Corcoran v. Bostic

2024 Ohio 2019
Ohio Court of Appeals·Decided May 28, 2024·No. CA2023-08-053·Published·Cited by 1 cases

Opinion

IN THE COURT OF APPEALS

TWELFTH APPELLATE DISTRICT OF OHIO CLERMONT COUNTY

THOMAS J. CORCORAN, :

Appellee, : CASE NO. CA2023-08-053

: OPINION

- vs - 5/28/2024 :

JUDD BOSTIC, et al., :

Appellants. :

CIVIL APPEAL FROM CLERMONT COUNTY COURT OF COMMON PLEAS Case No. 2019 CVH 0996

Jeff Corcoran, for appellee. Becker & Cade, and Dennis A. Becker and Justin S. Becker, for appellants.

PIPER, J.

{¶ 1} This case involves a civil action in the Clermont County Court of Common Pleas between appellant, Judd Bostic, and appellee, Thomas Corcoran. The evidence and testimony were developed before a magistrate revealing the following scenario.

Factual Background

{¶ 2} In 2014, Corcoran entered into an oral agreement with Bostic for restoration work on his 1969 Ford Bronco. The parties testified that the scope of the project was

intended to be limited. The original plan was for Bostic to repair the body of the vehicle, repaint it, and essentially make the Bronco roadworthy. However, the project later expanded to a full "restomod" of the Bronco.1 Corcoran and Bostic also discussed the possibility of entering the Bronco into premier custom car shows.

{¶ 3} The project extended several years and was fraught with disputes. The record shows there was an unsuccessful attempt to have the Bronco completed in time for a car show called the "Cavalcade of Customs" scheduled for January 2015. The deadline for that event passed, and work on the project slowed or ceased for a period of time. In early 2018, there was another attempt to have the Bronco ready for the "SEMA Show" scheduled for November 2018. However, the deadline again passed, and the Bronco remained unfinished.

{¶ 4} Corcoran expressed his frustration with the slow pace of the project. He also began noticing duplicate charges and other billing discrepancies. On December 5, 2018, Corcoran and Bostic entered into a written contract to bring the project to completion. Corcoran agreed to provide Bostic with $5,340.93 for an invoice labeled SO- 01609.2 The parties also agreed that Bostic would be paid $8,000 for his labor in completing the project. Corcoran agreed to pre-pay Bostic $6,000. The remaining $2,000 for labor would be paid upon "completion and final delivery of the vehicle." Corcoran also agreed to pay Bostic a timely completion bonus of $3,000 if the Bronco was completed on or before January 4, 2019.

{¶ 5} The written agreement stated that since some of the parts listed on invoice

1. A restomod of a vehicle involves taking an older model vehicle, preserving its classical design, but adding newer amenities.

2. Invoice SO-01609 lists a number of parts and systems, such as the GPS, USB Ports, alternator, serpentine pulley system, exhaust system, etc. At the very bottom is a line item for "LABOR" with a quantity listed as 189.5 hours. No specific information is listed as to how much labor was involved with any particular item.

SO-01609 were estimates, the parties agreed to conduct a final parts reconciliation prior to final delivery. As part of the reconciliation, Bostic agreed to provide Corcoran with receipts for all parts ordered that cost $150 or more. The final reconciliation was to determine the final payment due "at delivery." In pertinent part:

Prior to final delivery of the vehicle, BOSTIC shall provide to CORCORAN copies of the receipts for all parts ordered by BOSTIC and invoiced to CORCORAN since June 5th, 2018, and which were $150 or greater. A final reconciliation of any monies that may be due CORCORAN, or owing BOSTIC, shall be made and adjusted as part of any final payment at delivery.

After Bostic signed the contract, Corcoran wired him $11,340.93 (the balance of invoice SO-01609 and the $6,000 pre-payment of labor costs).

{¶ 6} It is undisputed that Bostic never completed the project. In addition, Bostic began sending invoices to Corcoran beyond those costs contemplated in the written agreement. In March 2019, Bostic submitted an invoice to Corcoran for $8,656.82 for additional work, which included $7,000 for axles. Corcoran asked for a copy of the receipt for the axles. Bostic replied that he did not have a receipt and indicated that he paid for the axles in cash. Corcoran paid Bostic $3,000; however, their relationship deteriorated and became contentious. Bostic corresponded with Corcoran telling him that he would no longer work on the Bronco. Bostic then claimed that Corcoran owed him $21,141.96 and demanded that Corcoran pay him storage fees. Bostic said he would be keeping the Bronco until he was "paid in full."

{¶ 7} On August 7, 2019, Corcoran brought this lawsuit against Bostic alleging claims for breach of contract, trespass to chattels, conversion, unjust enrichment, and fraudulent misrepresentation. Corcoran alleged that he had spent over $100,000 on the project and that Bostic was wrongfully withholding the Bronco from him. Bostic filed two pro se answers. He later retained counsel and filed an amended answer with a

counterclaim. In his counterclaim, Bostic claimed he had a garageman's lien on the Bronco and sought to foreclose on the lien.

{¶ 8} The matter proceeded to trial before a magistrate in September of 2021.

Following the close of evidence, Bostic sought a Civ.R. 41(B) dismissal of Corcoran's complaint arguing that Corcoran did not establish his ownership of the Bronco in accordance with R.C. 4505.04. Essentially, Bostic argued that Corcoran was required to prove ownership by certificate of title, admission in the pleadings, or stipulation. Bostic denied admitting to Corcoran's ownership through stipulation or admission in the pleadings. Therefore, because Corcoran did not introduce the certificate of title into evidence, Bostic argued Corcoran's complaint should be dismissed.

Decision of Magistrate and Trial Court Upon Review

{¶ 9} The magistrate found that Bostic "failed to perform his end of the bargain by completing the work." However, the magistrate also found that Bostic had added value to the Bronco and was entitled to a garageman's lien. The magistrate then considered Bostic's motion to dismiss. The magistrate accepted Bostic's argument that the circumstances required Cororan produce an actual certificate of title to establish his ownership interest in the Bronco. Therefore, in ruling on Bostic's motion to dismiss, the magistrate concluded that Bostic "has an artisan's lien for his work on the Bronco that predates and is superior to any undocumented claim of ownership by Corcoran." As a result, the magistrate granted Bostic's Civ.R. 41(B) motion to dismiss Corcoran's claims related to the Bronco and ordered that Bostic retain the Bronco.

{¶ 10} Corcoran timely filed objections with the trial court. Upon an independent review of the evidence and testimony the trial court rejected the magistrate's decision. The trial court concluded that Corcoran was, in fact, the owner of the Bronco. The trial court noted that Corcoran testified about registering the vehicle in Ohio, he just could not

remember "when" he registered the vehicle.3

{¶ 11} The trial court also found that Bostic did not have a garageman's lien on the Bronco after considering the parties' written agreement. According to the agreement, Corcoran had already paid Bostic the money due and owing. Corcoran was not obligated to provide Bostic with additional funds until the project was completed. Upon the vehicle's completion, Bostic would have been entitled the remaining $2,000 in labor charges (and the completion bonus if completed timely) along with any amounts owed following the final parts reconciliation. The trial court also noted that Bostic failed to provide Corcoran with a receipt, which was contrary to the terms of the written agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Corcoran v. Bostic, 2024 Ohio 2019 (Ohio Ct. App. 2024).

2024 Ohio 2019 (Corcoran v. Bostic) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Shafer Industrial Servs., Inc. v. A & M Towing & Road Serv., Inc.
2025 Ohio 3197 (Ohio Court of Appeals, 2025)