Commonwealth Edison Company v. Illinois Commerce Commission

2016 IL 118129, 402 Ill. Dec. 36
CourtIllinois Supreme Court
DecidedMay 19, 2016
Docket118129
StatusUnpublished
Cited by2 cases

This text of 2016 IL 118129 (Commonwealth Edison Company v. Illinois Commerce Commission) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commonwealth Edison Company v. Illinois Commerce Commission, 2016 IL 118129, 402 Ill. Dec. 36 (Ill. 2016).

Opinion

2016 IL 118129

IN THE SUPREME COURT OF THE STATE OF ILLINOIS

(Docket No. 118129)

COMMONWEALTH EDISON COMPANY et al., Appellees, v. ILLINOIS COMMERCE COMMISSION et al. (Illinois Competitive Energy Association et al., Appellants).

Opinion filed May 19, 2016.

JUSTICE KILBRIDE delivered the judgment of the court, with opinion.

Chief Justice Garman and Justices Freeman, Thomas, Karmeier, Burke, and Theis concurred in the judgment and opinion.

OPINION

¶1 The subject of this case is the FutureGen 2.0 “clean coal” project in Illinois. The issue brought before this court is whether the Illinois Commerce Commission (the Commission) has the authority to require Commonwealth Edison and Ameren, the two largest utility companies in Illinois, to negotiate energy procurement from the FutureGen 2.0 power plant on behalf of themselves as well as the state’s smaller Area Retail Electric Suppliers (ARES). After we allowed the petition for leave to appeal, federal funding for the FutureGen 2.0 project was suspended, project development efforts were ceased, and the sourcing agreements that are the subject of this appeal were terminated. We dismiss this appeal as moot and vacate the judgment of the appellate court without expressing an opinion on the merits of the appellate court opinion.

¶2 BACKGROUND

¶3 FutureGen Industrial Alliance, Inc. (FutureGen Alliance) was created to research and develop near-zero emissions coal technology and sought to use carbon capture and storage to develop the world’s first near-zero emissions coal power plant. The proposed retrofitted “clean coal” electric energy generating facility, known as “FutureGen 2.0,” was to be located in Meredosia, Illinois, and scheduled to begin operating in 2017.

¶4 In an effort to secure private investment for FutureGen 2.0, the Commission issued an order finding that it has the authority to force public utility companies and privately owned and competitively operated ARES to purchase all of FutureGen 2.0’s electrical output over a 20-year term. The Illinois Competitive Energy Association and Illinois Industrial Energy Consumers challenged the Commission’s authority to force ARES to enter into sourcing agreements. On appeal, the appellate court affirmed the order of the Commission. 2014 IL App (1st) 130544. This court allowed the petition for leave to appeal of the Illinois Competitive Energy Association and Illinois Industrial Energy Consumers pursuant to Illinois Supreme Court Rule 315 (eff. July 1, 2013).

¶5 In February 2015, while the appeal was pending before this court, the United States Department of Energy suspended funding for the FutureGen 2.0 project. This court then issued an order directing the parties to file additional briefs addressing the issue of mootness and, later, issued an order that the parties file reports concerning the status of the FutureGen 2.0 project.

¶6 FutureGen Alliance filed a supplemental brief informing this court that it had exhausted all administrative and legislative remedies available for restoring federal funding for the FutureGen 2.0 project. Consequently, the FutureGen Alliance board of directors approved a resolution in January 2016 ceasing all FutureGen 2.0 project development efforts. FutureGen Alliance’s supplemental brief also indicated its intention to terminate the sourcing agreements that are the subject of this appeal.

-2- ¶7 The Commission, FutureGen Alliance, and Commonwealth Edison filed a joint status report. The joint status report informed the court that the sourcing agreements that are the subject of this appeal were terminated and the appeal is now moot.

¶8 Appellants, Illinois Competitive Energy Association and Illinois Industrial Energy Consumers, filed their status report, agreeing that this appeal is now moot. However, appellants ask this court to address the substantive issues under the public interest exception to the mootness doctrine.

