Conway Corp. v. Construction Engineers, Inc.

782 S.W.2d 36, 300 Ark. 225, 1989 Ark. LEXIS 485
CourtSupreme Court of Arkansas
DecidedDecember 11, 1989
Docket89-34
StatusPublished
Cited by50 cases

This text of 782 S.W.2d 36 (Conway Corp. v. Construction Engineers, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Conway Corp. v. Construction Engineers, Inc., 782 S.W.2d 36, 300 Ark. 225, 1989 Ark. LEXIS 485 (Ark. 1989).

Opinion

Darrell Hickman, Justice.

Construction Engineers, Inc., (CEI), the low bidder on a municipal construction contract, sued the appellants for wrongfully rejecting its bid and awarding the contract to the second lowest bidder, Limbaugh Construction Company. Appellants are the Conway Corporation, a nonprofit corporation which, under contract, operates the utilities owned by the City of Conway; the Corporation’s directors; Jim Brewer, the general manager of the Corporation; and Bennie McCoy, the engineer on the construction project. The chancellor found the appellants wrongfully rejected CEI’s bid. Because that finding was clearly erroneous, we reverse and dismiss this case.

CEI filed suit in Pulaski County Chancery Court on August 20,1986, seeking injunctive and declaratory relief and damages. 1 The complaint alleged the contract was awarded in violation of the law, and that the appellants had conspired to interfere with CEI’s business expectancy. The appellants answered that they were immune from tort liability, and that they had exercised good faith discretion in carrying out their public duties.

After the lawsuit was filed, and without objection by the appellants, CEI requested a special master to hear evidence on the issue of temporary injunctive relief. In determining whether CEI had a probability of success on the merits, the master found there was a reasonable basis for the rejection of CEI’s bid and that the appellants had acted in good faith.

Those findings were presented to the chancellor. He did not immediately accept or reject the findings, but held a hearing to receive additional evidence. He concluded that an injunction should not issue because construction on the project was already 43% complete, but he rejected the remainder of the master’s findings. He determined that the Corporation’s rejection of CEI’s bid was arbitrary and without cause and that Brewer and McCoy acted in bad faith in urging rejection of the bid. The appellants were held jointly and severally liable for $ 194,295, the profit CEI would have made had it received the contract. Ratepayers, who had intervened with an illegal exaction suit, were awarded the $66,100 difference in CEI’s and Limbaugh’s bids.

The appellants seek reversal on a myriad of issues, including immunity, lack of jurisdiction, due process, improper remarks by the chancellor, and insufficiency of the evidence. CEI cross-appeals, asking for attorney fees, prejudgment interest and punitive damages. Amicus curiae briefs have been filed by the Arkansas Water Managers Association and by the Associated General Contractors of America. The case is resolved most readily by examining the evidence and the chancellor’s findings.

In May of 1986, the Conway Corporation solicited bids on the expansion of Conway’s water treatment plant. Jim Brewer asked Bennie McCoy to contact CEI and dissuade it from bidding on the project. The basis for Brewer’s concern was CEI’s performance in 1980-1981 as general contractor on another local project, the construction of an elementary school for the Conway School District. According to Brewer’s information (which was received from his close friend and school superintendent Carl Stuart, as well as from local newspaper articles), there had been serious problems with the school’s plumbing, cabinetwork, and windows as a result of faulty construction. When a dispute arose among CEI, the architect, the school district and the subcontractors as to who was responsible for the problems, a lawsuit was brought, resulting in lengthy delays. The school’s problems were apparently well known throughout Conway and Brewer described the project as a “fiasco.”

Following Brewer’s instructions, McCoy called Steve and Danielle Smith, the husband and wife engineers who owned CEI, on May 19 and May 29 and wrote them on June 3 to express Brewer’s reservations about their ability to perform the work. He told Steve Smith, “I understand you got a bit of a black eye in the Conway community over the Conway school you built.” Smith admitted he had gotten “cross-ways” with the architect on that project. McCoy also asked about rumors that CEI was behind schedule on one of its current projects, the construction of a sewage plant in nearby Morrilton. Smith said he was behind because of late equipment deliveries but expected that his completion schedule would be extended. CEI was not dissuaded from submitting a bid.

