and notice of the motion was served on Jamail or its attorney within three months after the award was filed or delivered; (2) Casa del Mar has challenged on appeal every independent basis on which the trial court could have denied the motion to vacate; (3) the Federal Arbitration Act (“Federal Act”) does not preempt the Texas Arbitration Act (“Texas Act”) and Texas common law as to the possible grounds for vacating the award; and (4) the Texas Arbitration Act does not preempt all common law grounds for vacating the.award.

Free access — add to your briefcase to read the full text and ask questions with AI

Casa Del Mar Association, Inc. v. Williams & Thomas, L.P. D/B/A Jamail Construction, 476 S.W.3d 96, 2015 Tex. App. LEXIS 9227, 2015 WL 5109746 (Tex. Ct. App. 2015).

476 S.W.3d 96 (Casa Del Mar Association, Inc. v. Williams & Thomas, L.P. D/B/A Jamail Construction) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related