Cover v. Platte Valley Public Power & Irrigation District

75 N.W.2d 661, 162 Neb. 146, 1956 Neb. LEXIS 39
CourtNebraska Supreme Court
DecidedMarch 16, 1956
Docket33807
StatusPublished
Cited by29 cases

This text of 75 N.W.2d 661 (Cover v. Platte Valley Public Power & Irrigation District) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cover v. Platte Valley Public Power & Irrigation District, 75 N.W.2d 661, 162 Neb. 146, 1956 Neb. LEXIS 39 (Neb. 1956).

Opinion

Chappell, J.

Plaintiff Noel Cover, in his own right and as assignee of Armour and Company, brought this action to recover for flood damages to their described personal property alleged to have been proximately caused by negligence of defendant, Platte Valley Public Power and Irrigation District, in the construction and maintenance of a flood *148 water drain under its canal. Defendant’s answer denied that it was negligent as claimed by plaintiff and alleged in effect that the sole proximate cause of any damages sustained by plaintiff was an act of God. Further, it alleged that in any event plaintiff was barred and estopped from proving or recovering any damages from defendant in his own right because with full knowledge of its underpass drain plaintiff had entered into a contract to purchase from defendant the south 60 acres located in the northwest quarter and that part of the southwest quarter of Section 9 lying just north of defendant’s canal, whereby plaintiff allegedly consented and agreed that the then existing underpass or drain could be maintained by defendant in its then condition and that plaintiff Cover would save defendant harmless from any damages caused thereby. Such lands will be hereinafter designated as the 60-acre tract. Plaintiff’s reply was a general denial.

Upon trial to a jury, the trial court held as a matter of law that under the provisions of the contract aforesaid, plaintiff Noel Cover could not recover any damages in his own right. Instruction No. 10 given by the trial court so informed the jury, and only the issue of plaintiff’s right as assignee of Armour and Company’s alleged damages to its interest in the personal property was submitted to the jury. In that regard, concededly Noel Cover and Armour and Company had been contractually engaged in a large sheep feeding and marketing venture whereby Cover was to receive 30 percent of the profits and be liable for 30 percent of the losses, which in any event should not exceed $25,000 in any one year, while Armour and Company was to receive 70 percent of the profits and be liable for 70 percent of the losses. However, Armour and Company had concededly assigned to plaintiff all of its rights, interests, claims, and demands against defendant which it might have by reason of any damages caused by the alleged flooding on or about June 21 and *149 22, 1947. Therefore, if plaintiff was entitled to recover in his own right he was also entitled to have submitted and recover in one verdict the total amount of the damages sustained without confusing the jury in any manner by requiring it to ascertain any percentage of the loss individually sustained by either Cover or Armour and Company. As the issues were thus submitted, the jury returned a verdict finding for defendant, and judgment was rendered thereon. Subsequently plaintiff’s motion for new trial was overruled and he appealed, assigning some 38 errors. Some of them were not argued and they will not be discussed. Those argued may be summarized as assigning: (1) That the trial court erred in holding as a matter of law that plaintiff Cover could not recover in his own right and in so instructing the jury; (2) that the trial court erred in the admission of certain evidence; and (3) that the trial court erred in the giving and refusal to give certain instructions. We sustain the assignments in the manner hereinafter set forth.

The record is voluminous and contains numerous photographs offered and received for the purpose of identifying the place where the flood occurred and the extent thereof. We need only summarize pertinent parts of the evidence as they relate to the assignments of error. The property alleged to have been damaged was some 26,000 sheep, 60 tons of feed, and 3 electric pump motors, all located on the northeast quarter of Section 8, and 220 tons of alfalfa and 1 electric pump motor, all located on the north 100 acres of the northwest quarter of Section 9. Said lands belonged to plaintiff Cover and none of the personal property claimed to have been damaged was located on the 60-acre tract contractually purchased by plaintiff from defendant. Any question with reference to the amount of the damages is not an issue for determination here. It is sufficient for us to say that the extent thereof was not controverted by defendant. Such damages resulted *150 from the flooding of plaintiff’s lands on June 21 and 22, 1947, when intersecting floodwaters backed up, completely inundating plaintiff’s lands except for a few knolls, which waters failed to escape for several days thereafter.

