SpawGlass Civil Construction, Inc. v. Horizon Excavation, Inc. and the Hanover Insurance Company

CourtCourt of Appeals of Texas
DecidedJuly 23, 2024
Docket01-23-00829-CV
StatusPublished

This text of SpawGlass Civil Construction, Inc. v. Horizon Excavation, Inc. and the Hanover Insurance Company (SpawGlass Civil Construction, Inc. v. Horizon Excavation, Inc. and the Hanover Insurance Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SpawGlass Civil Construction, Inc. v. Horizon Excavation, Inc. and the Hanover Insurance Company, (Tex. Ct. App. 2024).

Opinion

Opinion issued July 23, 2024

In The

Court of Appeals For The

First District of Texas ———————————— NO. 01-23-00829-CV ——————————— SPAWGLASS CIVIL CONSTRUCTION, INC., Appellant V. THE HANOVER INSURANCE COMPANY, Appellee

On Appeal from the 165th District Court Harris County, Texas Trial Court Case No. 2023-22284

MEMORANDUM OPINION

Appellant SpawGlass Civil Construction, Inc. is the general contractor for a

public construction project in Houston, Texas. SpawGlass retained Horizon

Excavation, Inc. to perform work as a subcontractor for the project, and Appellee

Hanover Insurance Company issued a performance bond to guarantee Horizon’s performance. SpawGlass filed suit against Horizon and Hanover for breach of their

respective contracts, and it later moved to compel arbitration of its disputes against

both parties. Horizon conceded that SpawGlass’s claims against it were subject to

arbitration, but Hanover opposed arbitration arguing it was neither a party nor a

signatory to the subcontract containing the arbitration clause and further that the

claims against it fell outside the scope of the arbitration provision.

The trial court granted SpawGlass’s motion to compel arbitration against

Horizon, but it denied the motion as it concerns Hanover. In this interlocutory

appeal, SpawGlass argues that the trial court erred in denying its motion to compel

arbitration against Hanover because (1) the subcontract’s arbitration clause was

incorporated by reference into the performance bond issued by Hanover,

(2) Hanover is Horizon’s successor under the subcontract, and (3) Hanover is

estopped from denying that it is bound by the subcontract’s arbitration clause

because Hanover sought and obtained direct and substantial benefits under the

subcontract.

We reverse the trial court’s order and we remand the matter to the trial court

for entry of an order compelling arbitration of SpawGlass’s claims against Hanover.

Background

In December 2021, Houston Parks Board LGC, Inc. and SpawGlass executed

a prime contract for SpawGlass to act as general contractor for the construction of

2 the Upper Brays Bayou Greenway – Segment BR26 Project in Houston, Texas

(“Project”). The Project involved construction of a greenway from Braeburn Glen

Boulevard to Eldridge Parkway in southwest Houston.

A. Horizon’s Subcontract

In early 2022, SpawGlass and Horizon signed Subcontract No. 5021049-0009

(“Subcontract”) under which Horizon agreed to furnish specified construction

services for the Project as a subcontractor to SpawGlass. The Subcontract defines

SpawGlass as the Contractor and Horizon as the Subcontractor. Section 9 of the

Subcontract states that SpawGlass, Horizon, and their “heirs, executors,

administrators, successors, and permitted assigns . . . agree to the full performance

of the covenants and agreements herein specified.”1

Horizon’s scope of work is set forth in Exhibit A to the Subcontract. With

respect to the timing of performance, Section 4.2, entitled “Subcontractor’s

Schedule,” states that Horizon is required to complete each portion of its work in a

prompt and diligent manner in compliance with the Subcontract Schedule, and

Section 24.18 provides that “time is of the essence.” Section 23.11 of the

Subcontract defines “Events of Default” by Horizon, and the events include

(1) refusing or neglecting to “supply a sufficient number of properly qualified

1 The Subcontract does not define “heirs, executors, administrators, successors, and permitted assigns.”

3 workers or a sufficient quantity of materials of proper quality,” (2) failing to

“promptly pay sub-subcontractors, suppliers, materialmen, or laborers,” and

(3) giving “Contractor a reasonable basis to doubt that the Subcontractor’s Work can

be completed for the unpaid portion of the Subcontractor’s Price or within the

required time.”

The Subcontract contains a mandatory arbitration clause requiring arbitration

of disputes “between Contractor and Subcontractor.” Section 21.4 of the

Subcontract provides:

ELECTION OF ARBITRATION OR LITIGATION. In the event of a dispute between Contractor and Subcontractor, Contractor, in its sole option, may elect to arbitrate such dispute in the manner provided below, or to litigate the dispute in a forum with jurisdiction to decide the dispute. . . . The award rendered by the arbitrator shall be final and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction . . . .

