Brazoria County v. Knutson

176 S.W.2d 740
CourtTexas Supreme Court
DecidedDecember 15, 1943
DocketNo. 8139
StatusPublished
Cited by78 cases

This text of 176 S.W.2d 740 (Brazoria County v. Knutson) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brazoria County v. Knutson, 176 S.W.2d 740 (Tex. 1943).

Opinion

CRITZ, Justice.

This suit was filed in the District Court of Brazoria County, Texas, by S. Knutson against such county, to recover the sum of $7,191.25, with legal interest, alleged by Knutson to be due him by the county as the balance owing for the construction of a courthouse for the county. The county defended on the ground that it was entitled to a certain credit from the contract price of the courthouse, because the piles under the footings thereof were not driven to a depth of 30 feet, as provided in the contract. Trial in the district court resulted in a judgment for Knutson for $3,216.-25. Such judgment was arrived at by allowing the county a deduction of $3,975 from the $7,191.25 sued for. It was conceded that the county owed Knutson the sum sued for, less any deduction the county was entitled to on account of the piles not being driven to a depth of 30 feet. On appeal by Knutson the Galveston Court of Civil Appeals in effect reversed the judgment of the district court, in so far as it allowed the cortnty the credit above mentioned, and rendered judgment for Knutson therefor. 170 S.W.2d 843. The county brings error.

On November 27, 1939, Brazoria County duly entered into a written contract with S. Knutson for the construction by Knut-son of a courthouse for the county, in accordance with plans and specifications prepared by Lamar Q. Cato as architect. The contract between Knutson and the county provided for either “pre-cast” concrete piles or “cast-in-place” concrete piles under the foundation. The “cast-in-place” piles were used. The contract provided that such piles should be driven to a depth of 30 feet. Knutson subcontracted the work of driving these piles. It was found that it was necessary to drive them only 20 'feet to secure a proper and adequate foundation, and they were driven only to such depth. No contention was' made that the contractor violated his contract in not having such piles driven to a depth of 30 feet, instead of to a depth of 20 feet. Knut-son required the subcontractor to deduct the sum of $2,650 from the amount of his contract, on account of driving the piles 20 feet instead of 30 feet.

The contract provided that the county should make monthly payments to the contractor on estimates approved by the architect. The first estimate was duly approved by the architect, except he deducted therefrom the sum of $2,650, on account of the fact that the concrete piles were driven to a depth of 20 feet, instead of 30 feet, as provided in the contract. Knutson presented the estimate to the county for payment, but refused to accept the deduction. The contract provided for deviations from the drawings or specifications in the execution of the work, on the approval of the architect. As we understand this record, all parties, including the architect, approve the depth to which these piles were driven; [742]*742but there was no direct agreement, one way or the other, as to whether or not any deduction would be made in favor of the county on account of the lesser depth to which they were driven, and no agreement has since been made in regard thereto. The contractor has finished the courthouse, and same has been accepted by the county. The county owes the contractor the $7,-191.25 here sued for, less any deduction the county may be entitled to on account of the piles being driven to a depth of 20 feet, instead of to a depth of 30 feet.

The original contract between the county and Knutson provided that: “All questions subject to arbitration under this contract shall ’ be submitted to arbitration at the choice of either party.” So far as here pertinent, the contract then provides that the county shall select one arbitrator, Knut-son one, and the two so selected shall select the third. Acting under the above contractual provision, Knutson demanded an arbitration. The county acceded to such demand, and each party selected an arbitrator. The two so selected selected a third.

It appears that a pretrial hearing was had in this cause, and as a result thereof the county made, among others, the following admissions:

“15.

“The Architect in his first estimate, dated January 31, 1940, which included the work of driving the piles as aforesaid, allowed the defendant Comity a credit against the contract price in the amount of $2,650.00 because of the fact that said piles were driven to a depth of 20 feet instead of to a depth of 30 feet.”

“16.

