Criton Corp. v. Highlands Insurance Co.

809 S.W.2d 355, 1991 Tex. App. LEXIS 1185, 1991 WL 74846
CourtCourt of Appeals of Texas
DecidedMay 9, 1991
DocketB14-90-608-CV
StatusPublished
Cited by32 cases

This text of 809 S.W.2d 355 (Criton Corp. v. Highlands Insurance Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Criton Corp. v. Highlands Insurance Co., 809 S.W.2d 355, 1991 Tex. App. LEXIS 1185, 1991 WL 74846 (Tex. Ct. App. 1991).

Opinion

OPINION

JUNELL, Justice.

In a non-jury trial the court rendered judgment in favor of the appellees Layton Bridge Company (Layton) and its surety, Highlands Insurance Company (Highlands). Appellant alleges error concerning attorneys’ fees and insufficient evidence. We affirm.

On October 20, 1986, Layton and Criton executed a Purchase Order which formed the basis for a subcontract. Layton was the general contractor in a bridge building project for Harris County, Texas. Highlands was Layton’s surety on the project and provided the statutory performance and payment bonds. Criton negotiated with Layton to act as a subcontractor to provide pedestrian rails and automobile guard rails for the bridge project. The price of the subcontract between Layton and Criton was $96,014.04. Criton was to provide the necessary materials and men to install the pedestrian rails and guard rails. Although the purchase order, i.e. contract, was executed in October of 1986, Criton’s work was not required until November of 1987. 1

Criton commenced actual work on or about November 5, 1987. The activities contemplated by the contract consisted of placing upright metal standards on anchor plates, supplied by Criton but installed by Layton, and then bolting on the guard rail. The rest of the facts are in dispute. Criton claims that when it went out to do the work, the anchor plates were not set to the spacing, 6'3", which had been specified in the plans. Criton contends that because of this it was necessary to burn holes in the rail in order to be able to bolt the rails to the standards. Criton claims that Layton’s foreman told Criton to “make it fit.” 2 Cri-ton did “make it fit” by burning holes.

Layton contends that Criton simply botched the beginning of the job, and carried the same mistake throughout. Lay-ton’s position is that if Criton had done the job correctly at the start, it would have been unnecessary to burn the holes with the acetylene torch.

Criton claims that it went on with the work, uninterrupted, until approximately one half day of work remained. At that point, Criton complains that Layton summarily removed Criton from the job without prior complaint. Criton contends that it wanted an opportunity to correct the work, if necessary, and complete the job. Layton claims that Criton refused to acknowledge that the work was defective, much less correct it. What is undisputed is that the Harris County inspector refused to accept the work because of the burned holes.

Approximately 660 feet of bridge rail was required to be removed and replaced due to the excessive holes being burned into the rail. Layton removed and replaced the work at a cost of $12,525.10. As it turns out, Layton was able, by replacing *357 the work itself, to do the job for $90,244.17. The original contract price being $96,-014.04, Layton actually saved $5,769.87. Layton pled this amount into the Registry of the Court claiming that this was the only monies due to Criton from the contract.

Criton filed this suit alleging breach of the subcontract and quantum meruit in the alternative. Layton responded by general denial and alleged affirmative defenses of payment and offset. Layton also claimed that Criton had breached the subcontract and thus it was entitled to attorneys’ fees under Tex.Civ.PRAc. & Rem.Code Ann. § 38.001. The trial court granted judgment in favor of Layton, and awarded the amount in the Registry to Criton to be offset against the $13,000 awarded to Lay-ton in attorneys’ fees.

In its first three points of error appellant contends, for various reasons, that Layton was not entitled to attorneys’ fees. Cri-ton’s basic contention is that Layton had no claim upon which to prevail, thus, it cannot be the prevailing party entitled to attorneys’ fees under Tex.Civ.PRAc. & Rem.Code Ann. § 38.001. Further, appellant argues that appellees failed to comply with the procedural requirements of Tex.Civ.Prac. & Rem.Code Ann. § 38.002. Specifically, Cri-ton claims that Layton failed to plead and prove presentment of a contract claim.