Admittedly defendant, a public corporation, owned and operated an irrigation canal along the south line of the northeast quarter of Section 8 and extending on eastward along the south line of the 60-acre tract contractually purchased by plaintiff from defendant. In other words, the south side of the 60-acre tract is adjacent to defendant’s canal and at about the center thereof defendant had constructed and maintained a 42-inch corrugated drain pipe under its canal for the purpose of draining away all intersecting waters flowing down' the Stump Ditch and Spring Creek drainage area from the north and west. Spring Creek is a natural drainway about 5 feet deep and 200 feet wide into which overflow waters from Stump Ditch have been diverted. They drain about 30,000 acres of land, extending over an area of some 20 to 30 miles north and west of the point where Spring Creek was intercepted by defendant’s canal. The 42-inch drain has a capacity of only 9.62 square feet which was both factually and as a matter of law inadequate to drain all intersecting waters that might be reasonably anticipated to drain through it. In that regard, such drain is now substantially in the' identical condition that it was on January 31, 1947, when this court in Faught v. Platte Valley Public Power & Irr. Dist., 147 Neb. 1032, 25 N. W. 2d 889, held that it was not adequate to permit the passage of all waters which defendant should have reasonably anticipated might drain through it, and that defendant was negligent in the construction and maintenance thereof because it violated the rule ’that: “It is the duty of those who build structures across natural drain-ways to provide for the natural passage through such obstruction of all waters which may be reasonably *151 anticipated to drain there. This is a continuing duty.”

In such case we specifically held that Faught, plaintiff therein, was entitled to a mandatory injunction requiring defendant to increase the carrying capacity of such 42-inch drain under its canal to an extent sufficient to carry off all waters flowing down Spring Creek on said plaintiff’s land. That case involved 70 acres of land immediately north of and adjacent to deféndant’s canal and drain thereunder. Evidently instead of increasing the carrying capacity of the 42-inch drain as ordered, defendant purchased the south 60 acres of such tract lying immediately north and adjacent to its canal and thereafter contractually sold same to plaintiff Noel Cover. The contract, exhibit No. 30, was offered and received in evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bristol v. Rasmussen
547 N.W.2d 120 (Nebraska Supreme Court, 1996)
Thomas v. Weller
281 N.W.2d 790 (Nebraska Supreme Court, 1979)
Peterson v. Nebraska Natural Gas Co.
281 N.W.2d 525 (Nebraska Supreme Court, 1979)
Dempsey v. City of Souris
279 N.W.2d 418 (North Dakota Supreme Court, 1979)
Crnkovich v. Scaletta
277 N.W.2d 416 (Nebraska Supreme Court, 1979)
County of Sarpy v. Iske
204 N.W.2d 146 (Nebraska Supreme Court, 1973)
Northwestern Bell Telephone Co. v. Henry Carlson Co.
165 N.W.2d 346 (South Dakota Supreme Court, 1969)
Farnes v. Freeman Lane
161 N.W.2d 297 (Supreme Court of Minnesota, 1968)
City of Tucson v. Wondergem
435 P.2d 77 (Court of Appeals of Arizona, 1967)
Kuffel v. Kuncl
150 N.W.2d 908 (Nebraska Supreme Court, 1967)
Cover v. Platte Valley Public Power & Irrigation District
115 N.W.2d 133 (Nebraska Supreme Court, 1962)
Nebraska Bottled Gas & Appliance Co. v. Aetna Casualty & Surety Co.
112 N.W.2d 740 (Nebraska Supreme Court, 1962)
Hill v. Stokely-Van Camp, Inc.
109 N.W.2d 749 (Supreme Court of Minnesota, 1961)
Baum v. County of Scotts Bluff
109 N.W.2d 295 (Nebraska Supreme Court, 1961)
Armbruster v. Stanton-Pilger Drainage District
100 N.W.2d 781 (Nebraska Supreme Court, 1960)
Wischmann v. Raikes
97 N.W.2d 551 (Nebraska Supreme Court, 1959)
McDonald v. Spokane County
336 P.2d 127 (Washington Supreme Court, 1959)
County of Keith v. Triska
95 N.W.2d 350 (Nebraska Supreme Court, 1959)
In Re Pike's Estate
95 N.W.2d 350 (Nebraska Supreme Court, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
75 N.W.2d 661, 162 Neb. 146, 1956 Neb. LEXIS 39, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cover-v-platte-valley-public-power-irrigation-district-neb-1956.