Coast Pump Associates v. Stephen Tyler Corp.

62 Cal. App. 3d 421, 133 Cal. Rptr. 88, 1976 Cal. App. LEXIS 1919
CourtCalifornia Court of Appeal
DecidedSeptember 30, 1976
DocketCiv. 38195
StatusPublished
Cited by6 cases

This text of 62 Cal. App. 3d 421 (Coast Pump Associates v. Stephen Tyler Corp.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coast Pump Associates v. Stephen Tyler Corp., 62 Cal. App. 3d 421, 133 Cal. Rptr. 88, 1976 Cal. App. LEXIS 1919 (Cal. Ct. App. 1976).

Opinion

*423 Opinion

EMERSON, J.

* Plaintiff Coast Pump Associates (hereafter appellant) appeals from a judgment that it take nothing upon its complaint against defendant Stephen Tyler Corporation (hereafter respondent). Appellant contends that respondent, the prime contractor on a public construction project, violated the Subletting and Subcontracting Fair Practices Act (Gov. Code, § 4100 et seq.) 1 when it refused to honor a bid submitted by appellant as subcontractor. In rendering judgment for respondent, the trial court made a finding of fact, among others, that respondent did not use appellant’s bid in computing its own overall bid figure. Consequently it concluded that respondent did not act improperly as to appellant and that appellant therefore suffered no damage. We are of the opinion that respondent clearly violated the Fair Practices Act and that whether or not it used appellant’s bid is immaterial. In such case, appellant is entitled to recover as damages the benefit of the bargain it would have realized had it not wrongfully been deprived of the subcontract. (Southern Cal. Acoustics Co. v. C. V. Holder, Inc. (1969) 71 Cal.2d 719, 727 [79 Cal.Rptr. 319, 456 P.2d 975].)

Facts

Appellant submitted a bid to furnish pumping equipment for use by respondent in the construction of a sewage collection system for the Hopland Public Utilities District. The equipment which appellant offered to supply was of the “Hydromatic” brand. Respondent, preparatory to bidding on the prime contract, recorded figures on its bid form for items B1 and B2 (pumping stations one and two) which apparently were based in part on the prices quoted by appellant. Respondent also listed the brand name of appellant’s equipment in the spaces provided on the bid form, which form was furnished or required to be used by the district.

Respondent’s bid on the prime contract was due at 2 p.m. on July 31, 1974. At 1:40 p.m. on that date, Stephen Tyler, respondent’s president, learned from his office that Walton-Hayes Associates had offered to supply Smith & Loveless pumping machinery at prices lower than that quoted by appellant for the Hydromatic equipment. Tyler *424 decided to use the Walton-Hayes figures in computing his own final bid. He did not, however, remove the name “Hydromatic” from the bid form or alter the prices previously recorded on the form for items B1 and B2; he merely put down a figure for the separate item of “site clearing and grubbing” (item B3) which reflected the savings afforded by the lower Walton-Hayes bid. Tyler testified that it was usually his practice in bidding on contracts to leave blank one item on the bid form, such as site clearing and grubbing, so that it could be filled in to reflect last-minute bids from subcontractors on other items. He further testified that he did not change the name “Hydromatic” on the bid form because of an oversight due to the shortness of time.

On September 27, 1974, sometime after respondent’s bid was accepted by the district, Tyler wrote to the district’s representative and requested permission to use the Smith & Loveless machinery rather than the Hydromatic equipment. The letter described respondent’s receipt and use of the Walton-Hayes bid and stated that refusal of the requested change would cause “financial hardship.” Permission for the change was granted by the district’s representative-.on the ground that respondent had committed an excusable mistake. On a date not specified in the record, respondent notified appellant, apparently by telephone, that its subcontract bid had not been accepted. It is clear from these facts that the substitution of subcontractors was made after the award of the prime contract.

Bid Shopping and Substitution

Respondent chooses to assert that it engaged in a practice known as bid shopping; it then argues that “bid shopping” does not violate the Fair Practices Act unless it occurs after the award of the prime contract.

Bid shopping has been defined as “. . . the use of the low bid already received by the general contractor to pressure other subcontractors into submitting even lower bids.” (Southern Cal. Acoustics Co. v. C. V. Holder, Inc., supra, at p. 726, fn. 7; italics added.) The record herein contains no indication that respondent used appellant’s bid for that purpose either before or after the award of the prime contract.

The Fair Practices Act does not contain the term “bid shopping.” Section 4107, as it existed at the times here involved, proscribed the substitution, by a prime contractor whose bid was accepted, of any person as subcontractor in place of the subcontractor listed in the *425 original bid. 2 The only exception to this proscription which is applicable here concerns relief from inadvertent clerical error, which we discuss below.

Respondent’s assertion that the lower Walton-Hayes bid was substituted before the prime contract was awarded cannot avail it. While it may be true that the lower price was reflected (through adjustment of the site clearing and grubbing figure) appellant remained the listed subcontractor. Section 4107 prohibits in unambiguous terms the substitution, except in certain circumstances, of one subcontractor for another listed in the bid of the prime contractor. Moreover, that the statute is applicable in situations such as that here under review is suggested by Southern Cal. Acoustics Co. v. C. V. Holder, Inc., supra, 71 Cal.2d 719, upon which respondent relies. There the prime contractor requested and received *426 permission from the awarding authority to make a substitution after the award of the prime contract, apparently on the ground that the plaintiff had been inadvertently listed in the place of the intended subcontractor. (Id. at p. 722.) The court held that the plaintiff subcontractor had stated a cause of action for breach of the duty imposed by section 4107. (Id., at p. 727.)

Thus it is apparent not only that respondent violated the Fair Practices Act, but that its conduct fell within the rule enunciated in Bay Cities Paving & Grading, Inc. v. Hensel Phelps Constr. Co. (1976) 56 Cal.App.3d 361, 365 [128 Cal.Rptr. 632] as follows: “Once the prime contractor’s bid is accepted, he is forbidden to make substitutions in place of the subcontractor designated in the original bid except with the consent of the contracting agency.” As further noted in Bay Cities Paving & Grading, Inc. v. Hensel Phelps Constr. Co., supra, the purpose of section 4107 is to protect the original subcontractor against replacement by another subcontractor. (Id.)

Inadvertent Clerical Mistake

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Beavor v. Tomsheck
2022 NV 71 (Nevada Supreme Court, 2022)
R.J. Land & Associates Construction Co. v. Kiewit-Shea
81 Cal. Rptr. 2d 615 (California Court of Appeal, 1999)
Clark Pacific v. Krump Construction, Inc.
942 F. Supp. 1324 (D. Nevada, 1996)
Cal-Air Conditioning, Inc. v. Auburn Union School District
21 Cal. App. 4th 655 (California Court of Appeal, 1993)
R. M. Sherman Co. v. W. R. Thomason, Inc.
191 Cal. App. 3d 559 (California Court of Appeal, 1987)
Kellum v. Gray
590 S.W.2d 33 (Supreme Court of Arkansas, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
62 Cal. App. 3d 421, 133 Cal. Rptr. 88, 1976 Cal. App. LEXIS 1919, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coast-pump-associates-v-stephen-tyler-corp-calctapp-1976.