Commonwealth Edison Co. v. Elston Avenue Properties, LLC

2017 IL App (1st) 153228, 76 N.E.3d 761
CourtAppellate Court of Illinois
DecidedMarch 31, 2017
Docket1-15-3228
StatusUnpublished
Cited by4 cases

This text of 2017 IL App (1st) 153228 (Commonwealth Edison Co. v. Elston Avenue Properties, LLC) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commonwealth Edison Co. v. Elston Avenue Properties, LLC, 2017 IL App (1st) 153228, 76 N.E.3d 761 (Ill. Ct. App. 2017).

Opinion

2017 IL App (1st) 153228 No. 1-15-3228

FIRST DIVISION March 31, 2017

IN THE

APPELLATE COURT OF ILLINOIS

FIRST JUDICIAL DISTRICT

COMMONWEALTH EDISON CO., ) Appeal from the Circuit Court of ) Cook County. Plaintiff-Appellee, ) ) v. ) ) ELSTON AVENUE PROPERTIES, LLC, ) DEVELOPMENTAL RESOURCES, INC., MARIA) No. 06 L 50404 PAPPAS, Treasurer and County Collector of Cook ) County, DAVID ORR, County Clerk of Cook ) County, and UNKNOWN OWNERS, ) ) Honorable Alexander P. White Defendants-Appellants. ) Judge Presiding.

JUSTICE SIMON delivered the judgment of the court, with opinion. Justices Harris and Mikva concurred in the judgment and opinion.

OPINION

¶1 This appeal follows drawn-out negotiations and proceedings precipitated by eminent

domain. Commonwealth Edison needed to dig on private property to run underground wires. The

parties reached an agreement on compensation and on the specifications for digging and

restoring the property. ComEd did not specifically follow the agreed-upon specifications for

refilling the dig sites, resulting in nonconforming work. Nonetheless, ComEd asked the court to

approve its performance and rule that its obligations had been satisfied. After the parties

presented evidence, the trial court issued an order of satisfaction from which the property owner

now appeals. We affirm. No. 1-15-3228

¶2 BACKGROUND

¶3 Plaintiff Commonwealth Edison filed an eminent domain suit to take underground

easements on property owned by defendant Elston Avenue Properties, LLC (“Elston

Properties”). The purpose of the taking was to construct deep vaults beneath the surface of the

property in order to ultimately carry electric transmission lines under the Chicago River. The

easements were part of plans for the “West Loop Project” designed to reinforce the electrical

capacity provided to the Chicago Central Business District. After the case was filed and after

Elston Properties filed a traverse, 1 the parties negotiated the easements and entered an agreed

judgment. The agreed judgment, as amended (referred to as the “Final Order”), stipulated the

compensation to be paid for the easements and the specifications for construction. Judgment was

entered on the Final Order terminating the eminent domain proceedings.

¶4 Construction began and ComEd excavated four shafts over 57 feet deep. The shafts were

approximately 14 feet wide and 35 feet long. They were reinforced with steel bracing. ComEd

then tunneled from the shafts under the river and ran the transmission lines through conduits to

their destination. The shafts were then backfilled and the surface was restored. However—and

this is the genesis of the dispute—ComEd deviated from the agreed specifications and filled a

portion of the vaults with sand where the Final Order called for concrete.

¶5 Following construction, ComEd tendered “as-built plans” to Elston Properties. ComEd

then filed a motion in the trial court for an order of satisfaction. That motion stated that all

compensation had been paid and that all work had been completed and, therefore, that ComEd

was seeking a determination that its obligations under the Final Order were satisfied.

¶6 Elston Properties noticed a deviation between the as-built plans and the specifications set

1 A traverse is a method by which a property owner can challenge a condemnation proceeding. Forest Preserve District of Du Page County v. Miller, 339 Ill. App. 3d 244, 250 (2003).

No. 1-15-3228

forth in the Final Order and alerted ComEd. The as-built plans indicated (as was actually the

case) that sand had been used instead of concrete in some areas. After being notified of the

deviation, ComEd prepared “revised” as-built plans that depicted concrete in much of the area

where it was supposed to be according to the Final Order, but where the original as-built plans

indicated (again, as was actually the case) that sand had been used. During the eight months

between Elston Properties notifying ComEd about the deviation and ComEd tendering the

revised plans, Elston Properties had performed its own testing on the composition of the vaults.

The testing demonstrated that the originally-tendered as-built plans actually reflected the true

method of construction—that sand had been used in areas where concrete was called for. Elston

Properties therefore believed that ComEd was attempting to deceive it with the revised as-built

plans.

¶7 There are two components of the construction that are important to distinguish—the duct

banks and the shafts themselves. The duct banks consist of the conduits that run horizontally

underground and the shafts are the vertical cavities descending from ground level to reach the

conduits. The specifications originally stated that the ducts were to be encased with 3000 psi

concrete and then, using stair-stepping, 1500 psi concrete was to be placed on top to fill the shaft

excavation. However, after construction began, the parties agreed to modify that backfilling

specification. Because the stair-stepping required for placing the 1500 psi concrete over the 3000

psi concrete was time-consuming and expensive, the parties agreed to just use 3000 psi concrete

throughout. 2 During the course of construction, however, ComEd gave the instruction to the

2 The original agreed order stated that "The vault excavations must be filled with min. 1500 psi lean concrete to a level eight (8) feet below existing grade, then CA-1 compacted to 95% modified proctor to a level four (4) feet below grade, then clay compacted to 95% modified proctor to grade." The Final Order states that "the required vault excavations be filled with 3000 psi concrete to a level of -5 CCD, then granular thermal backfill compacted to 95% modified proctor to elevation 0 CCD, then CA-1 compacted to 95% modified proctor level four (4) feet below grade, then clay compacted to 95% proctor to grade."

contractor to perform the duct backfilling with lifts of 3000 psi concrete “and then backfill with

compacted thermal sand.” The parties had agreed to modify the original agreement so that some

sand could be used as backfill in the duct banks, but they never agreed to such a modification for

backfilling the vaults in the manner it was done. There is no genuine dispute that the backfilling

was not done in accordance with the Final Order.

¶8 The specifications for construction set forth in the parties’ Statement of Conditions and

Restrictions and incorporated into the Final Order are intended “to assure ability of the Owner to

build over the ComEd facilities.” To that end, the Final Order states that:

“Upon completion of the installation of the Project Facilities in the

Permanent Subterranean Easement Areas, the Owner shall have the right to

construct improvements, including buildings, or grant easements above, or

between, or beyond the Project Facilities, provided only that the concrete

encasement around the Project Facilities (the 1500 psi lean concrete at the vault

excavations and the 100 psi flowable fill concrete at the duct bank excavations)

will not be penetrated by the foundations. The Owner may install deep

foundations (bearing elevation below -9.00 CCD) having a maximum bearing

pressure of up to 20,000 pounds per square foot anywhere within the Permanent

Subterranean Easement Area. Deep foundations located directly above the 6’

diameter reinforced concrete pipe casing shall be designed so that they do not

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Marriage of Watkins
2017 IL App (3d) 160645 (Appellate Court of Illinois, 2017)
Commonwealth Edison Co. v. Elston Avenue Properties, LLC
2017 IL App (1st) 153228 (Appellate Court of Illinois, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
2017 IL App (1st) 153228, 76 N.E.3d 761, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commonwealth-edison-co-v-elston-avenue-properties-llc-illappct-2017.