Culmer v. Hooper-Caine

61 P. 1008, 22 Utah 216, 1900 Utah LEXIS 23
CourtUtah Supreme Court
DecidedJune 9, 1900
StatusPublished
Cited by6 cases

This text of 61 P. 1008 (Culmer v. Hooper-Caine) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Culmer v. Hooper-Caine, 61 P. 1008, 22 Utah 216, 1900 Utah LEXIS 23 (Utah 1900).

Opinion

After stating the facts,

Miner, J.,

delivered the opinion of the court.

The appeal in this case is taken from'the judgment. No bill of exceptions was settled, or testimony returned.

1. Appellants first contention is that the cross-complaint does not set forth the contract between Wright, the contractor, and the owners of the property, Caine and Hooper, either in terms or legal effect, and no compliance with the terms of the contract is alleged as required by Sec. 2, and 10, Ch. 30, Sess. Laws, 1890, p. 25.

Upon an examination of the record we find that the cross-complaint was amended so as to obviate the objection made, and that as amended it was in compliance with the statute of 1890, prior to the change in its provisions in 1894, as held in Morrison v. Inter-mountain Salt Co., 14 Utah, 201. The case of Morrison, Merrill & Co. v. Willard, 17 Utah, 306, was applicable to Sec. 1372 R. S. 1898.

It is true that the sub-contractor can have no higher or greater right against the owner than the contractor. The contract with the latter measures and limits the rights of both. Boisot on Mech. Liens, Sec. 228; Phillips on Mech. Liens, Secs. 58, 62, 143.

2. Appellants also contend that no compliance with the [224]*224provisions of the contract requiring that the work was to be done to the satisfaction of the architect, to be evidenced by his certificate is shown.

With reference to this objection the court found that Duvall & Mills, the cross-complainants, “fully completed all work contracted to be performed on said building, under said sub-contract, in accordance with the requirements and terms of said sub-contract on the 1st day of March, 1891.” This is a finding of the ultimate facts which included within its terms a certificate from the-architect, and rendered it unnecessary for a finding of the particular evidentiary facts with reference to the actual proof of the architect’s certificate. The finding that the contract was performed in all its terms and requirements, included all the conditions and provisions of the contract.

When evidence is not before the appellate court it will be presumed that the findings were supported by the evidence. Blethen v. Blake, 44 Cal. 117.

If the owner or principal contractor intended to insist upon their rights to a final certificate'from the architect, they could have notified the contractor, and if the certificate was refused, they could properly refuse payment for that reason. Besides the findings show that the principal contractor agreed with the sub-contractor upon the amount due, showing a balance of $2,812.30, due the sub-contractor after the completion of the work. Bannister v. Patty, 35 Wis. 215; Blethen v. Blake, 44 Cal. 117.

3. Appellants third contention is that there is a fatal variance between the allegations of the cross-complaint wherein the contract price is specifically alleged at $16,636 and the notice of the lien claimed $18,363.58, that being the reasonable value for labor and materials furnished, and that the former was by individuals, and the latter by a partnership, and that the notice was not signed or sworn [225]*225to. Upon an examination we find that the notice or statement for a lien was subscribed Duvall & Mills, by Diehard Duvall, and was sworn to by Duvall, one of the claimants and joint contractors.' The claim was properly sworn to and the jurat was sufficient under the provisions of Sec. 10, Ch. 30, Laws of 1890. Neither Sec. 10, 15, or 17, Ch. 30 Laws of 1890, required the statement to contain the conditions of the contract, or that the several contracts should be separately stated. The statement-was required to contain a notice of the intention to claim a lien, a description of the property to be charged, an abstract of indebtedness showing the whole amount of the debt and credit, and the balance due, or to become due, with a verification of one or all of the claimants, or by some one for them. The notice or statement contained sufficient facts to justify a lien under the statute as it then existed. By Section 14, an incorrect statement of an amount due did not invalidate it unless made in bad faith. Phillips on Mech. Liens, Sec. 35,5; Garner v. Van Patten, 58 Pac. Bep. 684, 20 Utah 342.

Appellants fourth contention is untenable. The notice was in compliance with Sections 10 and 17, Sess. Laws 1890, and it was not necessary to state the amount' of work done or materials furnished, and amount due on each of the separate contracts. Under Sec. 17, where the work is continuous the lien attaches even if the work is done or materials furnished under separate contracts. The notice complied with Sec. 10, and stated the total amount of debt and credit, and the balance due. ,

5. The appellants contend that the notice for lien was not filed within 40 days from the last day of doing work and furnishing materials.

We find that the notice of lien'was filed March 28, 1891. The complaint, as amended, alleges the completion of the [226]*226contract, last work done, and materials furnished March 1, 1891. The notice was filed within 40 days from the completion of the contract as required by the statute. Under this head appellants also contend that under Sec. 21 no lien shall hold the property longer than one year after filing the statement unless an action be commenced within that time to enforce the same; that the statement was filed March 21, 1891, and that the cross-complaint of Duvall & Mills was filed to enforce the contract February 1, 1892, but that no summons was ever issued on the cross-complaint or service had thereof until October 1, 1896, either upon Wright, the principal contractor, or the defendants Caine and Hooper, and that Wright had never appeared; that a purported copy of the cross-complaint was mailed to Wright at Butte after October, 1896, and returned endorsed “Received a copy of the within,” and signed by Wright, but no proof of Wright’s handwriting is shown, and that by reason of the delay defendants have lost all means of indemnity against Wright and his bondsmen on account of .the intervening insolvency of Wright and his bondsmen; that the action was not’ commenced within the year as required by Sec. 21; that under Sec. 31, Ch. 30, Laws of 1890, the practice is declared to be in accordance with the code of civil procedure; that Sec. 305 of said code (being Sec. 3221 C. L. U. 1888) provides that “the cross-complaint must be served upon the parties affected thereby, and such parties may demur or answer thereto as to the original complaint.”

Upon an inspection of the record we find that the original summons was issued December 15, 1891, and personally served on Duvall & Mills on January 7, 1892, together with a copy of the complaint. A stipulation was filed February 1st giving Duvall & Mills until February 1st, 1892, in which to answer. On that day they appeared [227]*227and filed their answer and cross-complaint. The notice of lien was recorded on March 28, 1891. The answer and cross-complaint was filed within the year. Defendant Wright admitted service on the -back of the summons, as follows: “I hereby accept service of the.within summons this 8th day of January, 1892. (Signed) F. M.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rosenbaum v. Price Construction Co.
184 S.E. 261 (West Virginia Supreme Court, 1936)
Brewer v. Oil Well Supply Co.
1927 OK 232 (Supreme Court of Oklahoma, 1927)
Liebhauser v. Milwaukee Electric Railway & Light Co.
193 N.W. 522 (Wisconsin Supreme Court, 1923)
Sanford v. Kunkel
85 P. 363 (Utah Supreme Court, 1906)
Fields v. Daisy Gold Mining Co.
69 P. 528 (Utah Supreme Court, 1902)
Olson v. Oregon Short Line Railroad
68 P. 148 (Utah Supreme Court, 1902)

Cite This Page — Counsel Stack

Bluebook (online)
61 P. 1008, 22 Utah 216, 1900 Utah LEXIS 23, Counsel Stack Legal Research, https://law.counselstack.com/opinion/culmer-v-hooper-caine-utah-1900.