Corcoran v. Bostic

2024 Ohio 2019
CourtOhio Court of Appeals
DecidedMay 28, 2024
DocketCA2023-08-053
StatusPublished
Cited by1 cases

This text of 2024 Ohio 2019 (Corcoran v. Bostic) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Corcoran v. Bostic, 2024 Ohio 2019 (Ohio Ct. App. 2024).

Opinion

[Cite as Corcoran v. Bostic, 2024-Ohio-2019.]

IN THE COURT OF APPEALS

TWELFTH APPELLATE DISTRICT OF OHIO

CLERMONT COUNTY

THOMAS J. CORCORAN, :

Appellee, : CASE NO. CA2023-08-053

: OPINION - vs - 5/28/2024 :

JUDD BOSTIC, et al., :

Appellants. :

CIVIL APPEAL FROM CLERMONT COUNTY COURT OF COMMON PLEAS Case No. 2019 CVH 0996

Jeff Corcoran, for appellee.

Becker & Cade, and Dennis A. Becker and Justin S. Becker, for appellants.

PIPER, J.

{¶ 1} This case involves a civil action in the Clermont County Court of Common

Pleas between appellant, Judd Bostic, and appellee, Thomas Corcoran. The evidence

and testimony were developed before a magistrate revealing the following scenario.

Factual Background

{¶ 2} In 2014, Corcoran entered into an oral agreement with Bostic for restoration

work on his 1969 Ford Bronco. The parties testified that the scope of the project was Clermont CA2023-08-053

intended to be limited. The original plan was for Bostic to repair the body of the vehicle,

repaint it, and essentially make the Bronco roadworthy. However, the project later

expanded to a full "restomod" of the Bronco.1 Corcoran and Bostic also discussed the

possibility of entering the Bronco into premier custom car shows.

{¶ 3} The project extended several years and was fraught with disputes. The

record shows there was an unsuccessful attempt to have the Bronco completed in time

for a car show called the "Cavalcade of Customs" scheduled for January 2015. The

deadline for that event passed, and work on the project slowed or ceased for a period of

time. In early 2018, there was another attempt to have the Bronco ready for the "SEMA

Show" scheduled for November 2018. However, the deadline again passed, and the

Bronco remained unfinished.

{¶ 4} Corcoran expressed his frustration with the slow pace of the project. He

also began noticing duplicate charges and other billing discrepancies. On December 5,

2018, Corcoran and Bostic entered into a written contract to bring the project to

completion. Corcoran agreed to provide Bostic with $5,340.93 for an invoice labeled SO-

01609.2 The parties also agreed that Bostic would be paid $8,000 for his labor in

completing the project. Corcoran agreed to pre-pay Bostic $6,000. The remaining $2,000

for labor would be paid upon "completion and final delivery of the vehicle." Corcoran also

agreed to pay Bostic a timely completion bonus of $3,000 if the Bronco was completed

on or before January 4, 2019.

{¶ 5} The written agreement stated that since some of the parts listed on invoice

1. A restomod of a vehicle involves taking an older model vehicle, preserving its classical design, but adding newer amenities.

2. Invoice SO-01609 lists a number of parts and systems, such as the GPS, USB Ports, alternator, serpentine pulley system, exhaust system, etc. At the very bottom is a line item for "LABOR" with a quantity listed as 189.5 hours. No specific information is listed as to how much labor was involved with any particular item.

-2- Clermont CA2023-08-053

SO-01609 were estimates, the parties agreed to conduct a final parts reconciliation prior

to final delivery. As part of the reconciliation, Bostic agreed to provide Corcoran with

receipts for all parts ordered that cost $150 or more. The final reconciliation was to

determine the final payment due "at delivery." In pertinent part:

Prior to final delivery of the vehicle, BOSTIC shall provide to CORCORAN copies of the receipts for all parts ordered by BOSTIC and invoiced to CORCORAN since June 5th, 2018, and which were $150 or greater. A final reconciliation of any monies that may be due CORCORAN, or owing BOSTIC, shall be made and adjusted as part of any final payment at delivery.

