Constellation NewEnergy, Inc.

Armed Services Board of Contract Appeals·Decided December 8, 2020·No. ASBCA No. 62518·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Constellation NewEnergy, Inc. ) ASBCA No. 62518 ) Under Contract Nos. DE-AM36-09GO29040 ) T.O. N39430-16-F-1803 )

APPEARANCE FOR THE APPELLANT: William J. Spriggs, Esq. Spriggs Law Group Lynchburg, VA

APPEARANCES FOR THE GOVERNMENT: Craig D. Jensen, Esq. Navy Chief Trial Attorney Cindy M. Hurt, Esq. Matthew D. Bordelon, Esq. Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE O’CONNELL

By order dated August 21, 2020, the Board asked the parties to address whether appellant, Constellation NewEnergy, Inc. (CNE), stated a sum certain in its claim, as required by the Federal Acquisition Regulation (FAR) for the Board to possess jurisdiction. In response, the Navy moved to dismiss the appeal.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. This appeal involves a task order for several energy conservation measures (ECMs) at Naval Station Great Lakes, dated February 5, 2016 (R4, tab 296 at 1, 6 1).

2. On May 7, 2018, CNE submitted what it called Change Order Request #3. The submission was lengthy, seeking additional money for work that had already been performed, as well as proposed future work. (App. supp. R4, tab A017) CNE presented the Navy with two alternatives: “Option A” for $2,117,253 and “Option B” for $1,374,902 (id. at 10). The difference was that the former contained a proposal for additional work that CNE identified as ECM 4k, High MERV HVAC filters, pursuant to which CNE offered to replace “the existing conventional, low efficiency air filters in the air handling units with new properly sized, advanced electrostatic HVAC air cleaning systems . . .” in numerous buildings (id. at 9, 27).

1 Citations are to the .pdf page number of the electronic document. 3. A Navy contract specialist responded by email on July 24, 2018. She listed the items for which CNE had requested additional amounts and wrote “Concur” next to several of them. However, with respect to the ECM 4k work, she wrote “Disagree.” She explained “[t]he Government’s position is not to pursue the work at this time. The system may not be meeting the design intent, but it is working and currently reaching target energy savings.” (App. supp. R4, tab A018)2

4. On February 1, 2019, CNE wrote to the contracting officer stating that it had been attempting to discuss Change Order Request #3 with her and her team but had not received a response. CNE incorporated Change Order Request #3 in this submission, stated that it was certifying it as a claim, and requested a final decision. CNE did not state that the claim was limited to the Option B work. (R4, tab 313)

5. The contracting officer issued a final decision on April 3, 2020. She referenced CNE’s original submission of Options A and B, but noted that CNE had never performed the ECM 4k work unique to Option A. Accordingly, she stated that she would address Option B only. She granted the claim in part, awarding CNE a total of $315,970. (R4, tab 314)

6. CNE filed a timely appeal on May 15, 2020. The Board docketed the appeal relating to the solar hybrid systems (ECM 7A) as ASBCA No. 62518 and docketed the portion of the appeal relating to ECM 4d (Chillers) as ASBCA No. 62519. On December 2, 2020, the Board dismissed No. 62519 at the joint request of the parties due to their settlement of that appeal.

DECISION

The Contract Disputes Act provides that “[e]ach claim by a contractor against the Federal Government relating to a contract shall be submitted to the contracting officer for a decision.” 41 U.S.C. § 7103(a)(1). The contractor must certify claims for more than $100,000. 41 U.S.C. § 7103(b). The contracting officer must issue a decision within 60 days on a claim for more than $100,000, or notify the contractor of the time within which she will issue the decision. 41 U.S.C. § 7103(f)(2). “Claim” is defined in the FAR as “a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to the contract.” FAR 2.101. The Court of Appeals for the Federal Circuit has held that a claim must be submitted in writing and contain a “clear and unequivocal statement that gives the contracting officer adequate notice of the basis and amount of

2 This document was not in the Rule 4 file at the time that the Board requested the parties address the sum certain issue.

2 the claim.” Contract Cleaning Maintenance, Inc. v. United States, 811 F.2d 586, 592 (Fed. Cir. 1987).

The “sum certain” requirement can result in the rapid dismissal of an appeal for contractors who hedged on the amount sought. The Board has held that it lacks jurisdiction if the contractor states that it is seeking “approximately,” J.P. Donovan Construction, Inc., ASBCA No. 55335, 10-2 BCA ¶ 34,509 at 170,171, aff’d 469 Fed. App’x 903 (Fed. Cir. 2012), “at least,” Odyssey International, Inc., ASBCA No. 62062, 20-1 BCA ¶ 37,510 at 182,212, or “about” a specified amount, Elham Ahmadi Construction Co., ASBCA No. 61031, 17-1 BCA ¶ 36,861 at 179,604.

On the other hand, the Board has held that it is enough for jurisdiction if the amount sought can be calculated. In M.J. Hughes, Construction, Inc., ASBCA No. 61782, 19-1 BCA ¶ 37,235, the contractor presented a claim for $2,000,887 broken down into three discrete subparts, which added up to this amount. Id. at 181,234-35. The three subparts had overlapping damages, however, which would have to be subtracted out if the relevant portions of the claim were sustained, meaning that the maximum recovery would be some amount lower than $2,000,887. Id. at 181,235. The Board held that because this amount could be calculated, it was sufficient for our jurisdiction. Id.; Mohammed Darwish Ghabban Est., ASBCA No. 51994, 00-2 BCA ¶ 31,114 at 153,671 (sum certain calculated by multiplying daily rental rate by number of days).

The sum certain in a claim is not set in stone; a contractor can amend the claim by increasing or decreasing the amount while it is still before the contracting officer or after appeal to the Board. Santa Fe Engineers, Inc. v. United States, 818 F.2d 856, 858 (Fed. Cir. 1987); Zafer Taahhut Insaat Ve Ticaret A.S., ASBCA No. 56770, 12-1 BCA ¶ 34,951 at 171,831. And the Federal Circuit has held that a contractor met the sum certain requirement when it presented two alternative amounts arising from the same factual circumstances: the contractor in that appeal sought $4,342,245 based on a breach of contract theory or, in the alternative, $1,751,052 based on constructive changes and other theories. Heyl & Patterson, Inc. v. O’Keefe, 986 F.2d 480, 482 (Fed. Cir. 1993) (rev’d on other grounds Reflectone, Inc. v. Dalton, 60 F.3d 1572 (Fed. Cir. 1995) (en banc)). The Court of Appeals held that this was permissible because each alternative presented a sum certain under the different legal theories. Id. at 484-85.

Free access — add to your briefcase to read the full text and ask questions with AI

Constellation NewEnergy, Inc., (asbca 2020).

Constellation NewEnergy, Inc. (Constellation NewEnergy, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related