Coal River Energy, LLC v. Sally Jewell

751 F.3d 659, 409 U.S. App. D.C. 485, 44 Envtl. L. Rep. (Envtl. Law Inst.) 20107, 2014 WL 1887375, 2014 U.S. App. LEXIS 8876
CourtCourt of Appeals for the D.C. Circuit
DecidedMay 13, 2014
Docket13-5119
StatusPublished
Cited by9 cases

This text of 751 F.3d 659 (Coal River Energy, LLC v. Sally Jewell) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coal River Energy, LLC v. Sally Jewell, 751 F.3d 659, 409 U.S. App. D.C. 485, 44 Envtl. L. Rep. (Envtl. Law Inst.) 20107, 2014 WL 1887375, 2014 U.S. App. LEXIS 8876 (D.C. Cir. 2014).

Opinion

Opinion for the Court filed by Senior Circuit Judge SILBERMAN.

SILBERMAN, Senior Circuit Judge:

Under the Surface Mining Control and Reclamation Act, operators of coal mines must pay a fee for each ton of coal they produce by mining. The purpose of the fee is to fund the restoration of land damaged by coal mining. A Department of the Interior regulation requires mine operators to pay the reclamation fee when the coal is ultimately sold or used, rather than immediately after the coal is removed from the ground. Appellant, a coal mine operator, sued the Secretary in district court, arguing that the regulation could not be constitutionally applied to coal sold for export because the Export Clause of the Constitution states that “No Tax or Duty shall be laid on Articles exported from any state.” U.S. Const. Art. I, § 9, cl. 5. The district court dismissed the case as untimely. We affirm.

I.

In 1977, Congress enacted the Reclamation Act, establishing a fee on all coal mined in the United States. The Act set a fee of “28 cents per ton of coal produced by surface coal mining and 12 cents per ton of coal produced by underground mining.” 30 U.S.C. § 1232(a). Immediately after the coal is removed from the ground it is impure, mixed with other rocks and dirt. So if the coal were weighed at that moment, it would be impossible to determine exactly how much mass is attributable to coal and how much to other impurities. The Secretary of the Interior, recognizing that problem, promulgated the following rule:

(a) The operator shall pay a reclamation fee on each ton of coal produced for sale, transfer, or use, including the products of in situ mining.
(b) The fee shall be determined by the weight and value at the time of initial bona fide sale, transfer of ownership, or use by the operator.

30 C.F.R. § 870.12 (emphasis added). Measuring the weight of the coal at the time of sale increases accuracy, as most impurities will likely have been removed. The total weight — and total fee charged— should therefore be less.

A number of coal companies, nevertheless, challenged the regulation — at least with respect to the sales of coal for export. A direct tax on coal exported would violate the little-known Export Clause of the Constitution, which provides that “No Tax or Duty shall be laid on Articles exported from any state.” U.S. Const. Art. I, § 9, cl. 5. They sued in the Court of Federal Claims, were initially successful, but lost on appeal in the Federal Circuit. See Consolidation Coal Co. v. United States, 528 F.3d 1344, 1348 (Fed.Cir.2008), cert. denied — U.S.-, 131 S.Ct. 2990, 180 L.Ed.2d 821 (2011). The Federal Circuit, relying on the constitutional avoidance canon, interpreted the statutory phrase “coal produced” as referring to coal extracted, and therefore the regulation should be interpreted as a fee imposed on extraction but collected at a later date.

A few months later a newly established coal company, Coal River — which did not participate in the Consolidation Coal litigation — filed essentially the same suit, a *662 challenge to the regulation based on the Export Clause, in our district court, seeking ultimately a D.C. Circuit conflict with the Federal Circuit. Appellant relied on our opinion in Drummond Coal Co. v. Hodel, 796 F.2d 503 (D.C.Cir.1986), in which a coal company challenged a different portion of the Secretary’s regulation, which clarified that impurities not removed at the time of sale were included in the weight of the coal on which the fee was imposed. Although we noted that the term “ ‘coal produced’... could reasonably be interpreted to include the entire process of extracting and selling coal ... or it could refer solely to the process of extraction,” and the government was resting on the former interpretation, our key observation was that “nowhere does the [Act] specify what elements comprise a taxable piece of coal.” Id. at 505. In that case, although we sanctioned pursuant to Chevron the Department’s interpretation that “coal produced” was legitimately interpreted as the final step at sale or use, we were not faced with the constitutional argument presented in Consolidation Coal, which led the Federal Circuit to conclude the constitutional avoidance canon trumped the Department’s prior interpretation. Therefore, appellant’s argument that there is a conflict between the two circuits is somewhat strained.

But as will become apparent, any supposed conflict with the Federal Circuit is not really relevant because we agree with the district court that appellant’s challenge to the rule comes too late to be entertained. Section 1276 of the Reclamation Act explicitly provides — similar to a number of statutes — that all challenges to regulations promulgated under the Act must be brought within sixty days of a rule’s promulgation. 30 U.S.C. § 1276(a)(1).

II.

Before considering the scope of limitations language of § 1276, we need to deal with Coal River’s argument that § 1276 does not even apply to its suit, which relies on the Constitution and the Administrative Procedure Act, because it is not one challenging the regulation on its face. As we understand Coal River’s contention, it is that § 1276 only covers “facial” challenges to the regulation, whereas appellant’s claim — based as it is only on the regulation’s impact on sales for export, not all sales or uses of coal — should be thought of as an as-applied challenge. Although Coal River’s case is admittedly directed to only certain transactions covered by the regulation, it is still a challenge to the rule as it is written, and not simply as it might later be interpreted or applied. As such, it is certainly a challenge to an “action by the Secretary promulgating national rules or regulations,” and therefore § 1276 applies. 1

We turn now to the timeliness of the claim under the Reclamation Act. To be sure, § 1276 provides a safety valve; a challenge may be brought “after such date if the petition is based solely on grounds arising after the sixtieth day.” Coal River argues that, as a new coal company that was not in existence at the time the regulation was promulgated, it can take advantage of the safety valve provision. The government, without explicitly conceding that such a circumstance falls within the regulation’s exception, does not contest *663 this interpretation. But it contends that the district court was correct in determining that, at most, Coal River had sixty days after the fee was first imposed on it.

Coal River argues that imposing a sixty-day limitation on an after-arising claim is unauthorized by the statute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brook v. Holzerland
Fifth Circuit, 2025
Bernerd Young v. SEC
956 F.3d 650 (D.C. Circuit, 2020)
Peri & Sons Farms, Inc. v. Acosta
374 F. Supp. 3d 63 (D.C. Circuit, 2019)
Peri & Sons Farms, Inc. v. Acosta
District of Columbia, 2019
Brookens v. Department of Labor
District of Columbia, 2018
Brookens v. Acosta
297 F. Supp. 3d 40 (D.C. Circuit, 2018)
Williams v. Perez
110 F. Supp. 3d 1 (District of Columbia, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
751 F.3d 659, 409 U.S. App. D.C. 485, 44 Envtl. L. Rep. (Envtl. Law Inst.) 20107, 2014 WL 1887375, 2014 U.S. App. LEXIS 8876, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coal-river-energy-llc-v-sally-jewell-cadc-2014.