Sanford v. Kunkel

85 P. 363, 30 Utah 379, 1906 Utah LEXIS 75
CourtUtah Supreme Court
DecidedApril 23, 1906
DocketNo. 1685
StatusPublished
Cited by9 cases

This text of 85 P. 363 (Sanford v. Kunkel) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sanford v. Kunkel, 85 P. 363, 30 Utah 379, 1906 Utah LEXIS 75 (Utah 1906).

Opinions

STKAUP, J.

1. Tbis is an action brought by Sanford against Kunkel, tbe "Utah Lumber Company, and Charles E. Murphy, defendants, to foreclose a mechanic’s lien. Appellants Cain and Walsh were made parties and intervened. Judgment was had in favor of defendants and against plaintiff and interveners. The appeal is on the judgment roll, without a bill of exceptions containing any evidence. The assignments relate only to the conclusions of law. The findings, so far as material, show: On August 1, 1903, Kunkel was the owner of lots 8, 9, and 10. He then entered into a contract with appellant Cain to furnish plans and specifications and to superintend the construction of two dwellings to be erected on said lots; on August 5th, with appellant Sanford to construct the cellar walls and to, do the carpenter work; on August 3d, with appellant Walsh to do the plumbing; on August 5th, with Morrison Merrill & Co-., to furnish lumber, hardware-, and other material for the house on lot 10 and the south half of lot 9. Cain commenced his work on the 1st day of August, 1903, Walsh on the 3d, and Sanford on the 8th. The lastwork performed by them was on the 27th day of October, 1903. Morrison Merrill & Co., furnished the first material August 18, and the last October 26, 1903. The two buildings were erected on the said lots, one house substantially on lot 8 and the north half of lot 9, and the other on lot 10 and the south [382]*382half of lot 9 without any fence or barrier between them and all of said land was necessary for the use and occupation of said buildings. Appellants Sanford, Walsh, and Cain performed labor and furnished material on both houses in pursuance of their contracts. When the building on lot 8 and the north half of lot 9 was almost finished and the contracts of appellants nearly completed, on or about the 12th day of September, 1903, the respondents, the Utah Lumber Company and Charles E. Murphy, its manager, without the knowledge or consent of Kunkel, the owner of the ground, or of the appellants, removed said building from said lot 8 and the north half of lot 9 to lots 4 and 3 adjoining and owned by the Utah Lumber Company, and there caused it to be attached to a brick foundation. On November 9, 1903, Sanford filed a notice of lien on lots 8, 9, and 10; Walsh on November 7, 19‘03; Cain on November 4 1903; and Morrison Merrill & Co. on November 26, 1903. Sanford on the 18th day of September, 1903, Walsh on the 24th day of September, and Cain on the 26th day of October, also* filed notice of liens on lots 4 and 3; wherein, among other things it was stated that the building thereon was erected on lot 8 and north half of lot 9 for Kunkel, and that after it was substantially completed the Utah Lumber Company and Charles E. Murphy forcibly, wrongfully, and without the knowledge or consent of Kunkel or the lien claimants, removed it therefrom to lots 4 and 3. Morrison, Merrill & Co*, assigned its claim to Cain. Kunkel defaulted. Appellants prayed that their liens be foreclosed against lots 8, 9, and 10, and, if the proceeds of sale be insufficient to satisfy them, that then the house wrongfully removed from lot 8 and the north half of lot 9 be sold and the proceeds applied on such deficiency, and that they be granted such other relief as in equity they may be entitled. The trial court decreed a foreclosure as to lots 8, 9, and 10. Because of the removal of the building from lot 8 and the north half of lot 9, and its being attached to a brick foundation on lots 4 and 3, the court ruled the lien on the building was lost and did not follow it to its new location, hence denied appellants all relief with respect there[383]*383to, and merely gave them a deficiency judgment against Kun-kel. This ruling of the court presents the matter for review.

2. Section 1372 of the mechanic’s liens statute (Nev. St. 18.98) provides:

“Mechanics, materialmen, contractors, subcontractors, builders and all persons of every class performing labor upon or furnishing materials to be used in the construction, etc., of any building, etc., and also architects, etc., who have furnished designs, plats, plans, maps, specifications, drawings, estimates of cost, or superintendence, etc., shall have a lien upon the property upon which they have rendered service, or performed labor, or furnished materials, for the value of such service rendered, labor done, or materials furnished, by each respectively, whether at the instance of the owner or of any other person acting by his authority or under him as agent, contractor, or otherwise; provided, that a lien or liens shall attach only to such interest as the owner or lessee may have in the real estate.”

Section 1379:

“The liens granted by this chapter shall extend to and cover so much of the land whereon such building, structure or improvement shall be made, as may be necessary for the convenient use and occupation of such building, structure or improvement, and the same shall be subject to such liens; and in case any such building shall occupy two or more lots or other subdivisions of land, such lots or other subdivisions shall be deemed one lot for the purposes of this chapter,” etc.

Section 1384:

“The liens provided for herein are preferred to any lien, mortgage, or other incumbrance which may have attached subsequent to the time when the building, improvement, or structure was commenced, work done, or materials were commenced to be furnished; also to any lien, mortgage, or other incumbrance of which the lienholder had no notice and which was unrecorded at the time the building, improvement, or structure was commenced, work done, or materials commenced to be furnished.”

Section 1385:

“The liens herein provided shall relate hack to and take effect as of the time of the commencement to do work upon and furnish materials on the ground for the structure or improvement, and shall have priority over any lien or incumbrance subsequently intervening, except a lien herein provided for of the same class, or which may have been created prior thereto, which was not then recorded and of which the lienor under this chapter did have actual notice.”

[384]*384Section 1386 provides that the original contractor, within sixty days after the completion of his contract, and a subcontractor within forty days after furnishing the last material or performing the last labor for any building, shall file for record a notice of intention to hold and claim a lien. Section 1392 provides:

“The court shall cause the property to be sold in satisfaction of the liens and costs, as in the case of foreclosure of mortgages, subject to the right of redemption of the owner and creditors as provided by law,” etc.

A finding was made that, at the time of the removal of the building, appellants had no notice of lien filed of record, but it will be observed that, under the statute and as construed by this court, the lien has its inception from the time of the commencement of the work and the furnishing of materials, and, by relation, takes effect as of that date, and is given priority over any lien or incumbrance subsequently intervening, or which may have been created prior thereto' which was not recorded and of which the lien claimants had not actual notice. (Culmer v. Caine, 22 Utah 216, 61 Pac. 1008; Fields v. Daisy Min. Co., 25 Utah 76, 69 Pac.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Butterfield Lumber, Inc. v. Peterson Mortgage Corp.
815 P.2d 1330 (Court of Appeals of Utah, 1991)
John Wagner Associates v. Hercules, Inc.
797 P.2d 1123 (Court of Appeals of Utah, 1990)
Roberts v. Hansen
479 P.2d 345 (Utah Supreme Court, 1971)
King Bros., Inc. v. Utah Dry Kiln Company
440 P.2d 17 (Utah Supreme Court, 1968)
Oil Well Supply Co. v. First Nat. Bank of Winfield
106 F.2d 399 (Tenth Circuit, 1939)
Eccles Lumber Co. v. Martin
87 P. 714 (Utah Supreme Court, 1906)
Sanford v. Kunkel
85 P. 363 (Utah Supreme Court, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
85 P. 363, 30 Utah 379, 1906 Utah LEXIS 75, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sanford-v-kunkel-utah-1906.