“The Plaintiff promptly protested such deduction, but both the County and the Architect insisted on same, and failed and refused to pay the amount so deducted, or any part thereof, to plaintiff.”

“17.

“After the defendant and the Architect had insisted on said deduction of $2,650.00 from the contract price, and refused to pay the same, or any part thereof, to the plaintiff, plaintiff requested that the right of the defendant to such credit be submitted to arbitration, and named one Robert Thomas as an arbitrator, and the defendant, pursuant to plaintiff's request, named one Ben D. Cannan as an arbitrator. The two arbitrators so named chose one David M. Duller as the third arbitrator.”

“18.

“Plaintiff and defendant duly submitted the matter in dispute between them, towit, the question whether Brazoria County was entitled to a credit on account of the footage of piling not driven between the depths of 20 and 30 feet, to said arbitrators, namely, Robert Thomas, Ben D. Cannan and David M. Duller, who after due consideration rendered their award and decision in writing, and signed the same. The said award is in words and figures as follows, towit:

“Houston, Texas,

“November 12, 1940.

“Honorable O. K. Phillips,

“County Judge, Brazoria County,

“Angleton, Texas. '

“Knutson Construction Company,

“Houston, Texas.

“Gentlemen:

“We, the undersigned, two of whom were appointed by you to act as arbitraria and the third Colonel Duller, having been selected as the third member, wish to report our findings concerning the question of credit that might be due Brazoria County on the footage of pilings not driven on the construction of Brazoria County Court House.

“After carefully examining the plans and specifications, discussing the matter with the Architect, Mr. Cato and other investigations, we three have agreed that there is no legal requirements for any credit to be allowed for the footage of piling not driven as no definite agreement or written agreement was entered into on or prior the time the work was being prosecuted.

“However since it is our understanding that some credit was allowed the contractor by the sub-contractor for the footage of piling not driven, we believe that it would be in order for some allowance to be passed on to the county, and recommend that the architect and contractor promptly confer and agree on a settlement.

“Respectfully submitted,

“(Signed) David M. Duller,

“Ben D. Cannan

“Robert Thomas.”

Under the above record, we are convinced that Knutson and the county submitted the entire matter then in dispute between them to arbitration, as provided in the original contract. ■ The county was [743]*743then claiming a credit of $2,650 for piles driven to a depth of 20 feet instead of to a depth of 30 feet, as provided by the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Darling Homes of Texas, LLC v. Wade H. Khoury
Court of Appeals of Texas, 2021
Forest Oil Corp. v. El Rucio Land & Cattle Co.
446 S.W.3d 58 (Court of Appeals of Texas, 2014)
Graham-Rutledge & Co., Inc. v. Nadia Corp.
281 S.W.3d 683 (Court of Appeals of Texas, 2009)
Felipe Rubio Gaspar v. State
Court of Appeals of Texas, 2008
Statewide Remodeling, Inc. v. Williams
244 S.W.3d 564 (Court of Appeals of Texas, 2008)
Kendall Builders, Inc. v. Chesson
149 S.W.3d 796 (Court of Appeals of Texas, 2004)
Nicor International Corp. v. El Paso Corp.
318 F. Supp. 2d 1160 (S.D. Florida, 2004)
Blue Cross Blue Shield of Texas v. Juneau
114 S.W.3d 126 (Court of Appeals of Texas, 2003)
In Re Wells Fargo Bank Minnesota N.A.
115 S.W.3d 600 (Court of Appeals of Texas, 2003)
CVN Group, Inc. v. Delgado
95 S.W.3d 234 (Texas Supreme Court, 2002)
IPCO-G.&C. Joint Venture v. A.B. Chance Co.
65 S.W.3d 252 (Court of Appeals of Texas, 2002)
Joseph D. Longton v. Pamela Lyn Longton
Court of Appeals of Texas, 2001

Cite This Page — Counsel Stack

Bluebook (online)
176 S.W.2d 740, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brazoria-county-v-knutson-tex-1943.