Morrison v. Carey-Lombard Co.

9 Utah 70
CourtUtah Supreme Court
DecidedJune 15, 1893
StatusPublished
Cited by12 cases

This text of 9 Utah 70 (Morrison v. Carey-Lombard Co.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morrison v. Carey-Lombard Co., 9 Utah 70 (Utah 1893).

Opinion

Bartoh, J.:

The owner of a lot in Salt Lake City made a contract with a builder to erect a residence thereon, and the appellants and respondent were all sub-contractors in the first degree under the principal contractor. They all furnished material for use in the erection of the building, and, upon the principal contractor’s failure to pay in full therefor, filed notices of mechanic’s lien against the property. Suit was brought by these parties, and the cause was tried in the third district court on an agreed statement of facts. On an accounting between the owner of the property and the principal contractor it was ascertained that there was due the contractor the sum of 12,290, and by. agreement of the appellants and respondent the owner’s property was released of the liens upon his payment of that sum into court. The property of the owner having been released, the principal question to be determined is the right of priority to the fund paid into court as between the sub-contractors. The facts agreed upon between the several parties, sub-contractors, are, in substance, that the amounts due from the principal contractor to Spencer, By water & Co. is §442.30, to Morrison, Merrill & Co., $200, and to the Carey-Lombard Company, $4,396; that the several parties filed and had recorded against the property mechanics’ liens, respectively, December 22, 1890, November 15, 1890, and September 17, 1891; that the same parties commenced to furnish materials, respectively, on July 1, 1890, July 15, 1890, and on May 5, 1890; that they are sub-contractors of the first degree; and that all the liens were filed for record within 40 days from the date of furnishing the last material. Upon this statement [74]*74of facts the trial court entered judgment against the principal contractor for the several amounts above stated and in favor of the sub-contractors, and, as to the sum paid into court, entered judgment in favor of the Carey-Lombard Company. From this judgment the appellants appealed to this court.

The sole question raised is as to whether the lien of each of the several claimants attaches on the date of filing the notice for record, or whether it attaches on the date of furnishing the first material. Section 1 of the act approved March 12, 1890, (Sess. Laws Utah 1890, p. 25, c. 30,) provides “that whoever shall do work or furnish materials by contract, express or implied, with the owner of any land, to any amount, for the construction, enlargement, alteration, or repair of any building or other structure upon such land, or in making any other improvements,' or in doing any other work upon such land, as stated in the following sections, shall have a lien1 upon such land, building, structure, and other improvement1 for the amount and value of the work so done, or materials so furnished, to the extent of the interest or claim of such owner thereto at the time of the commencement to do such work or to furnish such materials. Said lien shall likewise attach to another or greater interest in any of such property acquired by such owner at any time subsequent to' such commencement to do work or to furnish materials, and before the establishment of said lien by process of law,” etc. From this section it would appear that the legislature intended to. limit the lien to such persons as had either express or implied contracts with the owner of the land, and that such persons should have a lien for such materials or work to the extent of the owner’s interest or claim in the property “at the time of the commencement to do such work or furnish such materials,” and such lien is extended to any other or greater interest which the owner [75]*75may acquire in the property thereafter, and before the lien is established by process of law. This is an express provision for such a lien for those who have a contract directly with the owner of the land, and is binding upon him, and defines what interest is subject to the lien; so that, after the contractor commences to perform his contract, the owner cannot convey his land free from the incumbrance, nor can he impose any other burdens upon it to in any manner affect the lien. From the day the contractor commences to work or furnish material it is notice to all persons thereafter contracting with the owner that the property is burdened with a lien, and, if there were no further enactment, then there could be no question about the notice or the time of the attachment of the lien, nor of the persons entitled thereto.

But section 2 of the"same"act provides: “Whoever shall do work or furnish materials by contract, express or implied, with the principal contractor mentioned in the preceding section to any amount, for any of the purposes mentioned in the preceding section, shall be deemed a sub-contractor in the first degree, and shall have a lien upon any and all such property, in like manner as said contractor.” This is a provision for the sub-contractor, and it defines his status to be precisely the same as that of the contractor mentioned in the first section. The appellants and respondent herein are subcontractors of the first degree, and their rights are subject to the provisions of this section. The next section provides for sub-contractors in the second degree, and then follow other sections, which define the classes of property which are subject to lien, and the pérsons who may avail themselves of the law in regard to liens. Then follows section 10, which provides: “Any party claiming a lien shall file in the office of the recorder of the county wherein said land is' situated a statement containing — first, a notice of [76]*76intention to hold and claim a lien; second, a description of the property to be charged therewith; third., an abstract of indebtedness, showing the whole amount of debt, the whole amount of credit, and the balance due or to become due to the claimant, which abstract of indebtedness shall be verified,'” etc. Every person claiming a lien must file the statement as provided in this section. This is indispensable to preserve the lien provided for in the preceding-sections, and section 11 provides that this statement shall be filed within 60 days in case of the principal contractor, and within 40 days in case of a sub-contractor in either degree, “after the time when the last work shall have been done or the last material shall have been furnished.” It is evident that the filing of the statement does not create the lien, for the language of the statute is, “Any party claiming a lien shall file,” etc., but simply holds it or keeps it in force for the time of one year, as provided in section 21 of the same act, so as to give the claimant an opportunity to enforce the same by process of law. It follows that when the principal contractor, or a sub-contractor in either degree, has done work or furnished material, and then filed the statement provided for in section 10 in the manner provided in section 11, his lien is complete, and superior to every incumbrance with which the property may have been burdened subsequent to the date of commencing to do such work or to furnish such material, and may be enforced within the time above mentioned.

Counsel for appellants contend that such lien does not attach until the date of filing the statement and notice, and that, in order for the lien to attach at the time of commencing to do work or to furnish material, it is necessary for the claimant to file a statement as provided in section 12, which reads as follows: “Any sub-contractor of either degree who shall intend to do work or to furnish [77]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Foothill Park, LC v. Judston, Inc.
2008 UT App 113 (Court of Appeals of Utah, 2008)
Edsa/Cloward, L.L.C. v. Klibanoff
2005 UT App 367 (Court of Appeals of Utah, 2005)
Knight v. Post
748 P.2d 1102 (Court of Appeals of Utah, 1988)
Buckle v. Ogden Furniture & Carpet Co.
216 P. 684 (Utah Supreme Court, 1923)
Langton Lime & Cement Co. v. Peery
159 P. 49 (Utah Supreme Court, 1916)
Fields v. Daisy Gold Mining Co.
69 P. 528 (Utah Supreme Court, 1902)
Culmer v. Hooper-Caine
61 P. 1008 (Utah Supreme Court, 1900)
Culmer v. Clift
47 P. 85 (Utah Supreme Court, 1896)
Morrison v. Inter-Mountain Salt Co.
46 P. 1104 (Utah Supreme Court, 1896)
Cary-Lombard Lumber Co. v. Partridge
37 P. 572 (Utah Supreme Court, 1894)
Spargo v. Nelson
37 P. 495 (Utah Supreme Court, 1894)

Cite This Page — Counsel Stack

Bluebook (online)
9 Utah 70, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morrison-v-carey-lombard-co-utah-1893.