Cubic Corporation v. Richard C. Cheney, Secretary of Defense and Kollsman, a Division of Sequa Corporation, Intervenor

914 F.2d 1501, 36 Cont. Cas. Fed. 75,943, 286 U.S. App. D.C. 243, 1990 U.S. App. LEXIS 16571, 1990 WL 135892
CourtCourt of Appeals for the D.C. Circuit
DecidedSeptember 21, 1990
Docket89-5277
StatusPublished
Cited by3 cases

This text of 914 F.2d 1501 (Cubic Corporation v. Richard C. Cheney, Secretary of Defense and Kollsman, a Division of Sequa Corporation, Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cubic Corporation v. Richard C. Cheney, Secretary of Defense and Kollsman, a Division of Sequa Corporation, Intervenor, 914 F.2d 1501, 36 Cont. Cas. Fed. 75,943, 286 U.S. App. D.C. 243, 1990 U.S. App. LEXIS 16571, 1990 WL 135892 (D.C. Cir. 1990).

Opinion

Opinion for the Court filed by Circuit Judge D.H. GINSBURG.

*1502 D.H. GINSBURG, Circuit Judge:

Cubic Corporation bid for a contract to produce an Air Force instrumentation system, but the Air Force found that Cubic was not a responsible contractor for the project and disqualified it. The Air Force acted on the basis of information suggesting that a senior executive of Cubic, and a defense consultant employed by Cubic, may have attempted to bribe an Air Force official in return for assistance in obtaining the contract. Cubic filed suit in district court to overturn the nonresponsibility determination and to require the Air Force to award it the contract. After rejecting Cubic’s claim that it had a right, under Title III of the Omnibus Crime Control and Safe Streets Act of 1968, 18 U.S.C. §§ 2510-2520, to challenge the legality of the Air Force’s using against it any information derived from wiretaps, the district court granted summary judgment for the Air Force. We reverse on that point and remand the matter for further proceedings.

I. BACKGROUND

Before a company may be awarded a government contract, a government contract official must make “an affirmative determination” that the contractor is responsible. The contractor bears the burden of persuasion on this point, for the Federal Acquisition Regulation, 48 C.F.R. § 9.103(b), provides that: “In the absence of information clearly indicating that the prospective contractor is responsible, the contracting officer shall make a determination of nonresponsibility.” In order to be deemed responsible, a prospective contractor must have, among other things, “a satisfactory record of integrity and business ethics.” 48 C.F.R. § 9.104-l(d).

On May 31, 1989, an Air Force contracting officer advised Cubic that it had found that the company was not a responsible contractor with respect to the Alaska/Wisconsin Air Combat Maneuvering Instrumentation (ACMI) procurement, for which Cubic had submitted a proposal. In making that determination, she considered two redacted search warrant affidavits that suggested that a consultant acting on behalf of Cubic, might have bribed Dr. Victor Cohen, then Assistant Secretary of the Air Force for Tactical Warfare Systems, in conjunction with the ACMI project. One of the affidavits states specifically the affi-ant’s belief “that Cohen will provide illegal assistance to Cubic in its effort to win [the ACMI] contract.”

The Air Force contracting officer found:

There is substantial evidence of improper activity on the part of the President of [Cubic’s subsidiary,] Cubic Defense Systems, Mr. Wellborn, who would have ultimate oversight and responsibility for Cubic’s performance of the Alaska ACMI procurement [predecessor of the Alaska/Wiseonsin ACMI procurement], and Cubic Corporation. They are both “targets” of the ongoing “Ill Wind” investigation and the affidavits used in support of search warrants at Cohen’s home and Wellborn’s office indicate that the Alaska ACMI procurement may have been tainted.

Cubic filed suit on June 2, 1989. It sought a temporary restraining order to prevent the Air Force from awarding the ACMI contract pending a decision on Cubic’s motion for a preliminary injunction or on the merits of its challenge to the nonre-sponsibility determination. The district court held a hearing, at the end of which it took the matter under advisement. While the case was thus pending, Cubic informed the Government that Wellborn was no longer working for the company, and asked that the Air Force reconsider the non-responsibility determination before awarding the contract; the Air Force agreed to do so. During the reconsideration, Cubic also advised the Air Force that it had hired a former Navy Judge Advocate General to oversee its ethics training program.

On June 16, the Air Force reaffirmed its non-responsibility determination. The contracting officer found that Wellborn’s departure and the arrival of the former Naval officer were insufficient reasons to change her earlier decision. The Air Force then awarded the contract to intervenor Kolls-man, a division of Sequa Corporation.

*1503 Cubic promptly filed an amended complaint seeking an injunction restraining Kollsman from performing the contract until the district court could review the Air Force's non-responsibility determination. The district court denied Cubic’s motion, and granted summary judgment for the Air Force. The court held that a contractor has no right to challenge an agency’s use, in making a non-responsibility determination, of information derived from a wiretap, and that the agency’s further use of such information to defend its action on judicial review is not subject to Title III. The court also rejected Cubic’s claims that the non-responsibility determination was not rational, and that the Air Force had denied Cubic due process of law.

II. Jurisdiction

On appeal, intervenor Kollsman alone challenges this court’s jurisdiction. Kollsman argues that the Federal Courts Improvement Act of 1982 vested the Claims Court with exclusive jurisdiction over pre-award challenges to procurement decisions, and that the district court was therefore without jurisdiction over this cause of action. The 1982 statute provides that “before the contract is awarded, the [Claims Cjourt shall have exclusive jurisdiction to grant declaratory judgments and such equitable and extraordinary relief as it deems proper, including but not limited to injunctive relief.” 28 U.S.C. § 1491(a)(3).

Of those courts of appeals that have confronted the issue, two have held that jurisdiction over pre-award challenges is exclusive in the Claims Court, see J.P. Francis & Assocs., Inc. v. United States, 902 F.2d 740 (9th Cir.1990); Rex Systems, Inc. v. Holiday, 814 F.2d 994, 997-98 (4th Cir.1987); two have said as much in dicta, see F. Alderete General Contractors, Inc. v. United States, 715 F.2d 1476, 1478 (Fed.Cir.1983); B.K. Instrument, Inc. v. United States, 715 F.2d 713, 721 n. 4 (2d Cir.1983), and two have found concurrent jurisdiction in the district courts, see Ulstein Maritime, Ltd. v. United States, 833 F.2d 1052, 1057-58 (1st Cir.1987) (district courts have “concurrent power to award injunctive relief in pre-award contract cases”); Coco Bros. v. Pierce, 741 F.2d 675

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Geo-Con, Inc. v. United States
853 F. Supp. 537 (District of Columbia, 1994)
Forsyth v. Barr
19 F.3d 1527 (Fifth Circuit, 1994)
Solano Garbage Co. v. Cheney
779 F. Supp. 477 (E.D. California, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
914 F.2d 1501, 36 Cont. Cas. Fed. 75,943, 286 U.S. App. D.C. 243, 1990 U.S. App. LEXIS 16571, 1990 WL 135892, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cubic-corporation-v-richard-c-cheney-secretary-of-defense-and-kollsman-cadc-1990.