Couvillion Group LLC v. Quality First Construction, LLC

CourtDistrict Court, E.D. Louisiana
DecidedSeptember 11, 2020
Docket2:19-cv-00676
StatusUnknown

This text of Couvillion Group LLC v. Quality First Construction, LLC (Couvillion Group LLC v. Quality First Construction, LLC) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Couvillion Group LLC v. Quality First Construction, LLC, (E.D. La. 2020).

Opinion

UNITED STATES DISTRICT COURT

EASTERN DISTRICT OF LOUISIANA

COUVILLION GROUP, LLC CIVIL ACTION

VERSUS NO. 19-676-WBV-KWR

QUALITY FIRST SECTION: D (4) CONSTRUCTION, LLC

FINDINGS OF FACT and CONCLUSIONS OF LAW

This matter was tried before the Court without a jury on November 18, 2019. The Court has carefully considered the testimony of all of the witnesses and the exhibits entered into evidence during the trial, as well as the record in this matter. Pursuant to Rule 52 of the Federal Rules of Civil Procedure, the Court enters the following Findings of Fact and Conclusions of Law. To the extent that any finding of fact may be construed as a conclusion of law, the Court hereby adopts it as such. To the extent that any conclusion of law may be construed as a finding of fact, the Court adopts it as such. Findings of Fact 1. Plaintiff, Couvillion Group, LLC (“Couvillion”) is a limited liability company organized under the laws of the States of Louisiana with its domicile address in Plaquemines Parish, Louisiana. 2. Timothy Couvillion is the CEO and one of the owners of Couvillion Group, LLC. 3. Okbel Guillen is the office manager and accounts receivable person for Couvillion. 4. Couvillion Group, LLC is a Louisiana contractor providing various marine services, including but not limited to marine construction, salvage, repair and maintenance in the marine industry.

5. Defendant, Quality First Construction LLC d/b/a Quality First Marine (“QFM”) is a Louisiana limited liability company headquartered in St. Tammany Parish, Louisiana. 6. At the time of the 2017 project at issue in this case, Darryl Couvillion was an owner and the Operations Manager of QFM.1 7. Darryl Couvillion is Timothy Couvillion’s brother.

8. As the Operations Manager, Darryl Couvillion had the authority to negotiate and bind contracts on behalf of QFM. 9. The President and majority owner of QFM at the time of the underlying project was Christina Couvillion, the former spouse of Darryl Couvillion. 10. Michael Ashcraft was QFM’s project manager for the project. 11. QFM provides marine construction, marine transportation/logistics and other services to the marine industry.

12. At the time of the 2017 project, Couvillion and QFM had an existing work relationship and had previously worked together on many projects for several years.

1 In October 2017, Darryl Couvillion was terminated from QFM by his ex-wife and majority QFM owner, Christina Couvillion. 13. During those prior projects, Darryl Couvillion of QFM gave verbal authorizations for work to be performed by Couvillion, which work was subsequently paid by QFM.

14. In January 2017, QFM contracted with the United States Army Corps of Engineers (“USACE”) for a project known as the Caernarvon Sector Gate Project (“the 2017 Project”) in St. Bernard Parish, Louisiana. 15. The 2017 Project involved the relocation of a hydraulic steel flood control gate along the Mississippi River. 16. Couvillion submitted a Lump Sum Proposal/Day Rate Proposal to QFM,

wherein Couvillion proposed that it could provide equipment/personnel to QFM for the 2017 Project for a lump sum of $164,735.2 17. QFM accepted Couvillion’s proposal. 18. In order to perform this project, on or about January 24, 2017, QFM entered into a Subcontract Agreement with Couvillion, wherein Couvillion would, “Furnish all labor, equipment, supplies and material for performing all operations necessary, for installing, dewatering, monitoring, rewatering and

removing dewatering components for the Hydraulic Steel Structure.”3 19. Paragraph 2 of the subcontract states: “Price. Contractor [QFM] shall pay Subcontractor [Couvillion] for the due and full performance of the Work based

2 Trial Exhibit 3. 3 Trial Exhibit 1, Schedule A. on the amounts reflected in Schedule C (“The Price”). Any variations of the price must be based on mutual written consent of the parties.”4 20. Schedule C, attached to the Subcontract, reflects the price of $164,735.