B. Hanover’s Performance Bond

Section 7 of the Subcontract requires Horizon to provide SpawGlass with

payment and performance bonds in the full amount of the Subcontract price, which

is “a sum not to exceed” $2,168,535.92. Pursuant to the Subcontract, Hanover issued

payment and performance bonds to Horizon for SpawGlass’s benefit, and Horizon

delivered those bonds to SpawGlass.

The Performance Bond states that the Subcontract between SpawGlass and

Horizon “is by reference made a part hereof the same as if it were set out verbatim

4 herein.” The Performance Bond, which defines Horizon as the Principal, Hanover

as the Surety, and SpawGlass as the Obligee, further states:

Whenever Principal shall be, and declared by, Obligee to be in default under the Subcontract, the Obligee having performed Obligee’s obligations thereunder, the Surety shall promptly remedy the default or shall promptly:

(1) Complete performance of the work in accordance with the terms and conditions of the Subcontract and Contract Documents; or

(2) Obtain a bid or bids for completion of the Subcontract in accordance with its terms and conditions, and, upon determination by Surety of the lowest responsible bidder, arrange for a contract between such bidder and Obligee, and make available as work progresses sufficient funds to pay the cost of completion less the balance of the Subcontract Price; but not exceeding, including other costs and damages for which the Surety may be liable hereunder, the amount set forth in the first paragraph hereof. The term of the “balance of the Subcontract Price” as used in this paragraph shall mean the total amount payable by Obligee to Principal under the Subcontract and any amendments thereto, less the amount properly paid by Obligee to Principal.

Unlike the Subcontract, the Performance Bond does not contain an arbitration

clause.

C. Performance of the Work under the Subcontract and Alleged Default

On April 18, 2022, Horizon commenced work under the Subcontract.

SpawGlass claims that by May 6, 2022, Horizon was already in non-compliance

with the Project schedule and that Horizon “continued its pattern of delinquent

performance falling further and further behind.” In August 2022, SpawGlass learned

5 that “several [of Horizon’s] employees were not being paid and a meeting was

scheduled to address that and other concerns.” According to SpawGlass, it began

receiving notices from Horizon’s vendors in September 2022, stating they had not

been paid for materials and equipment furnished to Horizon.

On October 5, 2022, SpawGlass sent a “Notice of Default and 72-Hour

Opportunity to Cure” to Horizon pursuant to Section 23.1 of the Subcontract, and

SpawGlass sent a courtesy copy of the notice to Hanover. In the October notice,

SpawGlass alleged that Horizon had defaulted on the Subcontract by refusing or

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dean Witter Reynolds Inc. v. Byrd
470 U.S. 213 (Supreme Court, 1985)
First Options of Chicago, Inc. v. Kaplan
514 U.S. 938 (Supreme Court, 1995)
James G. Neal v. Hardee's Food Systems, Inc.
918 F.2d 34 (Fifth Circuit, 1990)
In Re Kellogg Brown & Root, Inc.
166 S.W.3d 732 (Texas Supreme Court, 2005)
In Re Weekley Homes, L.P.
180 S.W.3d 127 (Texas Supreme Court, 2005)
In Re Rubiola
334 S.W.3d 220 (Texas Supreme Court, 2011)
Owen v. Hendricks
433 S.W.2d 164 (Texas Supreme Court, 1968)
Augusta Court Co-Owners' Ass'n v. Levin, Roth & Kasner, P.C.
971 S.W.2d 119 (Court of Appeals of Texas, 1998)
Raymond James & Associates, Inc. v. Bowman
196 S.W.3d 311 (Court of Appeals of Texas, 2006)
In Re Firstmerit Bank, N.A.
52 S.W.3d 749 (Texas Supreme Court, 2001)
Beard Family Partnership v. Commercial Indemnity Insurance Co.
116 S.W.3d 839 (Court of Appeals of Texas, 2003)
Carr v. MAIN CARR DEVELOPMENT, LLC
337 S.W.3d 489 (Court of Appeals of Texas, 2011)
Enchanted Estates Community Ass'n v. Timberlake Improvement District
832 S.W.2d 800 (Court of Appeals of Texas, 1992)
Reilly v. Rangers Management, Inc.
727 S.W.2d 527 (Texas Supreme Court, 1987)
Downer v. Aquamarine Operators, Inc.
701 S.W.2d 238 (Texas Supreme Court, 1985)
Prudential Securities Inc. v. Marshall
909 S.W.2d 896 (Texas Supreme Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
SpawGlass Civil Construction, Inc. v. Horizon Excavation, Inc. and the Hanover Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/spawglass-civil-construction-inc-v-horizon-excavation-inc-and-the-texapp-2024.