Cone Corp. v. Hillsborough County

983 F.2d 197, 1993 U.S. App. LEXIS 1900, 60 Empl. Prac. Dec. (CCH) 42,055, 1993 WL 10840
CourtCourt of Appeals for the Eleventh Circuit
DecidedFebruary 8, 1993
DocketNo. 91-4194
StatusPublished
Cited by4 cases

This text of 983 F.2d 197 (Cone Corp. v. Hillsborough County) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cone Corp. v. Hillsborough County, 983 F.2d 197, 1993 U.S. App. LEXIS 1900, 60 Empl. Prac. Dec. (CCH) 42,055, 1993 WL 10840 (11th Cir. 1993).

Opinion

OAKES, Senior Circuit Judge:

This case comes before the court on an appeal from a grant of summary judgment for the defendant, Hillsborough County, Florida. The United States District Court granted the county’s motion after concluding that the nonminority general contractor plaintiffs-appellants had no standing to challenge, on equal protection grounds, the county’s minority business enterprise program (MBE). 777 F.Supp. 1558. As appellants have alleged no injury in fact, we affirm.

BACKGROUND

This court has reviewed the details of the county’s plan before, in Cone Gorp. v. Hillsborough County, 908 F.2d 908, 909-11 (11th Cir.), cert. denied, 498 U.S. 983, 111 S.Ct. 516, 112 L.Ed.2d 528 (1990), when it reversed the district court’s grant of summary judgment to the contractors. For the purpose of this appeal, we review the facts only briefly.

Hillsborough County, which includes the city of Tampa, Florida, instituted its first MBE program in 1978 in order to be eligible for federal funding for a variety of construction projects. Initially, the county instituted a voluntary program. In 1984, after studying the effects of the voluntary program for six years, it concluded that more serious measures would be needed to increase minority participation in county contracts.

The mandatory program challenged by the appellants was instituted in 1988. It does not include quotas or set-asides for minority contractors or subcontractors, nor does it grant any bidding preferences to minorities. Rather, it requires the county to set goals for minority participation in particular contracts before bidding. No goals are included in the bid specifications on any contract unless at least three minority subcontractors in the area are available and capable of doing the work. A contractor whose bid does not include the requisite MBE participation may nonetheless win the contract if it can demonstrate a good-faith effort at compliance, or if its bid is substantially lower than the lowest responsive bid. Minority general contractors who plan to complete at least 51% of the work on a project themselves need only meet 50% of the goal for minority subcontractor participation.

The key point for purposes of this case is that all contractors, both minority and non-minority, must include minority participation where it is feasible, and must demonstrate a good-faith effort to find minority subcontractors where they are available. There is only one provision in the county’s resolution which treats minority and nonmi-nority general contractors differently: the reduction in the MBE goal for minority general contractors who do more than 50% of the work themselves. Appellants have alleged no injury stemming from the operation of this provision.

In 1989, the contractors filed a complaint seeking injunctive relief and a declaratory judgment that the program created an unconstitutional racial preference in violation of the equal protection clause of the Fourteenth Amendment. Appellants alleged three types of injury: (1) that they were deterred by extra risk and cost from bidding on county projects, thus foregoing profits; (2) that they lost profits on contracts they were awarded because they had to use minority subcontractors who were not the lowest bidders, rather than using [199]*199low bidding nonminority subcontractors or their own workforce; and (3) that they expended money complying with the county’s requirement that they make good faith efforts to meet the MBE goals.

The district court, after a brief hearing, granted a preliminary injunction barring continued enforcement of the program. Cone Corp. v. Hillsborough County, 723 F.Supp. 669 (M.D.Fla.1989). In 1990, the district court granted summary judgment for the contractors and entered a final order making the preliminary injunction permanent. Cone Corp. v. Hillsborough County, 730 F.Supp. 1568 (M.D.Fla.1990). This court reversed. Cone Corp. v. Hillsborough County, 908 F.2d 908 (11th Cir.1990).

Following this court’s reversal of the summary judgment motion for the contractors, and after further discovery, the county filed a summary judgment motion, arguing both that it should prevail on the merits and that the contractors had failed to allege any injury sufficient to confer standing. The county also filed, in the alternative, a motion to dismiss for lack of standing. The district judge granted both motions, concluding that precedents of this court compelled a finding that the contractors had no standing, although she expressed doubts as to whether these cases were consistent with the Supreme Court’s standing precedents.

The district court had jurisdiction under 28 U.S.C. § 1331 (1988). This court has appellate jurisdiction under 28 U.S.C. § 1291 (1988).

DISCUSSION

Under Article III of the Constitution, the appellant contractors have no standing to challenge the county’s MBE program unless they can allege an injury which is traceable to the program and redressable by court action. Valley Forge Christian College v. Americans United for Separation of Church and State, 454 U.S. 464, 472, 102 S.Ct. 752, 758, 70 L.Ed.2d 700 (1982). The district court properly rejected the contractors’ claims for failure to allege an injury in fact.

In an effort to satisfy the injury-in-fact requirement, appellants claim that they have absorbed extra costs and suffered a loss of profits by complying with the program’s requirements, and that they will lose future profits because they are deterred by extra risks and costs from competing for contracts with Hillsborough County.

As this court’s previous cases have made clear, appellants cannot allege an economic injury from the operation of an MBE program unless that program requires them to compete on an uneven economic playing field or bars them from competing for certain contracts. Northeastern Fla. Chapter of the Assoc’d Gen. Contractors of Am. v. City of Jacksonville, 951 F.2d 1217 (11th Cir.), cert. granted, — U.S. -, 113 S.Ct. 50, 121 L.Ed.2d 20 (1992); Cone Corp. v. Fla. Dep’t of Transp., 921 F.2d 1190 (11th Cir.), cert. denied, — U.S. -, 111 S.Ct. 2238, 114 L.Ed.2d 479 (1991); S.J. Groves & Sons Co. v. Fulton County, 920 F.2d 752 (11th Cir.), cert. denied, — U.S. -, 111 S.Ct. 2274, 114 L.Ed.2d 725 and cert. denied, — U.S. -, 111 S.Ct. 2893, 115 L.Ed.2d 1057 (1991); Capeletti Bros. v. Broward County, 738 F.Supp. 1415 (S.D.Fla.1990), aff'd without op., 931 F.2d 903 (11th Cir.), cert. denied, — U.S. -, 111 S.Ct. 2871, 115 L.Ed.2d 1037 (1991). Other circuits use the same criteria to find standing in challenges to MBE programs. See, e.g., O’Donnell Const. Co. v. District of Columbia, 963 F.2d 420, 423 (D.C.Cir.1992); Coral Const. Co. v. King County,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cone Corp. v. Hillsborough County
157 F.R.D. 533 (M.D. Florida, 1994)
Cone Constructors, Inc. v. Hillsborough County
5 F.3d 1397 (Eleventh Circuit, 1993)
Cone Corp. v. Hillsborough County
995 F.2d 185 (Eleventh Circuit, 1993)
The Cone Corporation v. Hillsborough County
983 F.2d 197 (Eleventh Circuit, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
983 F.2d 197, 1993 U.S. App. LEXIS 1900, 60 Empl. Prac. Dec. (CCH) 42,055, 1993 WL 10840, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cone-corp-v-hillsborough-county-ca11-1993.