Natgasoline LLC and Orascom E&C USA Inc. v. Refractory Construction Services, Co LLC

566 S.W.3d 871
CourtCourt of Appeals of Texas
DecidedDecember 18, 2018
Docket14-17-00503-CV
StatusPublished
Cited by14 cases

This text of 566 S.W.3d 871 (Natgasoline LLC and Orascom E&C USA Inc. v. Refractory Construction Services, Co LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Natgasoline LLC and Orascom E&C USA Inc. v. Refractory Construction Services, Co LLC, 566 S.W.3d 871 (Tex. Ct. App. 2018).

Opinion

Reversed and Remanded and Opinion filed December 18, 2018.

In The

Fourteenth Court of Appeals

NO. 14-17-00503-CV

NATGASOLINE LLC AND ORASCOM E&C USA INC., Appellants V. REFRACTORY CONSTRUCTION SERVICES, CO. LLC, Appellee

On Appeal from the 122nd District Court Galveston County, Texas Trial Court Cause No. 17-CV-0149

OPINION This appeal arises from competing motions to compel arbitration in a dispute involving the construction of a methanol plant.

Refractory Construction Services, Co. LLC sued Crawford Industrial Services, LLC, Orascom E&C USA, Inc., and Natgasoline LLC to recover money allegedly owed to Refractory Construction under a construction contract. Crawford, a subcontractor, asserted cross-claims against contractor Orascom and plant owner Natgasoline. Orascom and Natgasoline filed a joint motion to compel a bilateral Orascom- Crawford arbitration. Refractory Construction and Crawford jointly filed a competing motion to compel arbitration as to all parties and all claims.

The trial court denied Orascom’s and Natgasoline’s motion to compel and ordered a single arbitration proceeding involving all parties and all claims. Orascom and Natgasoline appealed. For the reasons below, we reverse the trial court’s orders compelling a single arbitration proceeding and remand for further proceedings consistent with this opinion.

BACKGROUND

At issue are two construction contracts involving three signatories. One contract was between contractor Orascom and subcontractor Crawford (the “subcontract”). The second contract was between subcontractor Crawford and sub- subcontractor Refractory Construction (the “sub-subcontract”). The subcontract and sub-subcontract governed construction of Natgasoline’s methanol plant in Beaumont, Texas.

2 Orascom and Crawford are the only signatories to the subcontract; only Refractory Construction signed the sub-subcontract between Refractory Construction and Crawford.

Both the subcontract and the sub-subcontract contain identical arbitration provisions:

11.3.3 ARBITRATION If the matter is unresolved after submission of the matter to a mitigation procedure or mediation, a demand for arbitration may be served by either Party. Any arbitration shall be conducted in Harris County, Texas, United States of America in the English language. The arbitration shall be conducted in accordance with the Rules of Arbitration of the International Chamber of Commerce but excluding the emergency arbitrator appointment rules (“Rules”) in effect on the date of this Agreement. The arbitration shall be presided over by three (3) arbitrators appointed in accordance with the Rules. Each arbitrator shall be fluent in English. The arbitrators’ decision, which shall be in writing, shall be final, binding and conclusive upon the Parties and may be confirmed or embodied in any order or judgment of any court having jurisdiction. The foregoing agreement to arbitrate shall be specifically enforceable and the award rendered by the arbitrators shall be final and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof. The subcontract and the sub-subcontract also contain identical provisions addressing multi-party disputes:

11.6 MULTI-PARTY PROCEEDING All parties necessary to resolve a matter agree to be parties to the same dispute resolution proceeding. To the extent disputes between the CONTRACTOR and SUBCONTRACTOR involve in whole or in part disputes between the CONTRACTOR and the OWNER, at the sole discretion of the CONTRACTOR disputes between the SUBCONTRACTOR and the CONTRACTOR shall be decided by the same tribunal and in the same forum as disputes between the CONTRACTOR and the OWNER.

3 Both documents define “OWNER” as Natgasoline, “CONTRACTOR” as Orascom, and “SUBCONTRACTOR” as Crawford. In the sub-subcontract, Refractory Construction is defined as the “SUPPLIER SUBCONTRACTOR.”

