Crouch Construction Co. v. Causey

747 S.E.2d 482, 405 S.C. 155, 2013 WL 4082358, 2013 S.C. LEXIS 200
CourtSupreme Court of South Carolina
DecidedAugust 14, 2013
DocketAppellate Case No. 2011-195510; No. 27300
StatusPublished
Cited by2 cases

This text of 747 S.E.2d 482 (Crouch Construction Co. v. Causey) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crouch Construction Co. v. Causey, 747 S.E.2d 482, 405 S.C. 155, 2013 WL 4082358, 2013 S.C. LEXIS 200 (S.C. 2013).

Opinion

Justice KITTREDGE.

This is a direct appeal from an order of the circuit court vacating an arbitration award on the ground of the arbitrator’s “evident partiality.” S.C.Code § 15-48-130(a)(2) (2005). We reverse.

I.

This dispute arises from the construction of a commercial building in West Columbia, South Carolina. Before the undeveloped property was purchased, Respondent Bryan Causey hired GS2 Engineering and Environmental Consulting, Inc. (GS2) to perform an engineering analysis of the soils on the property to determine whether the land was suitable for construction. Following inspections and testing, GS2’s engineering report indicated that the soils within a certain proximity of the surface were unsuitable and had to be removed and replaced with suitable soils.1 Causey formed Causey Consulting, LLC (Causey Consulting) of which he is the sole member, and thereafter Causey Consulting purchased the property for the purpose of constructing the commercial building. Appellant Crouch Construction Company was retained as the general contractor. Based on GS2’s initial report, the construction contract allowed $25,000 for “site work” to be conducted, which represented only a small part of the total contract amount of $616,538.

The parties’ dispute began over the amount of unsuitable soils excavated from the building site. During construction, it became apparent that more unsuitable soil needed to be removed than was initially anticipated, and the removal of additional soil increased the cost of the project. The construction project was substantially completed by December 2008 [161]*161and was occupied by Respondent Celebrations of Columbia, LLC, of which Causey is also a member.

When Appellant did not receive final payment for the work, it filed a mechanic’s lien and a suit to foreclose the lien in March 2009, claiming a balance due under the construction contract in the amount of $114,158. Respondents denied any debt to Appellant and raised various counterclaims seeking $296,018 in damages for incomplete and faulty construction work.2

In March 2010, the circuit court ordered arbitration pursuant to an arbitration clause in the construction contract. The parties agreed for attorney James Bruner of Bruner Powell Wall & Mullins, LLC, of Columbia, to serve as the arbitrator, and arbitration was conducted November 2-4, 2010. The arbitrator determined Appellant was owed $68,160 under the contract, plus interest, attorney’s fees and costs.3 Although two engineers from GS2 — George Sembos and Chad Bruorton — testified as Appellant’s fact and expert witnesses during the arbitration hearings, GS2 was not a party to the arbitration proceedings.

On February 3, 2011, Respondents filed their first motion to vacate the award, seeking to have it set aside based on several unfavorable evidentiary rulings and general allegations that the arbitrator manifestly disregarded the law. A hearing was conducted on February 14, 2011. At the conclusion of the hearing, the circuit court instructed the parties that it would deny Respondents’ motion to vacate and instructed Appellant’s counsel to prepare an order confirming the arbitration award. However, before an order was entered, Respondents learned “by happenstance” that an engineer employed by GS2, Jayson Floyd, was the brother of one of the arbitrator’s law partners, [162]*162Joey Floyd. As a result, on March 20, 2011, Respondents filed a supplemental motion to vacate the arbitration award, reiterating their previous arguments and raising several new claims, including that the arbitrator’s failure to disclose his law partner’s familial relationship with an employee of GS2 amounted to “evident partiality,” requiring the award to be set aside.

The circuit court granted the motion to vacate the arbitration award, finding the arbitrator had a duty to discover and disclose his law partner’s familial relationship with a GS2 employee and that the arbitrator’s failure to do so was tantamount to evident partiality. In finding vacatur was warranted, the circuit court held the relevant legal standard for analyzing claims of evident partiality under section 15-48-130 is not the language of the statute itself, but rather, is the standard set forth in the South Carolina Code of Ethics for Arbitrators, which requires disclosure of any relationship that “might reasonably create an appearance of partiality or bias.”4 The circuit court concluded that the undisclosed relationship was “clearly the type of relationship” that created an appearance of partiality and, therefore, the award should be set aside. As an alternative holding, the circuit court found that, even if the “appearance of bias” standard was not applicable and the appropriate legal standard was that of the Fourth Circuit Court of Appeals in ANR Coal Co. v. Cogentrix of North Carolina,5 Respondents met their burden of proving evident partiality. In so finding, the circuit court noted the existence of the undisclosed relationship and several unfavorable evidentiary rulings and vacated the arbitration award, concluding that, on the whole, the arbitrator’s conduct demonstrated evident partiality in favor of Appellants.

Following the circuit court’s denial of Appellant’s motion to alter or amend, this appeal followed. The matter was certified to this Court pursuant to Rule 204(b), SCACR.

II.

The circuit court’s adoption of a legal standard for evaluating claims of evident partiality under section 15-48-130 [163]*163is a question of law which we review de novo. See Town of Summerville v. City of N. Charleston, 378 S.C. 107, 110, 662 S.E.2d 40, 41 (2008) (“Determining the proper interpretation of a statute is a question of law, and this Court reviews questions of law de novo.”); Catawba Indian Tribe of S.C. v. State, 372 S.C. 519, 524, 642 S.E.2d 751, 753 (2007) (“We are free to decide a question of law with no particular deference to the circuit court.”).

Nevertheless, “ ‘[generally, an arbitration award is conclusive and courts will refuse to review the merits of an award.’ ” C-Sculptures, LLC v. Brown, 403 S.C. 53, 56, 742 S.E.2d 359, 360 (2013) (quoting Gissel v. Hart, 382 S.C. 235, 241, 676 S.E.2d 320, 323 (2009)). “An award will be vacated only under narrow, limited circumstances.” Id. “The judiciary should minimize its role in arbitration as judge of the arbitrator’s impartiality.” Commonwealth Coatings Corp. v. Cont’l Cas. Co., 393 U.S. 145, 151, 89 S.Ct. 337, 21 L.Ed.2d 301 (1968) (White, J., concurring). In reviewing arbitration awards, “the standards for judicial intervention are ... narrowly drawn to assure the basic integrity of the arbitration process without meddling in it.” Merit Ins. Co. v. Leatherby Ins. Co., 714 F.2d 673, 681 (7th Cir.1983). “The reasons for this are not hard to identify.” In re Andros Compañía Maritima, S.A.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Garofalo v. Di Vincenzo
Supreme Court of Virginia, 2026
Earl Hewlette v. Paula Hewlette
Court of Appeals of South Carolina, 2024
J. Don Gordon Construction, Inc. v. Brown
196 So. 3d 228 (Supreme Court of Alabama, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
747 S.E.2d 482, 405 S.C. 155, 2013 WL 4082358, 2013 S.C. LEXIS 200, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crouch-construction-co-v-causey-sc-2013.