CPM of America, LLC v. Roberto Gonzalez

CourtCourt of Appeals of Texas
DecidedOctober 31, 2024
Docket14-23-00720-CV
StatusPublished

This text of CPM of America, LLC v. Roberto Gonzalez (CPM of America, LLC v. Roberto Gonzalez) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CPM of America, LLC v. Roberto Gonzalez, (Tex. Ct. App. 2024).

Opinion

Affirmed as Modified and Opinion filed October 31, 2024.

In The

Fourteenth Court of Appeals

NO. 14-23-00720-CV

CPM OF AMERICA, LLC, Appellant V.

ROBERTO GONZALEZ, Appellee

On Appeal from the 234th District Court Harris County, Texas Trial Court Cause No. 2018-34883

OPINION

Three issues are presented in this appeal: the first two challenge the confirmation of an arbitration award, and the third challenges the trial court’s decision to grant additional attorney’s fees expended in pursuit of the award’s enforcement. We overrule the first two issues and affirm the portion of the trial court’s judgment confirming the award. But we sustain the third issue, modify the judgment to delete the award of additional attorney’s fees, and affirm the judgment as so modified. BACKGROUND

Roberto Gonzalez purchased a home from CPM of America, LLC. The home was newly constructed and covered by a written warranty.

Shortly after the purchase, Gonzalez discovered many problems with the home, including leaking pipes and other water-related issues. Gonzalez made written claims on the warranty. When those claims went unresolved, Gonzalez submitted them to arbitration, pursuant to a clause under the warranty. He also filed a petition in the trial court against CPM and two individuals, alleging that CPM had fraudulently transferred property to the individuals to thwart the collection of any arbitration award.

During the arbitration proceeding, Gonzalez presented one claim for breach of warranty, and a second claim for violating the DTPA. The arbitrator made findings in favor of Gonzalez on both of his claims and awarded him more than $121,000 in damages, costs, and attorney’s fees. The arbitrator also ordered CPM to pay Gonzalez within thirty days of the award.

Following the expiration of that thirty days, Gonzalez filed an amended petition in the trial court, alleging that CPM had not complied with the award. Gonzalez sought confirmation of the award, plus an additional amount of attorney’s fees arising out of the enforcement of the award.

Gonzalez moved for a partial summary judgment on his confirmation application and on his request for an additional amount of attorney’s fees, which he calculated at $3,179. CPM filed a response, but the trial court granted Gonzalez’s motion.

The remaining claims for fraudulent transfer eventually proceeded to a trial by jury, but the parties settled those claims after the jury was empaneled. The parties

2 agreed to a final judgment that confirmed the arbitration award, and they further agreed that the award of attorney’s fees arising out of the motion for partial summary judgment should be increased by $50,000, for a total of $53,179. Notwithstanding these agreements, the parties stipulated that CPM could appeal the trial court’s ruling on the motion for partial summary judgment, including the award of post-arbitration attorney’s fees.

ANALYSIS

CPM raises three issues on appeal, and consistent with the parties’ agreement, all of those issues challenge the trial court’s ruling on the motion for partial summary judgment. CPM contends that the ruling was erroneous because (1) Gonzalez did not establish his entitlement to summary judgment, (2) the arbitrator exceeded his authority by making a monetary award, and (3) Gonzalez was not entitled to the award of post-arbitration attorney’s fees. We examine each of these issues in turn.

I. Entitlement to Summary Judgment

A motion for summary judgment is not required for a trial court to confirm an arbitration award, but when a party chooses to pursue confirmation of the award through summary judgment proceedings rather than through the motion procedure provided by the FAA, which governed here, the movant assumes the traditional burdens of summary judgment practice. See Baker Hughes Oilfield Operations, Inc. v. Hennig Prod. Co., 164 S.W.3d 438, 442–43 (Tex. App.—Houston [14th Dist.] 2005, no pet.). Thus, as the movant below, Gonzalez was required to show that he was entitled to judgment as a matter of law and that there were no genuine issues of material fact. See Tex. R. Civ. P. 166a(c).

