Chevron U.S.A., Inc., a California Corporation v. United States Environmental Protection Agency

908 F.2d 468
CourtCourt of Appeals for the Ninth Circuit
DecidedSeptember 5, 1990
Docket89-70194
StatusPublished
Cited by4 cases

This text of 908 F.2d 468 (Chevron U.S.A., Inc., a California Corporation v. United States Environmental Protection Agency) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chevron U.S.A., Inc., a California Corporation v. United States Environmental Protection Agency, 908 F.2d 468 (9th Cir. 1990).

Opinion

WALLACE, Circuit Judge:

Chevron U.S.A. Inc. (Chevron) petitions for review of a final order of the United States Environmental Protection Agency (EPA) establishing upper limits for the discharge of water-borne oil and grease from offshore oil facilities operated by Chevron. The EPA acted pursuant to sections 301, 304 and 402 of the Clean Water Act (Act), 33 U.S.C. §§ 1311, 1314, 1342. Chevron brings the petition pursuant to 33 U.S.C. § 1369(b)(1). However, we hold that the petition is time-barred under that section; therefore, we deny the petition.

I

On August 8, 1979, the EPA issued a National Pollutant Discharge Elimination System (NPDES) permit to Chevron to operate certain oil extraction facilities in the Santa Barbara Channel. Pursuant to the Act, the permit limited discharge of oil and grease from the facility to a maximum daily level of 72 mg/1. In 1982, pursuant to the NPDES permit, Chevron began production of oil and gas at its Platform Grace facility. Soon afterward, Chevron observed unexpectedly high levels of oil and grease discharge. After studying the problem, Chevron concluded that certain aspects of oil and grease discharge had not been included in prior estimations of ex *469 pected pollutant release. Chevron determined that oil discharge came in two forms: first, oil mixed with water, and second, oil dissolved in water. The former component was well-known, easily measured, and relatively susceptible to cleanup technologies. The presence of oil pollutants dissolved in the water was not recognized at the time the permit was issued, and such pollutants are not readily observed or removed.

Without requesting a modification of the pollutant limit, Chevron successfully applied for a renewal of the Platform Grace permit on December 29, 1983. The renewed permit expired on March 31, 1984, but continued in force absent EPA action to revoke it. During this time pollutant discharge levels continued to exceed the 72 mg/1 level. Chevron experimented unsuccessfully with methods of controlling the discharge. Chevron also informally discussed the possibility of regulatory relief with the EPA. However, Chevron never formally requested an action on the part of the EPA, nor in any other way initiated proceedings which would have required agency action.

On December 29, 1988, the government filed a civil enforcement action against Chevron, alleging, among other violations, discharge of pollutant in excess of the permitted level from Platform Grace. Chevron then filed this petition for review on April 26, 1989, challenging the NPDES permit.

II

The relevant statute provided:

Review of the [EPA’s] action ... in promulgating any effluent standard, prohibition, or pretreatment standard ... [and] in issuing or denying any permit ..., may be had by any interested person in the Circuit Court of Appeals of the United States for the Federal judicial district in which such person resides or transacts such business upon application by such person. Any such application shall be made within ninety days from the date of such determination, approval, promulgation, issuance or denial, or after such date only if such application is based solely on grounds which arose after such ninetieth day.

33 U.S.C. § 1369(b)(1) (emphasis added) (since amended to provide for a 120-day rather than a 90-day limit). The EPA contends that Chevron’s application is time-barred under this provision.

Clearly, Chevron did not bring its petition within 90 days of the issuance of the challenged permit, as stated in section 1369. However, Chevron argues that it is asserting the challenge on the basis of “grounds which arose after [the] ninetieth day.” The EPA concedes that the evidence before this court indicates that the dissolved oil phenomenon, if any, on which Chevron bases the challenge was discovered in 1982, more than 90 days after the issuance of the permit. However, the EPA argues that we should construe the statute to require that challenges based on new grounds be made within 90 days of the discovery of the new grounds. Since Chevron admits that it recognized the dissolved oil problem as early as 1982, its petition filed in 1989 would, under the EPA’s view of the law, be untimely.

We are unable to conclude that the statute provides the 90-day limitation urged by the EPA. The relevant language expressly provides that the 90-day limit applies unless new grounds are discovered. When new grounds are alleged, challenges may be brought “after such date” (i.e., after 90 days after issuance); the statute does not then state a limitation period applicable to the exception. The legislative history similarly omits any such limitation:

The Committee recognizes that it would not be in the public interest to measure for all time the adequacy of a promulgation of any standard requirement or regulation by the information available at the time of such promulgation.... The judicial review section, therefore, provides that any person may challenge any requirement after the date of promulgation whenever it is alleged that significant new information has become available.

*470 S.Rep. No. 414, 92nd Cong., 1st Sess. 85 (1971), reprinted in 1972 U.S.Code Cong. & Admin.News 3668, 3751.

We conclude that the only fair reading of the statute is that Congress did not provide a statute of limitations for bringing challenges based on grounds arising after the expiration of the 90-day limit. Based upon this, Chevron argues that, if no limitations period is provided, we should accept challenges filed at any time after the 90-day period so long as new evidence is alleged. Ordinarily, however, when courts are faced with federal statutes which do not specify a limitations period, they will apply the period set forth in the most nearly analogous state or federal law. Reed v. United Transportation Union, 488 U.S. 319, 109 S.Ct. 621, 625-26, 102 L.Ed.2d 665 (1989) (Reed)) Del Costello v. Teamsters, 462 U.S. 151, 171-72, 103 S.Ct. 2281, 2294-95, 76 L.Ed.2d 476 (1983); Occidental Life Insurance Co. v. EEOC, 432 U.S. 355, 367, 97 S.Ct. 2447, 2455, 53 L.Ed.2d 402 (1977); Sierra Club v. Chevron U.S.A., Inc., 834 F.2d 1517, 1520-22 (9th Cir.1987) (Sierra Club); 2 Moore’s Federal Practice § 3.08[2]. Although under certain circumstances we may conclude that no statute of limitations should apply, see Sierra Club, 834 F.2d at 1520, we refuse to do so here.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
908 F.2d 468, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chevron-usa-inc-a-california-corporation-v-united-states-ca9-1990.