Cray Research, Inc. v. Department of Navy

556 F. Supp. 201, 31 Cont. Cas. Fed. 71,185, 1982 U.S. Dist. LEXIS 9914
CourtDistrict Court, District of Columbia
DecidedOctober 6, 1982
DocketCiv. A. 82-2512
StatusPublished
Cited by6 cases

This text of 556 F. Supp. 201 (Cray Research, Inc. v. Department of Navy) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cray Research, Inc. v. Department of Navy, 556 F. Supp. 201, 31 Cont. Cas. Fed. 71,185, 1982 U.S. Dist. LEXIS 9914 (D.D.C. 1982).

Opinion

MEMORANDUM

GESELL, District Judge.

This case involves a challenge to the procurement of a computer to be used for analysis and prediction of weather conditions worldwide by the United States Department of the Navy (“Navy”). After competitive bidding, in which plaintiff Cray Research, Inc. (“Cray”) competed but lost, the contract to supply the computer was awarded to Control Data Corporation (“CDC”) as the lowest bidder and an agreement between CDC and the Navy was signed on July 5, 1979. CDC delivered and installed a Cyber 203 model computer in December, 1980. The contract between CDC and Navy required that the computer pass four benchmark performance tests before it was finally accepted. 1 While the 203 passed three of the four performance tests in December, 1980, it proved unable to pass the fourth, Benchmark A, despite the Navy’s granting of several extensions of the time in which Benchmark A was to be completed.

Performance of the contract was endangered. CDC offered to replace the central memory and central processing unit of the 203 with newer, more advanced Cyber 205 equipment of far greater value to the Navy at additional cost. That proposal was rejected by the Navy. On March 26, 1982, CDC submitted a proposal to replace the *203 203 with the newer 205 at no additional cost. That proposal was accepted, with the 205 to be delivered and installed in November of 1982.

Cray has developed an ability to compete effectively for a procurement calling for a computer with Cyber 205 characteristics and claims the substitution of the 205 for the 203 constitutes an invalid sole-source procurement. It has filed a protest with the General Accounting Office (“GAO”), claiming that a major systems upgrade has occurred three years after the contract was let and that the Cyber 205 is a more advanced system for a more advanced purpose. The decision of the GAO is still pending. Meantime, Cray is before this Court on a motion for a preliminary injunction to prevent installation of the Cyber 205 until the GAO’s decision is available. Under the standards governing injunctive relief in government procurement cases, Cray’s request for a preliminary injunction must be denied.

Cray claims that if the 205 is installed Cray will be irreparably injured by loss of a major sale and the future business such a sale might engender, because after a procurement contract has been performed, a disappointed bidder’s only relief may be legal damages. But disappointed bidders seeking injunctive intervention in the procurement process must show more than the possibility of irreparable injury. They must show that contracting officials have taken action which is irrational or contravenes statutory limitations on the agency’s authority or the agency’s own regulations. “Only when the court concludes that there has been a clear violation of duty by the procurement officials should it intervene in the procurement process... . [C]ourts should be reluctant to intervene absent a clear showing of illegality by the party attempting to overturn the agency determination.” M. Steinthal & Co. v. Seamans, 455 F.2d 1289, 1303 (D.C.Cir.1971).

Cray has failed by a considerable margin to make such a clear showing. Cray makes no challenge to the original bid process, but rather suggests that the replacement of the 203 with the 205 is such a “cardinal change” in the provisions of the original contract as to constitute, in effect, a completely new sole source procurement in violation of the competitive bid process. Cray relies on the improved technology of the 205 as grounds for its contention that the contract between CDC and the Navy has been so modified as to become a new contract altogether.

It is undisputed, however, that even with the substitution of the 205 equipment both the specifications and the price of the original contract between the Navy and CDC remain unaltered. The original contract never required CDC to provide the 203 model; it simply required CDC to provide a model meeting certain performance requirements. If the 205 not only meets, but exceeds, those performance requirements, the Navy has done no more than accept the windfall CDC has offered. Such action does not constitute the clear showing of illegality necessary to justify judicial intervention in the procurement process.

The “cardinal change” doctrine prevents government agencies from circumventing the competitive procurement process by adopting drastic modifications beyond the original scope of a contract. The basic standard is whether the modified contract calls for essentially the same performance as that required by the contract when originally awarded so that the modification does not materially change the field of competition. Webcraft Packaging, Division of Beatrice Foods Co., B-194086, 79-2 CPD 1120 (Aug. 14,1979). Air-A-Plane Corp. v. United States, 408 F.2d 1030, 1033 (Ct.Cl.1969). Necessarily this must be resolved on a case-by-case basis.

In this case, the only “change” that has occurred in the contract is that CDC has elected to replace equipment which failed to meet performance tests with equipment that does meet those specifications, rather than default. None of the cases cited by Cray stretch the cardinal change doctrine to bar this result. Those cases all appear to deal with circumstances in which the procuring agency has either altered its demand *204 specifications during contract performance, or adjusted price or payment terms after the contract was awarded, and thus are not squarely on point. See, e.g., Memorex Corp., B-200722, 81-2 CPD ¶ 334 (October 23, 1981) (change of contract from purchase to lease-to-ownership plan is cardinal change requiring competitive procurement); U.S. Financial Services, Inc., B-197082, 81-2 CPD ¶ 104 (August 7, 1981) (renewal of lease requires competitive process); Webcraft Packaging, Division of Beatrice Foods Co., B-194087, 79-2 CPD ¶ 120 (August 14, 1979) (relaxation of contract specifications after award is cardinal change). When neither price nor specifications have been altered, the field of competition cannot have materially changed. 2

Cray also suggests that the Navy itself believes use of the 205 to be a cardinal change because Navy officials had represented at one point that replacement of the 203 central memory and central processing unit should be done on a competitive basis. The alleged statements do not support Cray’s argument because the statements, whatever their binding effect, were made before CDC offered the 205 to the Navy at no additional cost. Navy statements questioning the legality of a modification resulting in change in contract terms have no relevance to a proposed modification that does not involve such changes.

Even if Cray had made a clear showing of illegality, injunctive relief would still be inappropriate in this case because the Navy has shown that a delay in the installation of the Cyber 205 is contrary to the public interest in a strong national defense. M. Steinthal, supra at 1302;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J.A. Jones Construction Co. v. Lehrer McGovern Bovis, Inc.
89 P.3d 1009 (Nevada Supreme Court, 2004)
Graphicdata, LLC v. United States
41 Cont. Cas. Fed. 77,110 (Federal Claims, 1997)
Miller Elevator Co. v. United States
39 Cont. Cas. Fed. 76,635 (Federal Claims, 1994)
LK Comstock & Co., Inc. v. Becon Const. Co., Inc.
932 F. Supp. 906 (E.D. Kentucky, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
556 F. Supp. 201, 31 Cont. Cas. Fed. 71,185, 1982 U.S. Dist. LEXIS 9914, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cray-research-inc-v-department-of-navy-dcd-1982.