¶9 ANALYSIS

¶ 10 An appeal is moot if no actual controversy exists or when events have occurred that make it impossible for the reviewing court to render effectual relief. In re Marriage of Peters-Farrell, 216 Ill. 2d 287, 291 (2005). “As a general rule, courts of review in Illinois do not decide moot questions, render advisory opinions, or consider issues where the result will not be affected regardless of how those issues are decided.” In re Barbara H., 183 Ill. 2d 482, 491 (1998). “This court will not review cases merely to establish a precedent or guide future litigation.” Madison Park Bank v. Zagel, 91 Ill. 2d 231, 235 (1982). When a decision on the merits would not result in appropriate relief, such a decision would essentially be an advisory opinion. Berlin v. Sarah Bush Lincoln Health Center, 179 Ill. 2d 1, 8 (1997).

¶ 11 Here, after federal funding of the FutureGen 2.0 project was suspended, FutureGen Alliance ceased all FutureGen 2.0 project development efforts, and the sourcing agreements that are the subject of this appeal were terminated. Thus, events have occurred that make it impossible for this court to grant effectual relief, rendering this appeal moot.

¶ 12 Despite agreeing that this appeal is now moot, appellants argue that this court should consider the issues raised in this appeal pursuant to the public interest exception to the mootness doctrine. The public interest exception to the mootness doctrine permits review of an otherwise moot question when the magnitude or immediacy of the interests involved warrants action by the court. See In re Shelby R., 2013 IL 114994, ¶ 16. The public interest exception to the mootness doctrine applies only when “(1) the question presented is of a public nature; (2) an

-3- authoritative determination of the question is desirable for the future guidance of public officers; and (3) the question is likely to recur.” In re Shelby R., 2013 IL 114994, ¶ 16.

¶ 13 The public interest exception is narrowly construed and requires a clear showing of each of its criteria. Felzak v. Hruby, 226 Ill. 2d 382, 393 (2007). If any one of the criteria is not established, the exception may not be invoked. In re Commitment of Hernandez, 239 Ill. 2d 195, 202 (2010). Indeed, the public interest exception is invoked only on “rare occasions” when there is an extraordinary degree of public interest and concern. People ex rel. Partee v. Murphy, 133 Ill. 2d 402, 410 (1990) (citing People ex rel. Cairo Turf Club, Inc. v. Taylor, 2 Ill. 2d 160, 164 (1954), and La Salle National Bank v. City of Chicago, 3 Ill. 2d 375, 380 (1954)). In this case, none of the criteria was established.

¶ 14 We begin by considering the first requirement for the public interest exception to the mootness doctrine to apply, whether “the question presented is of a public nature.” In re Shelby R., 2013 IL 114994, ¶ 16. The question presented in this appeal would have incidentally affected Illinois electric energy consumers who would ultimately have paid higher utility rates as a result of the sourcing agreements. Undoubtedly, Illinois electric energy consumers have an interest in affordable utility rates. Nevertheless, the issue in this case uniquely applies only to a specific group of regulated entities for a specific project. FutureGen 2.0, if it had succeeded, would have been the world’s first near-zero emissions coal power plant. Development of the FutureGen 2.0 project, however, has ceased. The sourcing agreements relating to the FutureGen 2.0 project were terminated. Because of the unique character of this project, any public nature of the question presented in this appeal ceased to exist with the termination of the FutureGen 2.0 project. We therefore determine that this case does not present a question of a public nature. Accordingly, the first criterion is not met for application of the public interest exception to the mootness doctrine.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maday v. Township High School District 211
2018 IL App (1st) 180294 (Appellate Court of Illinois, 2018)
Commonwealth Edison Company v. Illinois Commerce Commission
2016 IL 118129 (Illinois Supreme Court, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
2016 IL 118129, 402 Ill. Dec. 36, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commonwealth-edison-company-v-illinois-commerce-commission-ill-2016.