Bay Cities Paving & Grading, Inc. v. Hensel Phelps Construction Co.

56 Cal. App. 3d 361, 128 Cal. Rptr. 632, 1976 Cal. App. LEXIS 1359
California Court of Appeal·Decided March 19, 1976·No. Civ. 36921·Published·Cited by 5 cases

Opinion

Opinion

CHRISTIAN, J.

Bay Cities Paving and Grading, Inc. appeals from a judgment that it take nothing upon its complaint against Hensel Phelps Construction Company.

Appellant submitted bids to respondent for excavation and asphalt paving subcontracts in connection with construction of the Bay Area Rapid Transit (BART) station at Concord, California. Respondent informed appellant that appellant’s bid for the excavation work was too high, but that appellant’s bid for the paving was almost the lowest bid. Appellant then cut its paving bid by $8,931, and respondent agreed to list appellant as its designated subcontractor for the paving.

Respondent submitted its total bid as prime contractor to BART. Included with the bid was the required “designation of subcontractors,” wherein respondent listed both itself and appellant as the subcontractors responsible for the paving and excavation work. Respondent was subsequently awarded the construction contract by BART.

After the contract was awarded, appellant asserted that it was the designated subcontractor for both the excavation and paving work, and sought an agreement from respondent that appellant perform the excavation at a price different from appellant’s subcontract bid. Respondent claimed it had specified itself as responsible for the excavation, declined appellant’s offer, and arranged for another company to perform the excavation. Respondent also offered appellant a written subcontract for the paving work, but appellant refused it. At respondent’s request, and without opposition from appellant, BART substituted another subcontractor to do the paving.

*365 Appellant then commenced this action against respondent, alleging breach of contract and violation of the statute regulating the designation of subcontractors in public works contracts. 1

Appellant contends that the trial court erred in determining that respondent did not violate the Subletting and Subcontracting Fair Practices Act by the manner in which respondent inserted itself and appellant on its list of designated subcontractors. In its designation of subcontractors, respondent listed both itself and appellant on the same line and indicated that the portion of work to be done was excavation and asphalt paving without differentiating the work to be done by each of the parties. The purpose of the Subletting and Subcontracting Fair Practices Act is to prevent the practices of bid shopping and bid peddling in connection with public works projects. 2 Bid shopping is the use of the lowest bid already received by the general or prime contractor to pressure other subcontractors into submitting even lower bids; bid shopping is prohibited by the statute after the award of the prime contract. (Southern Cal. Acoustics Co. v. C. V. Holder, Inc. (1969) 71 Cal.2d 719, fn. 7 at p. 726 [79 Cal.Rptr. 319, 456 P.2d 975].) To foster this purpose, the act requires any prime contractor bidding on public works to designate what portion of the work will be done by each subcontractor, and to “list only one subcontractor for each such portion as is defined by the prime contractor in his bid.” (§ 4104, subd. (b).) Once the prime contractor’s bid is accepted, he is forbidden to make substitutions in place of the subcontractor designated in the original bid except with the consent of the contracting agency. (§ 4107.) The purpose of these provisions is to protect the original subcontractor against replacement by either another subcontractor or by the prime contractor. (Fred J. Early, Jr., Co. v. County Sanitation Dist. (1963) 214 Cal.App.2d 505, 507-508 [29 Cal.Rptr. 633] [construing former § 4104, now § 4107].) By designating both itself and appellant on the same line in the designation of subcontractors, respondent frustrated the purpose of the listing requirement of the act. The purpose of the act was further frustrated by respondent’s listing of appellant on the same line in the *366 designation of subcontractors as respondent had listed excavation work to be done by respondent itself. Therefore, the trial court’s conclusion that respondent had not violated the act was incorrect.

Free access — add to your briefcase to read the full text and ask questions with AI

Bay Cities Paving & Grading, Inc. v. Hensel Phelps Construction Co., 56 Cal. App. 3d 361, 128 Cal. Rptr. 632, 1976 Cal. App. LEXIS 1359 (Cal. Ct. App. 1976).

56 Cal. App. 3d 361 (Bay Cities Paving & Grading, Inc. v. Hensel Phelps Construction Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Clark Pacific v. Krump Construction, Inc.
942 F. Supp. 1324 (D. Nevada, 1996)
Valley Crest Landscape, Inc. v. City Council
41 Cal. App. 4th 1432 (California Court of Appeal, 1996)
Cal-Air Conditioning, Inc. v. Auburn Union School District
21 Cal. App. 4th 655 (California Court of Appeal, 1993)
R. M. Sherman Co. v. W. R. Thomason, Inc.
191 Cal. App. 3d 559 (California Court of Appeal, 1987)
Coast Pump Associates v. Stephen Tyler Corp.
62 Cal. App. 3d 421 (California Court of Appeal, 1976)