After Bostic signed the contract, Corcoran wired him $11,340.93 (the balance of invoice

SO-01609 and the $6,000 pre-payment of labor costs).

{¶ 6} It is undisputed that Bostic never completed the project. In addition, Bostic

began sending invoices to Corcoran beyond those costs contemplated in the written

agreement. In March 2019, Bostic submitted an invoice to Corcoran for $8,656.82 for

additional work, which included $7,000 for axles. Corcoran asked for a copy of the receipt

for the axles. Bostic replied that he did not have a receipt and indicated that he paid for

the axles in cash. Corcoran paid Bostic $3,000; however, their relationship deteriorated

and became contentious. Bostic corresponded with Corcoran telling him that he would

no longer work on the Bronco. Bostic then claimed that Corcoran owed him $21,141.96

and demanded that Corcoran pay him storage fees. Bostic said he would be keeping the

Bronco until he was "paid in full."

{¶ 7} On August 7, 2019, Corcoran brought this lawsuit against Bostic alleging

claims for breach of contract, trespass to chattels, conversion, unjust enrichment, and

fraudulent misrepresentation. Corcoran alleged that he had spent over $100,000 on the

project and that Bostic was wrongfully withholding the Bronco from him. Bostic filed two

pro se answers. He later retained counsel and filed an amended answer with a

-3- Clermont CA2023-08-053

counterclaim. In his counterclaim, Bostic claimed he had a garageman's lien on the

Bronco and sought to foreclose on the lien.

{¶ 8} The matter proceeded to trial before a magistrate in September of 2021.

Following the close of evidence, Bostic sought a Civ.R. 41(B) dismissal of Corcoran's

complaint arguing that Corcoran did not establish his ownership of the Bronco in

accordance with R.C. 4505.04. Essentially, Bostic argued that Corcoran was required to

prove ownership by certificate of title, admission in the pleadings, or stipulation. Bostic

denied admitting to Corcoran's ownership through stipulation or admission in the

pleadings. Therefore, because Corcoran did not introduce the certificate of title into

evidence, Bostic argued Corcoran's complaint should be dismissed.

Decision of Magistrate and Trial Court Upon Review

{¶ 9} The magistrate found that Bostic "failed to perform his end of the bargain

by completing the work." However, the magistrate also found that Bostic had added value

to the Bronco and was entitled to a garageman's lien. The magistrate then considered

Bostic's motion to dismiss. The magistrate accepted Bostic's argument that the

circumstances required Cororan produce an actual certificate of title to establish his

ownership interest in the Bronco. Therefore, in ruling on Bostic's motion to dismiss, the

magistrate concluded that Bostic "has an artisan's lien for his work on the Bronco that

predates and is superior to any undocumented claim of ownership by Corcoran." As a

result, the magistrate granted Bostic's Civ.R. 41(B) motion to dismiss Corcoran's claims

related to the Bronco and ordered that Bostic retain the Bronco.

{¶ 10} Corcoran timely filed objections with the trial court. Upon an independent

review of the evidence and testimony the trial court rejected the magistrate's decision.

The trial court concluded that Corcoran was, in fact, the owner of the Bronco. The trial

court noted that Corcoran testified about registering the vehicle in Ohio, he just could not

-4- Clermont CA2023-08-053

remember "when" he registered the vehicle.3

{¶ 11} The trial court also found that Bostic did not have a garageman's lien on the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shafer Industrial Servs., Inc. v. A & M Towing & Road Serv., Inc.
2025 Ohio 3197 (Ohio Court of Appeals, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
2024 Ohio 2019, Counsel Stack Legal Research, https://law.counselstack.com/opinion/corcoran-v-bostic-ohioctapp-2024.