Commonwealth Electric Co. v. ISYS Securities Systems, Inc. (In Re Commonwealth Electric Co.)

118 B.R. 720, 1990 Bankr. LEXIS 1849
CourtUnited States Bankruptcy Court, D. Nebraska
DecidedMay 21, 1990
Docket19-80144
StatusPublished
Cited by1 cases

This text of 118 B.R. 720 (Commonwealth Electric Co. v. ISYS Securities Systems, Inc. (In Re Commonwealth Electric Co.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Nebraska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commonwealth Electric Co. v. ISYS Securities Systems, Inc. (In Re Commonwealth Electric Co.), 118 B.R. 720, 1990 Bankr. LEXIS 1849 (Neb. 1990).

Opinion

*722 MEMORANDUM

TIMOTHY J. MAHONEY, Chief Judge.

Trial of this adversary proceeding was held on November 14 and 15, 1989. Edward Tricker and James Overcash of Woods & Aiken located in Lincoln, Nebraska, appeared on behalf of the plaintiff. William Hadley and Bradley White of Andersen, Berkshire, Lauritsen, Brower & Hadley located in Omaha, Nebraska, appeared on behalf of defendant. Following trial, the Court requested post-trial written arguments and final briefs, the last of which was received on January 4, 1990. This memorandum contains the findings of fact and conclusions of law required by Fed.R.Civ.P. 52 and Fed.Bankr.R. 7052. This complaint which was brought as a request for turnover of property of the estate is a core proceeding under 28 U.S.C. § 157(b)(2)(E) and (0).

Background

Commonwealth Electric Company (Commonwealth) has been a debtor-in-possession under Chapter 11 of the Bankruptcy Code since August, 1987. Several years prior to that, Commonwealth entered into a subcontract arrangement with the defendant, ISYS Securities Systems, Inc. (ISYS). By virtue of the subcontract arrangement, ISYS had a construction contract with the United States Government to complete certain projects on the Consolidated Space Operation Center (“CSOC” or “project”) which was located near Colorado Springs, Colorado. Commonwealth was to perform certain installation functions pursuant to its subcontract with ISYS.

In late June of 1987, Commonwealth was unable to continue its business operations and terminated its participation in the project after a significant amount of work had been completed. As a result of Commonwealth’s inability to complete the project, ISYS was required to complete it in order to be in compliance with its contract with the Government. The dispute in Count I of the complaint concerns the amount due Commonwealth for the work it completed but had not received payment for as of the date of its work termination and the offset, if any, in favor of ISYS for the costs incurred by ISYS in completing the project.

The second count concerns an interpretation of the rights of the parties pursuant to the subcontract. During the work on the project, Commonwealth incurred certain additional costs as a result of delays by the Government. The contract between the Government and ISYS provides that any claim for additional cost caused by the Government to the contractor is subject to the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613 (Contract Disputes Act). As will be discussed later, that Act apparently requires certification of the costs and the cause of such costs by the contractor and submission to the Government for a determination by contract administration officers or an administrative panel. No action is permitted to be brought on the claim as between the contractor and the Government in the courts of the United States, at least until the full administrative process has been completed.

The subcontract between ISYS and Commonwealth states that disputes between the subcontractor and the contractor are also subject to the Contract Disputes Act. The issue is whether or not Commonwealth must submit its additional costs to ISYS, and then await Government determination of the allowance of the costs or may Commonwealth, as a result of language or lack of specific language in the subcontract look directly to ISYS for the additional costs whether or not the. Government allows ISYS an increase in the contract amounts resulting from such additional costs?

The parties have agreed that the Court may interpret the contract language and declare the rights of the parties under the subcontract. If the Court determines that Commonwealth has a right to proceed directly against ISYS, it must then be determined whether or not there is sufficient evidence to permit judgment to be entered in favor of Commonwealth and against ISYS or whether further trial must be had on the damage issue.

*723 Count I. Turnover.

Commonwealth, by leaving the project and terminating its work at the end of June, 1987, breached its contractual obligation to complete the project. At the time of the breach, it had billed ISYS for $3,437,417.65 for work done on the project. Commonwealth had received $3,203,169.62. This left a balance of $234,248.03 for invoiced amounts. In the pretrial statement, Filing No. 15, at Paragraph III.8., “uncon-troverted facts,” ISYS admits, without considering any offsets, that Commonwealth is still owed $225,957.00 for work under the contract. Commonwealth believes that the amount owed under the contract is $234,-248.03. ISYS spends a substantial amount of time in its final argument and brief urging the Court to find that Commonwealth has presented insufficient evidence to support the $225,957.00 amount and, therefore, the Court should find that Commonwealth has failed to meet its burden of proof and is owed nothing for the work performed prior to the breach of the contract. However, the Court believes ISYS misunderstands the purpose of the pretrial statement. That statement contained the position of the parties with regard to controverted and uncontroverted facts. The admission by ISYS in the summary of un-controverted facts eliminates the need for Commonwealth to present any evidence on its allegation that prior to the breach it performed work on the contract and was due at least $225,957.00 for such work. Had ISYS simply admitted that it had been billed a specific amount, such an admission would not have permitted Commonwealth to stand on the admission, but Commonwealth would have been required to present evidence of the completion of the work which resulted in its claim of at least $225,957.00.

From testimony of Mr. Cerretto, a witness for ISYS, the Court finds as a fact that the project was completed, as far as Commonwealth’s subcontract is concerned, in February, 1988. ISYS now claims it owes Commonwealth nothing because Commonwealth did not complete the contract. However, the contract work was eventually completed and ISYS admitted an amount due for work completed prior to Commonwealth’s breach. ISYS has a claim of offset which will be treated in this opinion.

This Court finds as a fact, based upon the admission in the pretrial statement, that ISYS owes Commonwealth as of August 8, 1987, the bankruptcy petition date, $225,957.00.

Commonwealth claims to be owed an additional $8,291.03 based upon its billings to ISYS as of the date of the breach. The only evidence Commonwealth presented concerning the additional monies owed was the testimony of Thomas Shea, former general counsel for Commonwealth, and Exhibits 1 and 2. Mr. Shea testified that in his investigation of the project, he discussed its status with Mr. Steve Trutna, formerly an employee of Commonwealth but, following the breach, an employee of ISYS. The questions and answers concerning the matter are contained on page 71 of the transcript of the trial and are as follows:

Line 4, Q. Alright, what did Mr. Trutna say to you insofar as what the balance of the work was to complete the Commonwealth subcontract?

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carroll v. US Postal Service
764 F. Supp. 143 (E.D. Missouri, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
118 B.R. 720, 1990 Bankr. LEXIS 1849, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commonwealth-electric-co-v-isys-securities-systems-inc-in-re-nebraskab-1990.