Armbruster v. Stanton-Pilger Drainage District

100 N.W.2d 781, 169 Neb. 594, 1960 Neb. LEXIS 139
CourtNebraska Supreme Court
DecidedJanuary 15, 1960
Docket34614
StatusPublished
Cited by55 cases

This text of 100 N.W.2d 781 (Armbruster v. Stanton-Pilger Drainage District) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Armbruster v. Stanton-Pilger Drainage District, 100 N.W.2d 781, 169 Neb. 594, 1960 Neb. LEXIS 139 (Neb. 1960).

Opinion

*597 Chappell, J.

This case is here on appeal a second time. Our former opinion is reported as Armbruster v. Stanton-Pilger Drainage Dist., 165 Neb. 459, 86 N. W. 2d 56. Therein plaintiffs, Bert Armbruster and Irene Armbruster, his wife, appealed, and we reversed the judgment of the trial court which had dismissed plaintiffs’ amended and supplemental petition on motion of defendant, Stanton-Pilger Drainage District, at conclusion of plaintiff’s case. We then remanded the cause for new trial. Plaintiffs’ action sought a mandatory injunction and damages against defendant. Hereinafter, when referring to Bert Armbruster alone he will be called plaintiff, and when referring to both plaintiffs, they will be so designated.

Except on the issues of plaintiffs’ alleged release of their claim for damages and their alleged estoppel to claim the same, this, appeal will be considered in the light of the applicable and controlling rules appearing in Snyder v. Lincoln, 156 Neb. 190, 55 N. W. 2d 614, which held that: “When this court determines the law of the case on appeal, the trial court is bound thereby and its judgment in accordance therewith will not ordinarily be disturbed on a subsequent appeal.” Generally, however, if other and different issues of fact and of law relating thereto have been properly adduced and presented in a new trial, the law of the case is not controlling thereof in a subsequent appeal. It would serve no useful purpose here to restate the determined rules of law which appear in our first opinion as syllabus points 2 to 8 inclusive. The entire record, including all evidence adduced by plaintiffs at the first trial together with all evidence adduced by the parties at the new trial, is now before this court for consideration.

To clarify the situation, we point out that this case involved the alleged interference with and diversion by defendant of waters flowing in a small natural stream known as Cedar Creek, hereinafter called the creek, *598 which caused damages to plaintiffs’ land by erosion of said creek. In that connection, it is undisputed that prior, during, and subsequent to 1950, plaintiffs were joint owners of the north half of a described section of land in Stanton County. Prior to 1950, the creek entered plaintiffs’ land from the south at a point near the southeast corner, then flowed 3,960 feet north and northwest, then left plaintiffs’ land at their north line under a county bridge which spanned the creek on an east and west county road, thence flowed on north over land of another and emptied into the Elkhorn River, which flowed generally from east to west in a meandering course about 2,200 feet north of plaintiffs’ north line.

It was stipulated as follows: That a petition to form defendant district under the' provisions of sections 31-401 to 31-450, R. R. S. 1943, inclusive, was filed August 19, 1949. It was signed by 12 named persons other than plaintiffs. The same day a statutory bond was filed which was signed by all such named persons except one. On October 11, 1949, five named directors other than plaintiffs were elected, who all continued to serve defendant as such for more than 5 years thereafter. On October 24, 1949, such directors instructed defendant’s engineer, theretofore employed by them, to ■ prepare ' detailed plans, specifications, and cost estimates for the construction of a pilot channel, hereafter called ditch, with which to straighten the channel of the Elk-horn River. On February 9, 1950, such plans, specifications, and cost estimates were presented to defendant’s directors, who approved and adopted a proposed plan which provided for the construction' of a ditch 34 feet wide at the top, 24 feet wide at the bottom, and 10 feet deep, with a right-of-way 100 feet wide on each side, and such plans were left at all times thereafter in the custody of defendant’s lawyer. In that connection, it is undisputed that ho part of plaintiffs’ land was within the boundaries of the district except plaintiffs’ described northwest 40 acres, and plaintiffs’ land, through which *599 the creek flowed and on which damages directly occurred by erosion, was entirely outside the boundaries of. the district.