Bids were opened on June 26. CEI’s bid was lowest and Limbaugh’s the next lowest. Brewer immediately ordered McCoy to conduct a post-bid investigation of both CEI and Limbaugh (neither Brewer nor McCoy was familiar with Limbaugh). In the meantime, Brewer obtained legal advice on the propriety of awarding the contract to the second lowest bidder.

Between June 30 and July 3, McCoy spoke with various references who gave excellent reports on Limbaugh, but gave CEI, at best, mixed reviews. One reference reported that CEI did good, quality work, and CEI’s surety gave a favorable report. But damaging references were given by the engineers on the Morrilton project who spoke of supervisory problems and a “paper war” which resulted when CEI missed a critical milestone, and by the architect on the Conway school who said the project was the worst he had ever experienced.

These matters were presented to the board of the Corporation at its next meeting. The board was concerned that the improvements be completed on time to avoid an anticipated water shortage. After hearing Brewer’s information and recommendation, the members were unanimous in their conviction that the job could be completed on time with Limbaugh, but not with CEI. They also noted that, while CEI had never completed a project of this magnitude, Limbaugh had constructed ten water and sewage treatment plants in the past five years.

The first question we must answer is, did the Corporation have the discretion to award the contract to anyone other than the lowest monetary bidder? The answer is yes.

CEI and the Associated General Contractors rely on Ark. Code Ann. §§ 19-11-403 and 404 (1987), arguing that the Corporation had no discretion to award the contract to anyone other than the lowest bonded bidder. Section 19-11-403 provides that bids submitted on public construction contracts must be accompanied by a surety bond. Section 19-11-404 provides as follows:

All bidders being made responsible in the manner stated in § 19-11-403, it shall be the duty of persons empowered to accept bids to accept no other bid than the lowest, except upon default of the lowest bidder.

The appellants urge the application of Ark. Code Ann. § 22-9-203 (1987), which governs the award procedure on public improvement contracts, including municipal improvements costing over $ 10,000. Section 22-9-203 (d) provides that the awarding authority shall:

[Ojpen and compare bids, and thereafter award the contract to the lowest responsible bidder, but only if it is the opinion of the authority that the best interests of the taxing unit would be served thereby.

We find the legislature did not intend §§ 19-11-403 and 404 to apply to contracts like the one here.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ellis v. Arkansas Department of Human Services
2016 Ark. App. 318 (Court of Appeals of Arkansas, 2016)
Bachner Company, Inc. v. Weed
315 P.3d 1184 (Alaska Supreme Court, 2013)
J & S SERVICES, INC. v. Tomter
139 P.3d 544 (Alaska Supreme Court, 2006)
Office MacHines, Inc. v. Mitchell
234 S.W.3d 906 (Court of Appeals of Arkansas, 2006)
MIAMI-DADE CTY. SCHOOL BOARD v. J. Ruiz School Bus Service, Inc.
874 So. 2d 59 (District Court of Appeal of Florida, 2004)
Rn v. Jm
61 S.W.3d 149 (Supreme Court of Arkansas, 2001)
H & W Contracting, LLC v. City of Watertown
2001 SD 107 (South Dakota Supreme Court, 2001)
Delk Construction Co v. Leo George Munford
2 F. App'x 646 (Eighth Circuit, 2001)
Benton v. Gunter
29 S.W.3d 719 (Supreme Court of Arkansas, 2000)
Opinion No.
Arkansas Attorney General Reports, 2000
Shelton Ex Rel. Piccirilli v. Fiser
8 S.W.3d 557 (Supreme Court of Arkansas, 2000)
Mason v. Wal-Mart Stores, Inc.
969 S.W.2d 160 (Supreme Court of Arkansas, 1998)
Lamminen v. City of Cloquet
987 F. Supp. 723 (D. Minnesota, 1997)
Board of Trustees v. Stodola
942 S.W.2d 255 (Supreme Court of Arkansas, 1997)
Texas Beef Cattle Co. v. Green
921 S.W.2d 203 (Texas Supreme Court, 1996)
Honeycutt v. Rickman (In Re Honeycutt)
198 B.R. 306 (E.D. Arkansas, 1996)
Masterson v. Stambuck
902 S.W.2d 803 (Supreme Court of Arkansas, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
782 S.W.2d 36, 300 Ark. 225, 1989 Ark. LEXIS 485, Counsel Stack Legal Research, https://law.counselstack.com/opinion/conway-corp-v-construction-engineers-inc-ark-1989.