Refractory Construction sued Crawford, Orascom, and Natgasoline in February 2017 and asserted claims for payment allegedly owed to Refractory Construction under the sub-subcontract. Crawford asserted cross-claims against Orascom and Natgasoline. Orascom and Natgasoline asserted affirmative defenses against Refractory Construction and Crawford.

Orascom and Natgasoline filed a joint motion to compel bilateral arbitration between Orascom and Crawford under the subcontract. Orascom’s and Natgasoline’s motion also asked the trial court to stay trial court proceedings “in their entirety pending the completion of such mandatory alternative dispute resolution.” While Orascom’s and Natgasoline’s motion to compel bilateral arbitration was pending, Refractory Construction and Crawford filed a joint motion to compel a single arbitration as to all parties and all claims.

The trial court signed an order on May 24, 2017, stating in relevant part as follows:

It is therefore, ORDERED, ADJUDGED, and DECREED that [Refractory Construction’s and Crawford’s] Motion to Compel Alternative Dispute Resolution as to All Claims and All Parties is in all things GRANTED. Or, in the alternative, it is therefore, ORDERED, ADJUGED, and DECREED that [Orascom’s and Natgasoline’s] Motion to Stay the Entire Case Pending Alternative Dispute Resolution between [Orascom] and Crawford is in all things DENIED. Orascom and Natgasoline filed a notice of appeal asserting that the trial court’s May 2017 order “constitute[d] a final, appealable order.” Orascom and Natgasoline alternatively perfected the appeal as an interlocutory appeal. In the further 4 alternative, Orascom and Natgasoline asked this court to treat their appellate brief as a petition for writ of mandamus. Refractory Construction is the only party to appear as appellee; Crawford did not file an appearance on appeal or an appellate brief.

Upon receipt of the appeal, this court mailed a letter to the parties’ counsel addressing appellate jurisdiction and stating that the appeal would be dismissed unless a response was filed “showing meritorious grounds for continuing the appeal.” Orascom and Natgasoline filed a response asserting that appellate jurisdiction exists because this case involves (1) an appeal from a final judgment; or (2) a statutorily authorized interlocutory appeal; or (3) a mandamus proceeding.

Refractory Construction filed a motion to dismiss Orascom’s and Natgasoline’s appeal for lack of jurisdiction. After receiving Orascom’s and Natgasoline’s response, this court denied Refractory Construction’s motion to dismiss.

The case was orally argued on May 7, 2018. After arguments were heard, this court issued an order abating the appeal to allow the trial court to clarify its intent with respect to the May 2017 order. The trial court signed a second order on June 6, 2018, stating that “it was the intent of the [trial court] to grant [Refractory Construction’s and Crawford’s] Motion to Compel Alternative Dispute Resolution as to All Claims and All Parties and that a single arbitration proceeding occur involving All Claims and all Parties . . .” (emphasis in original). Orascom’s and Natgasoline’s appeal was reinstated upon receipt of the trial court’s June 2018 order. After the appeal was reinstated, the parties filed supplemental briefs addressing jurisdictional issues.

GOVERNING LAW

We must determine as a threshold matter whether the Federal Arbitration Act

5 (the “FAA”) or the Texas Arbitration Act (the “TAA”) applies to this dispute. See generally 9 U.S.C.A. §§ 1-16 (West 2009); Tex. Civ. Prac. & Rem. Code Ann. §§ 171.001-.098 (Vernon 2011). The arbitration provisions at issue do not refer to the FAA or the TAA. The subcontract and sub-subcontract state that they “shall be governed by the Law in effect at the location of the Project.” The project is located in Beaumont, Texas.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
N.D. Iowa, 2026
Maria Colacurcio v. Brent Frei
455 P.3d 192 (Court of Appeals of Washington, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
566 S.W.3d 871, Counsel Stack Legal Research, https://law.counselstack.com/opinion/natgasoline-llc-and-orascom-ec-usa-inc-v-refractory-construction-texapp-2018.