We will first discuss appellant’s contention that Layton had no claim and was therefore not a prevailing party entitled to attorneys’ fees.

In its Second Amended Original Answer and First Amended Counterclaim, Layton first made a general denial. Then, Layton made specific denials and allegations as to the work done by Criton. Most importantly, Layton alleged that Criton had breached the subcontract and damaged Layton. Layton requested damages caused by the breach. After a general denial and claims that Criton breached the contract, Layton asserted the affirmative defenses of payment and offset. Layton also requested attorneys’ fees pursuant to the Texas Civil Practice and Remedies Code.

It has been consistently held in Texas that the purpose of pleadings is to define the issues at trial and give the opposing party fair and adequate notice of the pleader’s contentions. Murray v. O & A Express, Inc., 630 S.W.2d 633 (Tex.1982); Tennell v. Esteve Cotton Co., 546 S.W.2d 346 (Tex.Civ.App.—Amarillo 1976, writ ref’d n.r.e.); Yeager Electric & Plumbing, Inc. v. Ingleside Cove Lumber & Builders, 526 S.W.2d 738 (Tex.Civ.App.—Corpus Christi 1975, no writ). Further, the substance of a pleading for relief should be looked to to determine the nature of the pleading, not merely the form or title given to it. State Bar of Texas v. Heard, 603 S.W.2d 829 (Tex.1980).

A substantive reading of the pleading filed by Layton reveals that Layton did have a contract claim against Criton. Lay-ton’s pleading claimed that Criton had breached the subcontract causing damage to Layton. Thus, Criton’s argument that Layton did not seek affirmative relief and damages and is therefore not entitled to attorneys’ fees is not supported by the record. Further, at trial, Layton presented evidence that Criton had breached the subcontract and caused money damages to Layton.

Having determined that Layton did have a claim against Criton, the question remains as to whether Layton was the prevailing party on the claim. Black’s Law Dictionary, Revised Fourth Edition defines “prevailing party” as:

That one of the parties to a suit who successfully prosecutes the action or successfully defends against it, prevailing on the main issue, even though not to the extent of his original contention.

In this action, the main issue was which party breached the subcontract. The trial court specifically found that Criton had breached the subcontract and damaged Layton in that Layton was required to repair and complete the bridge rails. Where a general contractor recovers the amount necessary to complete the contract less the amount the general contractor retains, the general contractor is the prevailing party entitled to attorneys’ fees. Davis Masonry, Inc. v. B-F-W Construction Co., Inc.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

in Re Richard Stephen Calkins
Court of Appeals of Texas, 2015
Design Electric v. Cadence McShane Corporation
Court of Appeals of Texas, 2007
Lacey Kersey v. State
Court of Appeals of Texas, 2006
Flagship Hotel, Ltd. v. City of Galveston
117 S.W.3d 552 (Court of Appeals of Texas, 2003)
Flagship Hotel, Ltd. v. the City of Galveston
Court of Appeals of Texas, 2003
In Re JNF
116 S.W.3d 426 (Court of Appeals of Texas, 2003)
In the Interest of J.N.F and J.M.F.
116 S.W.3d 426 (Court of Appeals of Texas, 2003)
Hawkins v. Ehler
100 S.W.3d 534 (Court of Appeals of Texas, 2003)
Robert Lee Hawkins v. Terry Lynn Ehler
Court of Appeals of Texas, 2003
Exxon Corp. v. Breezevale Ltd.
82 S.W.3d 429 (Court of Appeals of Texas, 2002)
Vingcard A.S. v. Merrimac Hospitality Systems, Inc.
59 S.W.3d 847 (Court of Appeals of Texas, 2001)
Seelbach v. Clubb
7 S.W.3d 749 (Court of Appeals of Texas, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
809 S.W.2d 355, 1991 Tex. App. LEXIS 1185, 1991 WL 74846, Counsel Stack Legal Research, https://law.counselstack.com/opinion/criton-corp-v-highlands-insurance-co-texapp-1991.