Convoy Company, an Oregon Corporation v. Sperry Rand Corporation, a Delaware Corporation

672 F.2d 781, 1982 U.S. App. LEXIS 20668
CourtCourt of Appeals for the Ninth Circuit
DecidedMarch 26, 1982
Docket80-3266, 80-3288
StatusPublished
Cited by14 cases

This text of 672 F.2d 781 (Convoy Company, an Oregon Corporation v. Sperry Rand Corporation, a Delaware Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Convoy Company, an Oregon Corporation v. Sperry Rand Corporation, a Delaware Corporation, 672 F.2d 781, 1982 U.S. App. LEXIS 20668 (9th Cir. 1982).

Opinion

GOODWIN, Circuit Judge.

This court remanded the initial judgment in favor of Convoy Company for a determination whether the judgment, when coupled with a prior settlement, resulted in a double recovery. Convoy Corp. v. Sperry Rand Corp., 601 F.2d 385 (9th Cir. 1979). On remand the district court found that Convoy’s total provable damages exceeded the total of the settlement and the judgment and entered judgment in the same amount previously entered.

On appeal Sperry Rand, (referred to as Univac) argues that the district court erred by including in the damages (a) prejudgment interest, (b) the cost of salaried supervisors, and (c) the total electronic data processing staff costs. Convoy cross-appeals, arguing that the interest on the judgment should be increased.

After reviewing the record, transcripts, and briefs we conclude (1) that Univac has failed to show that the district court erred as a matter of law; and (2) that any mistake as to the factual computation of damages is harmless because Convoy’s total damages would still exceed the amount necessary to avoid a double recovery. It does appear, however, that the district court erred in failing to provide for the increase in legal interest adopted by Oregon in 1979.

In 1969 Convoy entered into a contract with a firm named WOFAC under which WOFAC agreed to design a computerized load makeup and rerouting system for use in Convoy’s motor vehicle trans|x>rt business. Convoy entered into a second contract with Univac under which Univac agreed to provide the computer hardware to be used with WOFAC’s software and certain software support.

The system never functioned properly and Convoy withdrew from the project and sued WOFAC for $516,129.09 in out-of-pocket costs and for more than $1,000,000 in lost profits and punitive damages. Convoy *783 settled with WOFAC for $354,500. Convoy then sued Univac for $216,398.61 for out-of-pocket costs. The district court entered judgment for Convoy in the full amount of its claim and Univac appealed. 1

On appeal this court affirmed in part, reversed in part, and remanded the case. Univac’s major contention on appeal was that Convoy was not entitled to a double recovery. The court agreed, but noted that the question of a double recovery was complicated by the fact that (a) Convoy had sought damages for lost profits and punitive damages from WOFAC but not from Univac 2 , and (b) the settlement with WO-FAC had not allocated portions of the total amount to particular claims. The court rejected Univac’s argument that the settlement with WOFAC should be applied to offset all of Convoy’s claims against Uni-vac. Rather, the judgment approved Convoy’s reliance on Ciluffo v. Middlesex General Hospital, 146 N.J.Super. 476, 370 A.2d 57 (App.Div.1977), and concluded:

“[W]e believe that the trial court should have applied the principles enunciated in Ciluffo to the facts of this case. Univac is liable to Convoy, but its liability is limited to the total provable damages to which Convoy is entitled from both successive, independent wrongdoers, minus the $354,500 received in the settlement from WOFAC.
“The trial court did not find Convoy’s total provable damages against the two defendants. It merely stated that the settlement received from WOFAC did not fully compensate Convoy for its out-of-pocket expenses. A remand is therefore necessary for additional factfinding.” 601 F.2d at 389.

On remand the parties spent considerable court time arguing over the effect of their prior stipulations as to damages. The court found that Convoy’s total damages exceeded $570,898.61 (the total of the WOFAC settlement and the prior judgment against Univac), and therefore reentered judgment for Convoy and against Univac for $216,-398.61 (the same amount previously awarded) with 6 percent interest from March 26, 1971. In his opinion, the trial judge found that (a) the parties were bound to the agreement in the initial pretrial order that electronics data processing staff costs for a stated period totaled $88,045.94; but that evidence of such costs for additional periods could be adduced; (b) Convoy was entitled to recover for the hours its salaried person?nel spent supervising the computer system and for construction of a new building addition to house the computer operation; (c) Convoy was entitled under Oregon law to interest on the unliquidated damages from the date of the breach of contract to the date of the settlement with WOFAC; and (d) as the out-of-pocket expenses, coupled with interest exceeded $570,898.61, the court did not have to consider Convoy’s third element of damages, loss of the benefit of the bargain.

The following issues remain for decision:

(1) Was the trial court’s finding that Convoy suffered total provable damages in excess of $570,898.61 reversible error because:'

(a) electronics data processing staff costs of $113,095.35 were neither pleaded nor proved by substantial evidence;
(b) salaried supervisory staff costs of $83,281.63 were not allowable as a matter of law, and
(c) interest was not an item of damages within this court’s mandate, was on sums not readily ascertainable as to due date or amount, and resulted in an award of interest on interest?

(2) Should the rate of interest on the judgment increase, as Convoy claims, to 9 percent on July 25, 1979, pursuant to the change in the Oregon statutory rate of interest?

As the district court interpreted this court’s prior opinion, the district court had *784 only to determine whether Convoy’s total provable damages against WOPAC and Univac exceeded $570,898.61. If the damages exceeded that amount, Convoy was entitled to a judgment of $216,398.61. Convoy, on remand, did not seek recovery beyond that amount.

The district court held that total provable damages exceeded $570,898.61 because out-of-pocket expenses alone were $541,997.13, and that the interest on this amount exceeded $100,000. Having made these findings, the district court held that it need not consider whether Convoy was entitled to recover damages for the loss of benefit of the bargain.

Because the district court found that combination of the two items of out-of-pocket expenses and interest exceeded $570,898.61, a mistake in computing damages is harmless unless, either by itself or in combination with other errors, the error reduces the total to less than $570,898.61.

The propriety of awarding interest will be considered first because the district court found only $541,997.13 in expenses, exclusive of interest. Second, the propriety of including the cost of salaried personnel will be considered. The amount in issue, $83,-000, might reduce the total below $570,000 even if interest was properly awarded.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Under Armour v. Ziger/Snead
Court of Special Appeals of Maryland, 2017
Under Armour, Inc. v. Ziger/Snead, LLP
158 A.3d 1134 (Court of Special Appeals of Maryland, 2017)
Tennessee Valley Authority v. United States
69 Fed. Cl. 515 (Federal Claims, 2006)
State v. Rouse
2002 WI App 107 (Court of Appeals of Wisconsin, 2002)
VMark Software, Inc. v. EMC Corp.
642 N.E.2d 587 (Massachusetts Appeals Court, 1994)
United States v. CBS, Inc.
103 F.R.D. 365 (C.D. California, 1984)
SDS Lumber Co. v. Allendale Mutual Insurance
563 F. Supp. 608 (D. Oregon, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
672 F.2d 781, 1982 U.S. App. LEXIS 20668, Counsel Stack Legal Research, https://law.counselstack.com/opinion/convoy-company-an-oregon-corporation-v-sperry-rand-corporation-a-ca9-1982.