Cummings v. Helena & Livingston Smelting & Reduction Co.

68 P. 852, 26 Mont. 434, 1902 Mont. LEXIS 38
CourtMontana Supreme Court
DecidedApril 29, 1902
DocketNo. 1,383
StatusPublished
Cited by27 cases

This text of 68 P. 852 (Cummings v. Helena & Livingston Smelting & Reduction Co.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cummings v. Helena & Livingston Smelting & Reduction Co., 68 P. 852, 26 Mont. 434, 1902 Mont. LEXIS 38 (Mo. 1902).

Opinion

MR. JUSTICE PIGOTT

delivered the opinion of the court.

The plaintiff, having suffered ¡personal injuries in a mine [441]*441situate in Jefferson county and operated by tlie defendant, brought this action to recover $35,000 as damages. The injuries are alleged to have occurred through the defendant’s negligence. When the plaintiff rested, the court granted a non-suit upon several grounds, one being that the plaintiff had assumed the risk of the accident which occasioned the injury, and another being that he had been guilty of contributory negligence. Judgment for the defendant was then entered, and the plaintiff has appealed.

On motion for nonsuit, whatever the evidence is sufficient to prove in favor of the plaintiff must be considered as established; in other words, when sirch motion is interposed, the truth of the evidence tending to support the plaintiff’s case must he assumed and must be regarded in the light most favorable1 to him, — that which the evidence tends to show must be taken ¡is proved. This Avell settled rule has been repeatedly declared and applied by this court. No less well settled is the rule that if the plaintiff, in attempting to make a case, shows that he ought not to recover, either a nonsuit should be entered or a verdict directed on motion, whichever practice prevails in the particular jurisdiction. In this state, nonsuit is the technically correct method. (McKay v. Montana Union Ry. Co., 13 Mont. 15, 21 Pac. 999.) In actions for personal injuries the absence of contributory negligence is not required to be pleaded or proved by the plaintiff, but its presence is a matter of defense. Such is the law in Montana. (Higley v. Gilmer, 3 Mont. 90, 35 Am. Rep. 450; Mulville v. Pac. Mutual Life Ins. Co., 19 Mont. 95, 47 Pac. 650; Snook v. City of Anaconda, 26 Mont. 128, 66 Pac. Rep. 756.) The contrary rule Avas announced in Ryan v. Gilmer, 2 Montana Reports, 517, 25 American Reports, 744, but has been overturned by the oases cited and those referred to by the opinions therein. If, hoAvever, the complaint sIioavs the proximate (or a proximate) cause of the injury to have been the act of the plaintiff, the complaint must also state his freedom from negligence in the doing of the act; othenvise the pleading is bad. (Kennon [442]*442v. Gilmer, 4 Mont. 433, 2 Pac. 21) ; and so, if the evidence in behalf of the plaintiff shows the injury to have been directly caused (cither in whole or in part) by his act, the burden is 'immediately upon him to prove that he was exercising ordinary care at the time. (Nelson v. City of Helena, 16 Mont. 21, 39 Pac. 905.) Another rule, from which there seems to be no dissent except in North Carolina (Bolden, v. Railway Co., 123 N. C. 614, 31 S. E. 851; Cogdell v. Railroad Co., 124 N. C. 302, 32 S. E. 706; Powell v. Railway Co., 125 N. C. 370, 34 S. E. 530), is that if the evidence in plaintiff’s behalf establishes, beyond question, that his own omission to use ordinary care contributed immediately to, or itself caused, the injury, the court should on motion direct a verdict or grant a nonsuit.