The record discloses that in 1950 defendant constructed .the ditch over right-of-way acquired by it for the purpose of straightening the Elkhorn River channel and .to provide for the passage of waters which would otherwise have flowed through the old Elkhorn River channel. The ditch was constructed from west to east and then from east to west until it intersected or cut across the channel of the creek on land of another about. 990 feet north, of plaintiffs’ north line. The ditch, which was completed by defendant in November or December 1950, .was cut about 6 feet below the base or bed of Cedar ■ Creek and the Elkhorn River, which created a. waterfall 6 feet high where defendant’s ditch intersected the creek, and the water therefrom emptied into the ditch. The evidence is conclusive that thus such waterfall created by defendant naturally and directly caused the channel of the creek to substantially erode upstream in the creek, thus deepening and widening the creek and continuing to do so until it reached and entered plaintiffs’ land, and, as hereinafter observed, caused and continued to cause substantial and irreparable damage to ■plaintiffs’ land and the use thereof, and to plaintiffs’ improvements and structures on their land.

Before such erosion caused by the waterfall had reached plaintiffs’ land, and before any material damage had been caused on their land, plaintiffs notified defendant of the apparent progressive damage which had already manifested itself on the land of another north of plaintiffs. However, although there were and are standard, practical, feasible, and effective structures, means, and methods by which defendant could -have built, and thereby arrested and prevented the damage ■to plaintiffs which naturally ensued, occurred, has continued, and will continue to occur through all 3,960 ■feet of plaintiffs’ land unless prevented, defendant has *600 failed and refused to employ any such means or methods. On June 27, 1952, before damages had occurred on plaintiffs’ land, they filed an original petition against defendant, praying for a mandatory injunction and requiring defendant to build some such structure in the bed and channel of the creek to prevent further erosion to and upon plaintiffs’ land. While such action was pending, the waterfall had eroded into plaintiffs’ land for some distance, deepening, widening, and eroding the bed and banks of the creek and causing substantial and irreparable damage to plaintiffs’ land and the use thereof, and to some improvements and structures on plaintiffs’ land.

In the meantime, about August 25, 1952, plaintiffs consulted with and employed an engineer, and, as advised by him, plaintiffs expended some $7,267.74 in the respective construction of three separate piling structures in the creek on plaintiffs’ land, thereby attempting to prevent further erosion and damages, but each of such structures eventually washed out during heavy rains and failed to stop the continued erosion. Plaintiffs had also expended substantial sums to protect, remove, or repair the property and improvements on their land which had been damaged or were threatened by the erosion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Douglas Cty. Sch. Dist. No. 10 v. Tribedo, LLC
307 Neb. 716 (Nebraska Supreme Court, 2020)
Trimble v. BNSF Railway Co.
636 F. Supp. 2d 916 (D. Nebraska, 2009)
Hogelin v. City of Columbus
741 N.W.2d 617 (Nebraska Supreme Court, 2007)
Outlook Windows Partnership v. York International Corp.
112 F. Supp. 2d 877 (D. Nebraska, 2000)
Wyoming Realty Co. v. Cook
872 P.2d 551 (Wyoming Supreme Court, 1994)
Kula v. Prososki
424 N.W.2d 117 (Nebraska Supreme Court, 1988)
Parriott v. Drainage Dist. No. 6 of Peru
410 N.W.2d 97 (Nebraska Supreme Court, 1987)
Cracchiolo v. State
660 P.2d 494 (Court of Appeals of Arizona, 1983)
Thomas v. Weller
281 N.W.2d 790 (Nebraska Supreme Court, 1979)
Armbruster v. Stanton-Pilger Drainage District
280 N.W.2d 72 (Nebraska Supreme Court, 1979)
City of Omaha v. Matthews
248 N.W.2d 761 (Nebraska Supreme Court, 1977)
Swartz v. Topping
213 N.W.2d 718 (Nebraska Supreme Court, 1974)
Czarnick v. Loup River Public Power District
209 N.W.2d 595 (Nebraska Supreme Court, 1973)
Trausch v. Knecht
165 N.W.2d 738 (Nebraska Supreme Court, 1969)
Varney v. Taylor
448 P.2d 164 (New Mexico Supreme Court, 1968)
State, Department of Roads v. Merritt Bros. Sand & Gravel Co.
144 N.W.2d 180 (Nebraska Supreme Court, 1966)
Swanson v. Dalton
131 N.W.2d 704 (Nebraska Supreme Court, 1964)
Lansman v. STATE, DEPARTMENT OF ROADS
128 N.W.2d 569 (Nebraska Supreme Court, 1964)
Pieper v. City of Scottsbluff
126 N.W.2d 865 (Nebraska Supreme Court, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
100 N.W.2d 781, 169 Neb. 594, 1960 Neb. LEXIS 139, Counsel Stack Legal Research, https://law.counselstack.com/opinion/armbruster-v-stanton-pilger-drainage-district-neb-1960.