County of Suffolk v. United States

26 Cl. Ct. 924, 1992 U.S. Claims LEXIS 349, 1992 WL 179389
CourtUnited States Court of Claims
DecidedJuly 29, 1992
DocketNo. 570-86L
StatusPublished
Cited by4 cases

This text of 26 Cl. Ct. 924 (County of Suffolk v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
County of Suffolk v. United States, 26 Cl. Ct. 924, 1992 U.S. Claims LEXIS 349, 1992 WL 179389 (cc 1992).

Opinion

OPINION

ANDEWELT, Judge.

This action involves two related federal grant agreements1 between plaintiff, County of Suffolk, New York (Suffolk), and the United States Environmental Protection Agency (EPA) covering the design and construction of a waste water treatment project known as the Suffolk County Southwest Sewer District No. 3 (the Project). The agreements, entered pursuant to the Federal Water Pollution Control Act, 33 U.S.C. § 1251 et seq., obliged the EPA to pay a fixed percentage of “allowable” costs for the Project. In this action, plaintiff contends that the EPA improperly disallowed certain of the costs plaintiff incurred during construction of the Project. This action is presently before the court on cross-motions for partial summary judgment. For the reasons set forth below, defendant’s cross-motion is granted in part.

I.

The first issue to address is the weight to be given to the EPA’s determination that the costs in dispute were not allowable. Defendant previously had argued unsuccessfully that review of the EPA’s determination of allowable costs should be conducted under the standards set forth in the Administrative Procedure Act (APA), 5 U.S.C. § 704 et seq., for review of agency action, i.e., that the court must limit its inquiry to the administrative record and may not overturn the EPA’s determination unless it is found to be arbitrary, capricious, or not supported by substantial evidence. This court rejected applicability of the APA standard in an opinion authorizing plaintiff to conduct discovery beyond the administrative record. County of Suffolk v. United States, 19 Cl.Ct. 295 (1990) (Suffolk I).

In Suffolk I, the court explained that the grant agreements satisfy all of the traditional requirements for an enforceable contract (i.e., an offer, an acceptance, and consideration passing between the parties) and, therefore, the parties’ respective responsibilities should be evaluated based on a breach of contract analysis. As to that analysis, the court explained that breach of contract allegations generally are evaluated by this court on a de novo basis unless the parties limit the scope of this court’s inquiry through the inclusion of limiting provisions in the contract.2 Id. at 299. [927]*927Here, agency regulations incorporated into the contract had at one time specified a limited standard for judicial review of the agency’s determinations, but those regulations subsequently were modified to eliminate the specific reference to the judicial review standard. At the conclusion of Suffolk I, this court explained: “Since defendant has not cited any provision in the contract or controlling regulations that limits the scope of this court’s review of such a breach claim, the scope of this court’s review here will be the same as it would be for any other federal contract.” Id. at 300.

In its cross-motion, defendant points to a provision in the ’624 grant that would appear to limit the scope of judicial review of the EPA’s determination on cost allowability. The ’624 grant provides, in pertinent part:

The amount of the Federal grant will not exceed the appropriate percentage of the estimated reasonable cost of the project, as established by law, or such dollar limitation so established; provided, that in the event the actual reasonable cost of any project, as determined by the Commissioner [of the Federal Water Pollution Control Administration] upon completion of construction, is less than the estimated reasonable cost upon which the grant offer is based, such actual cost shall be used to determine the amount of the Federal grant, and the grant shall be reduced as necessary to conform with the limitations hereinabove cited.

Thus, the ’624 grant first delegates to the Commissioner the responsibility of making the determination as to what is the actual reasonable cost (“the actual reasonable cost ... as determined by the Commissioner” (emphasis added)), and then mandates that this actual reasonable cost as determined by the Commissioner be used in determining the total amount of the federal grant, which in turn controls the amount that plaintiff is entitled to receive under the contract. The Federal Water Pollution Control Administration later became part of the EPA and the authority of the Commissioner was vested in the Administrator of the EPA.

The Court of Claims has previously addressed analogous contractual provisions where the parties to a contract agree to give broad discretion to one of the parties to make a crucial factual determination under the contract. See e.g., John Reiner & Co. v. United States, 325 F.2d 438, 163 Ct.Cl. 381 (1963), cert. denied, 377 U.S. 931, 84 S.Ct. 1332, 12 L.Ed.2d 295 (1964); Knotts v. United States, 121 F.Supp. 630, 128 Ct.Cl. 489, 491 (1954). In Knotts, the court explained:

In innumerable cases it has been held that where discretion is conferred on an administrative officer to render a decision, this decision must be honestly rendered, and that if it is arbitrary or capricious, or rendered in bad faith, the courts have power to review it and set it aside. This court has this question presented to it constantly in cases arising under Government contracts, where the contracting officer and the head of the department are given the power to render final decisions on questions of fact. Both this Court and the Supreme Court have many times held that if the decision is arbitrary or capricious or so grossly erroneous as to imply bad faith, it will be set aside. See, e.g., Burchell v. Marsh, 17 How. 344, 349 [15 L.Ed. 96 (1854)]; Kihlberg v. United States, 97 U.S. 398 [24 L.Ed. 1106 (1878) ]; United States v. Gleason, 175 U.S. 588, 602 [20 S.Ct. 228, 233, 44 L.Ed. 284 (1900)]; Ripley v. United States, 223 U.S. 695, 701 [32 S.Ct. 352, 355, 56 L.Ed. 614 (1912) ].

121 F.Supp. 630, 128 Ct.Cl. at 491.

The EPA determined the “actual reasonable cost” pursuant to regulations which established the procedures for determining allowability of costs incurred by grant recipients.3 In view of the pertinent wording of the ’624 grant and the case law cited above interpreting analogous contract pro[928]*928visions, this court should not set aside the EPA’s determination as to the “actual reasonable cost” unless that determination “is arbitrary or capricious or so grossly erroneous as to imply bad faith.” Id.

II.

In its complaint, plaintiff attacks the EPA’s determination not to allow certain costs plaintiff incurred during the construction of the Project. In their respective cross-motions, the parties each seek summary judgment as to certain of these disputed costs. After oral argument, the parties reached a tentative settlement of all but one of the issues raised in the cross-motions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

27-35 Jackson Ave LLC v. United States
127 F.4th 1314 (Federal Circuit, 2025)
Reservation Ranch v. United States
42 Cont. Cas. Fed. 77,286 (Federal Claims, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
26 Cl. Ct. 924, 1992 U.S. Claims LEXIS 349, 1992 WL 179389, Counsel Stack Legal Research, https://law.counselstack.com/opinion/county-of-suffolk-v-united-states-cc-1992.