21. The $164,735 price was the same price in Couvillion’s Lump Sum Proposal initially provided to QFM.5 22. Paragraph 8 of the Subcontract provides that: Contractor [QFM] may . . . order extra or additional work, deletions, or other modifications to the Work, such changes to be effective only upon written order of Contractor. Any adjustment to the Price or to the time for completion of the Work shall be made in accordance with the applicable provisions of the Contract, or in the absence of such provisions, on an agreed or equitable basis. Notwithstanding any inability to agree upon any adjustment or the basis for an adjustment, Subcontractor shall, if desired by Contractor, nonetheless proceed in accordance with the order, and the Price and time of completion shall be adjusted in accordance with the foregoing.”6

23. QFM and Couvillion also entered into a written agreement for the use of a houseboat to support personnel working on the 2017 Project. 24. Under the “On Hire/Time Charter Agreement” (“Charter Agreement”), Couvillion agreed to provide the houseboat to QFM for a flat rate of $72,508 to house and feed workers on the 2017 Project, including Couvillion’s workers.7 25. The Charter Agreement provides a start date of January 24, 2017.

4 Trial Exhibit 1. 5 Trial Exhibit 3. 6 Trial Exhibit 1. 7 Trial Exhibit 2. 26. Couvillion and QFM intended for the houseboat to be used for the duration of the 2017 Project, as agreed to in the Subcontract. 27. Couvillion was paid the $72,508 for the houseboat pursuant to the Charter

Agreement. 28. The 2017 Project experienced some delays associated with the inspections of welds on the flood gate and its components. 29. According to the parties, these delays were caused by the USACE and another subcontractor on the 2017 Project. 30. QFM requested that Couvillion keep the houseboat on site for QFM’s use

during the period of delay. 31. In written communication, QFM requested that Couvillion provide the day rate for the use of the houseboat during the period of delay. 32. Couvillion provided QFM a day rate of $1,500 for the additional days that QFM used the houseboat. 33. QFM requested that Couvillion provide an invoice for the use of the houseboat during the period of delay.

34. On May 31, 2017, Couvillion submitted an invoice to QFM in the amount of $37,500 which reflected the houseboat rental for an additional 25 days due to the delay.8 35. Couvillion provided the houseboat for QFM’s use for the additional 25 days.

8 Trial Exhibit 4. 36. QFM submitted Couvillion’s houseboat pricing to the USACE and received payment from the USACE for the use of the houseboat. 37. QFM has not paid Couvillion for the use of the houseboat during the additional

25 days. 38. Couvillion has not been paid by any party for the use of the houseboat during the standby delay period. 39. A third company, Crescent Coating and Services (“CCS”), was responsible for scaffolding and sand removal for the 2017 Project. 40. CCS was the blasting and painting subcontractor to QFM.

41. Couvillion performed all of the work requested by QFM for the 2017 Project pursuant to the Subcontract. 42. QFM requested that Couvillion provide additional equipment and services to address the delays caused by the USACE and CCS. 43. At the request of Darryl Couvillion, QFM’s owner and Operations Manager, Couvillion provided additional scaffolding services, work and labor to CCS. This additional work was outside of the Subcontract agreed to by the parties.

44. Couvillion performed the additional work requested by QFM, which included the use of a crane for scaffolding work. 45.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Taita Chemical Co. v. Westlake Styrene Corp.
246 F.3d 377 (Fifth Circuit, 2001)
Kossick v. United Fruit Co.
365 U.S. 731 (Supreme Court, 1961)
Vulcan v. Zapata Ugland Drilling, Inc.
553 F.2d 489 (Fifth Circuit, 1977)
Noritake Co., Inc. v. M/v Hellenic Champion
627 F.2d 724 (Fifth Circuit, 1980)
In Re Nicole Trahan
10 F.3d 1190 (Fifth Circuit, 1994)
Lewis v. Hamilton
652 So. 2d 1327 (Supreme Court of Louisiana, 1995)
Lantech Construction Co. v. Speed
15 So. 3d 289 (Louisiana Court of Appeal, 2009)
Tidewater Marine, Inc. v. Sanco International, Inc.
113 F. Supp. 2d 987 (E.D. Louisiana, 2000)
LLOG Exploration Company, LLC v. Signet Maritime C
673 F. App'x 422 (Fifth Circuit, 2016)
Roland Alonso v. Westcoast Corporation
920 F.3d 878 (Fifth Circuit, 2019)
Devin Barrios v. Centaur, L.L.C.
942 F.3d 670 (Fifth Circuit, 2019)
Driver Pipeline Co. v. Cadeville Gas Storage, LLC
150 So. 3d 492 (Louisiana Court of Appeal, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Couvillion Group LLC v. Quality First Construction, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/couvillion-group-llc-v-quality-first-construction-llc-laed-2020.