3 Gonzalez argued in his motion that that the arbitration award should be confirmed. And in support of that argument, Gonzalez attached to his motion an affidavit from the arbitrator and a copy of the arbitration award.

CPM did not challenge the evidence produced by Gonzalez or otherwise suggest that a fact issue precluded summary judgment. However, CPM filed a response to the motion and argued that summary judgment would be improper for two legal reasons. First, CPM argued that an “as is” clause in the purchase contract defeated each of the claims that Gonzalez had presented to the arbitrator. And second, CPM argued that Gonzalez had failed to negate all bases for vacating the arbitration award.

CPM repeats these same arguments in its appellant’s brief, but neither of them has any merit.

In its first argument concerning the “as is” clause, CPM contends that the arbitrator granted relief that was precluded by law. But even if the arbitrator made such a mistake—which is an issue we need not decide—an arbitration award governed by the FAA cannot be set aside on the basis that the arbitrator made a mistake of law. See Casa Del Mar Ass’n, Inc. v. Williams & Thomas, L.P., 476 S.W.3d 96, 99 (Tex. App.—Houston [14th Dist.] 2015, no pet.) (“If Casa del Mar sought to vacate the award under the Federal Act, then the trial court did not err in denying the motion to vacate because neither gross mistake nor manifest disregard of the law is listed in the Federal Act as a basis for vacating an arbitration award, and the grounds stated in the statute are the exclusive grounds for vacating arbitration awards under the Federal Act.”); see also 9 U.S.C. § 10(a) (providing the grounds for vacating an award under the FAA without mentioning a mistake of law); Hall Street Assocs., L.L.C. v. Mattel, Inc., 552 U.S. 576, 578 (2008) (holding that these statutory grounds are exclusive).

4 CPM’s second argument is founded on a misstatement of law. Relying entirely on Mariner Financial Group, Inc. v. Bossley, 79 S.W.3d 30 (Tex. 2002), CPM asserts that, as the party moving for summary judgment below, Gonzalez had the burden of negating every possible basis for vacating an arbitration award available under the FAA. But Bossley does not impose such a sweeping or comprehensive burden. That case merely held that the movants for a traditional summary judgment had the burden of negating a single statutory basis for vacating an arbitration award (evident partiality) where the party opposing the award had previously filed a motion to vacate asserting that same basis. Id. at 32.

At the time that the trial court here ruled on the motion for partial summary judgment, CPM had not pleaded any grounds for vacating the arbitration award, nor had CPM attached any evidence to its response raising a ground for vacating the arbitration award. Accordingly, Gonzalez had no burden to negate any of the statutory grounds for vacating an arbitration award under the FAA.

II. Monetary Award

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alyeska Pipeline Service Co. v. Wilderness Society
421 U.S. 240 (Supreme Court, 1975)
Hall Street Associates, L. L. C. v. Mattel, Inc.
552 U.S. 576 (Supreme Court, 2008)
Vanessa Menke v. Eric Monchecourt
17 F.3d 1007 (Seventh Circuit, 1994)
Baker Hughes Oilfield Operations, Inc. v. Hennig Production Co., Inc.
164 S.W.3d 438 (Court of Appeals of Texas, 2005)
Mariner Financial Group, Inc. v. Bossley
79 S.W.3d 30 (Texas Supreme Court, 2002)
Barton v. FASHION GLASS AND MIRROR, LTD.
321 S.W.3d 641 (Court of Appeals of Texas, 2010)
Babcock & Wilcox Co. v. PMAC, LTD.
863 S.W.2d 225 (Court of Appeals of Texas, 1993)
Tony Gullo Motors I, L.P. and Brien Garcia v. Nury Chapa
212 S.W.3d 299 (Texas Supreme Court, 2006)
D.R. Horton - Texas, Ltd. v. William Bernhard and Nadia Bernhard
423 S.W.3d 532 (Court of Appeals of Texas, 2014)
Stage Stores, Inc. v. Jon Gunnerson
477 S.W.3d 848 (Court of Appeals of Texas, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
CPM of America, LLC v. Roberto Gonzalez, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cpm-of-america-llc-v-roberto-gonzalez-texapp-2024.