The motion for a nonsuit in the case at bar was similar to the common law demurrer to the evidence, in that it performed the office of admitting’ as facts what the evidence tended to prove, thereby presenting the question whether the facts so conceded, when viewed in the light most favorable to the plaintiff, were, as matter of law, sufficient to justify a verdict for him. So considering the evidence, the facts may be stated thus: On Saturday, September 28, 189.5, the plaintiff, aged 33 years, a practical miner of sixteen years’ experience, familiar with the risk and dangers incident, to the hazardous occupation, was severely injured by a fall of rock in the Alta mine, operated by the defendant, a corporation. He had been so in the employ of the defendant, and working for it as an underground miner in Ihe .Vita mine since 1892. Eor many years he had operated a machino drill used for boring holes in tunnels and raises so that blasting might be done. When hurt lie was engaged in constructing a three-compartment, inclined raise on the vein, following the foot wall, from the 1200-foot level to an intermediate tunnel eighty feet distant. The raise departed from flie perpendicular at an angle of about 45 degrees — the dip of the vein. Each compartment was a separate chute; the-middle one was the man-way, the others, one on each side of [443]*443tlie man-way, were used for ore. Four sets of timbers were needed to make the three compartments., These consisted of four equi-distant stringers, or uprights, next to the hanging wall; four stulls or cross-pieces eight to ten feet in length (according to- the pitch of the walls) attached to, and supporting the top of, the stringers, and reaching from wall to wall; three “girds,” or girders, laid on top of the stringers and parallel with the strike or course of the vein, and running from stull to stull. The stulls supported the stringers, and the girders served to keep- both in place. Each three-compartment section of the rise was about six and one-half feet in height by thirteen in length, each room or compartment being about four feet and four inches in length along the lode on its strike or course, which is east and west. When the ground did not blast so as to permit the stulls.and stringers to fit snugly against the country rack, the stringers were lagged crosswise with round poles four feet and four inches in length, and then the space between the lagging and the hanging wall was filled in with waste so as to keep the timbers secure.' To make a floor, lagging of the same sort was laid on top of the timbers from stull to stull, and across the openings leading up to the face of the raise. The machine was set upon the floor and the holes drilled overhead in the face. Each set of four timbers carried the raise six and one-half feet further towards the tunnel. A floor was not left on each set of timbers, hut whenever advance of a set higher (six and one-luilf feet) had been made, the lagging of the lower floor of the last set would be moved up and the top flooring of that, set left, so that there were always two floors lagged in whole or in part. The top or upper floor was always left open ■ — that is, without lagging — on the side not- blasted, in order that the miners might gain ingress to- it from the floor below and see the face of the ground. After drilling and before blasting, the space between the timbers immediately under the ground to he blasted was always lagged. This was done as a measure of protection to miners going to the; lower floor; with the upper floor (or top of the timbers) tightly lagged under [444]*444tlie ground blasted or about to- be blasted, a man. could, with a reasonable degree of safety, reach the lower floor, cross to the side or end over which blasting had not been done, or was not about to be done, and then go to the upper floor through the opening left under the solid ground. The plaintiff testified: “As we went up we would set the machine for tire purpose of drilling on one c f these floors, the bar set on one of those floors that would be lagged up. We put lagging on top of the timber, too, and that made a floor, and from that floor we bored above us-. As we proceeded with the work, we did not leave these floors on each set of timbers; when we would get up a set higher we would pull up the under floor and move it on up again; wo kept two floors all the time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lake v. Emigh
190 P.2d 550 (Montana Supreme Court, 1948)
Roecher v. Commercial National Bank
289 P. 388 (Montana Supreme Court, 1930)
Villanueva Carballo v. Suárez Pérez
41 P.R. 39 (Supreme Court of Puerto Rico, 1930)
Armstrong v. Billings
283 P. 226 (Montana Supreme Court, 1929)
McKeon v. Kilduff
281 P. 345 (Montana Supreme Court, 1929)
Grant v. Chicago, Milwaukee & St. Paul Ry. Co.
252 P. 382 (Montana Supreme Court, 1927)
Grant v. Chicago Etc. Ry. Co.
252 P. 382 (Montana Supreme Court, 1927)
Awbery v. Schmidt
211 P. 346 (Montana Supreme Court, 1922)
Calumet v. Gardner
187 P. 563 (Arizona Supreme Court, 1920)
Conway v. Monidah Trust
157 P. 178 (Montana Supreme Court, 1916)
López v. Sánchez
22 P.R. 521 (Supreme Court of Puerto Rico, 1915)
Michalsky v. Centennial Brewing Co.
134 P. 307 (Montana Supreme Court, 1913)
Dunseth v. Butte Electric Railway Co.
108 P. 567 (Montana Supreme Court, 1910)
Schroder v. Montana Iron Works
100 P. 619 (Montana Supreme Court, 1909)
Poor v. Madison River Power Co.
99 P. 947 (Montana Supreme Court, 1909)
Leary v. Anaconda Copper Min. Co.
92 P. 477 (Montana Supreme Court, 1907)
Anderson v. Northern Pacific Ry. Co.
85 P. 884 (Montana Supreme Court, 1906)
Orient Insurance v. Northern Pacific Railway Co.
78 P. 1036 (Montana Supreme Court, 1905)
Western Loan & Savings Co. v. Silver Bow Abstract Co.
78 P. 774 (Montana Supreme Court, 1904)
Shaw v. New Year Gold Mines Co.
77 P. 515 (Montana Supreme Court, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
68 P. 852, 26 Mont. 434, 1902 Mont. LEXIS 38, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cummings-v-helena-livingston-smelting-reduction-co-mont-1902.