Cotton Commercial USA, Inc. v. Clear Creek Independent School District

387 S.W.3d 99, 2012 Tex. App. LEXIS 9150, 2012 WL 5395929
CourtCourt of Appeals of Texas
DecidedNovember 6, 2012
Docket14-12-00272-CV
StatusPublished
Cited by36 cases

This text of 387 S.W.3d 99 (Cotton Commercial USA, Inc. v. Clear Creek Independent School District) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cotton Commercial USA, Inc. v. Clear Creek Independent School District, 387 S.W.3d 99, 2012 Tex. App. LEXIS 9150, 2012 WL 5395929 (Tex. Ct. App. 2012).

Opinion

OPINION

SHARON McCALLY, Justice.

Appellant, Cotton Commercial USA, Inc. (hereinafter “SURVIVING COMPANY”), appeals the trial court’s order denying its motion to compel arbitration of appellee’s, Clear Creek Independent School District (hereinafter “the School District”), claims. We affirm, in part, and reverse and remand, in part.

I. Background

On September 8, 2012, the School District executed a “Restoration Service Agreement” with Cotton Commercial USA, L.P. d/b/a Cotton USA (hereinafter “CONTRACTOR”) for debris removal and remediation and restoration services to the School District’s school campuses after Hurricane Ike (the Restoration Agreement). 1 It is undisputed that the Restoration Agreement contained the following arbitration provision:

Any controversy, dispute or claim arising out of this Agreement or the Work done hereunder (which can not [sic] be amicably resolved by senior management representatives of Cotton and the Customer), shall first be submitted to non-binding mediation. Both parties .shall share equally in the expense of such mediation in which a non-interested mediator shall serve to facilitate the resolution of the dispute. If such controversy, dispute or claim can not [sic] be settled or resolved by non-binding mediation, either party may then submit such dispute to arbitration in accordance with the terms of this Article VII, provided, however, that in circumstances where equitable (non-monetary) relief is sought, such dispute may be submitted to a court of competent jurisdiction sitting in equity who may issue injunctive relief or other equitable remedy. 2

According to the School District’s amended petition, under the Restoration Agreement, CONTRACTOR was “to remove debris from its premises and perform remediation and restoration services following clean up.” The Restoration Agreement specifically authorized the use of subcontractors and provided for payment in accordance with a rate schedule. The Restoration Agreement also authorized the use of “a particular trade or service” on a “cost plus 10% overhead and 10% profit” basis if there was a “specific need” because CONTRACTOR did not provide those services.

The debris removal occurred from approximately September 18, 2008, through September 29, 2008. Remediation occurred through the end of October 2008. CONTRACTOR invoiced the School District, and its invoices reflected work performed by Cottonwood Debris Company, LLC (hereinafter “SUBCONTRACTOR”). The School District questioned the invoices; the relationship between CON *102 TRACTOR and SUBCONTRACTOR; and the characterization of SUBCONTRACTOR as a “subcontractor,” which gave rise to the higher billing under the Restoration Agreement.

CONTRACTOR sent its final invoice in December 2008, but persisted in billing SUBCONTRACTOR’S services as a subcontractor. The School District refused to pay the 20% markup associated with SUBCONTRACTOR’S characterization as a subcontractor because it had determined that SUBCONTRACTOR was an entity “closely related to” CONTRACTOR.

In the subsequent negotiations over SUBCONTRACTOR’S invoices, SUBCONTRACTOR provided the School District with documentation to support certain fuel charges billed by SUBCONTRACTOR. The School District determined that these were fraudulent or fabricated invoices. Further, SUBCONTRACTOR included in its billings a $6,000 per campus charge for “food disposal services.” SUBCONTRACTOR could not back these charges up with supporting documentation; the School District determined from its own records that the services had not been performed at all. SUBCONTRACTOR’S billings included a $170.73 per cubic yard charge for debris removal that was three times the cost permitted by Federal Emergency Management Agency (“FEMA”), to whom the School District was applying for reimbursement. The School District informed FEMA that it had concerns about the “authenticity of the underlying invoices from [SUBCONTRACTOR].” FEMA denied the School District’s application, resulting in the loss of $700,000 in FEMA reimbursements.

Prior to this suit, and as alleged in the School District’s petition, CONTRACTOR and SUBCONTRACTOR were “merged out of existence” to form SURVIVING COMPANY. Thus, when, on December 1, 2010, the School District filed suit arising from the previously described conduct by SUBCONTRACTOR, the School District named only SURVIVING COMPANY. Specifically, its claims are for fraud and money had and received.

On May 18, 2011, SURVIVING COMPANY filed its motion to stay and compel arbitration of the School District’s claims. In its motion to stay and to compel arbitration, SURVIVING COMPANY stated that it had not formally asserted its counterclaims for the School District’s failure to pay $705,123 in the action pending in the trial court because of the arbitration clause in the Restoration Agreement. Instead, in its draft statement of claim and demand for arbitration filed with the American Arbitration Association, which was attached to its motion to compel arbitration, SURVIVING COMPANY asserted causes of action for breach of contract and violations of the Prompt Pay Act for failing to pay $705,123.

On March 1, 2012, the trial court (1) denied SURVIVING COMPANY’S motion to stay and compel arbitration with respect to the School District’s claims against SURVIVING COMPANY; and (2) granted SURVIVING COMPANY’S motion to stay and compel arbitration with respect to SURVIVING COMPANY’S counterclaims against the School District.

On April 23, 2012, the trial court made the following findings of fact:

1. After Hurricane Ike made landfall, Clear Creek Independent School District (CCISD) and Cotton Commercial USA, L.P. d/b/a Cotton USA (Cotton USA) entered into a contract for hurricane remediation.
2. CCISD and Cotton USA’s contract contained on [sic] arbitration provision.
*103 3. Cotton USA employed a subcontractor, Cottonwood Debris Company, LLC, to perform some hurricane remediation for CCISD.
4. Cottonwood was not a party [to] or a signatory to the contract between Cotton USA and CCISD.
5. Cottonwood was not a party to or a signatory to the arbitration agreement between Cotton USA and CCISD.
6. Cottonwood and Cotton USA merged into a single entity in September 2010, Cotton Commercial USA, Inc. f/k/a Cottonwood Debris Company, LLC, (Cotton Commercial).
7. In December 2010, CCISD filed suit against Cotton Commercial asserting claims related to Cottonwood’s hurricane remediation work.
8. Cotton Commercial failed to present any evidence demonstrating that Cottonwood and CCISD were signatories to an arbitration agreement.
9. Cotton Commercial failed to present any evidence demonstrating that Cottonwood was an intended third-party beneficiary of the contract between CCISD and Cotton USA.

The trial court also reached the following conclusions of law;

1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Newman v. Plains All Amer Pipel
23 F.4th 393 (Fifth Circuit, 2022)
Black v. Diamond Offshore Drilling, Inc.
551 S.W.3d 346 (Court of Appeals of Texas, 2018)
Jody James Farms, Jv v. the Altman Group, Inc. and Laurie Diaz
547 S.W.3d 624 (Texas Supreme Court, 2018)
John Hays v. HCA Holdings, Incorporated
838 F.3d 605 (Fifth Circuit, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
387 S.W.3d 99, 2012 Tex. App. LEXIS 9150, 2012 WL 5395929, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cotton-commercial-usa-inc-v-clear-creek-independent-school-district-texapp-2012.