Clevecon, Inc. v. Northeast Ohio Regional Sewer District

628 N.E.2d 143, 90 Ohio App. 3d 215, 1993 Ohio App. LEXIS 4255
CourtOhio Court of Appeals
DecidedSeptember 13, 1993
DocketNo. 63319.
StatusPublished
Cited by21 cases

This text of 628 N.E.2d 143 (Clevecon, Inc. v. Northeast Ohio Regional Sewer District) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clevecon, Inc. v. Northeast Ohio Regional Sewer District, 628 N.E.2d 143, 90 Ohio App. 3d 215, 1993 Ohio App. LEXIS 4255 (Ohio Ct. App. 1993).

Opinion

*218 Patricia A. Blackmon, Judge.

This appeal requires us to decide whether the absence of contractual privity is an absolute bar to malpractice liability by a design professional who causes economic damages from its architectural plans and specifications, and to decide if the setoff provision of R.C. 2807.32(F) applies to this case. Jenny Engineering Corporation (“Jenny”), defendant-appellant, appeals the decision of the Cuyahoga County Court of Common Pleas, which denied Jenny’s motion for summary judgment and motion for directed verdict. Jenny’s appeal also challenges the trial court’s failure to grant Jenny’s motion for judgment notwithstanding the verdict and a setoff of the jury’s verdict under R.C. 2307.32(F). Jenny assigns the following errors for our review:

“I. The trial, court erred in overruling defendant-appellant Jenny’s motion for summary judgment, three motions for a directed verdict during trial, and post-trial motion for judgment notwithstanding the verdict because, in the absence of privity of contract, a cause of action does not exist in favor of a contractor against an architect or engineer for purely economic losses, and there was no contractual relationship between Clevecon and Jenny.

“II. The trial court erred in instructing the jury that Clevecon could recover economic damages premised on tort theories of liability, in refusing to give a jury instruction based on the Floor Craft decision, and in instructing the jury regarding Clevecon’s breach of warranty theory.

“III. The trial court erred in overruling defendant-appellant Jenny’s motion for setoff df verdict pursuant to Ohio Revised Code Section 2307.32(F) because Clevecon received $1.5 million in settlement with a joint tortfeasor originally joined as a defendant in this action.”

General contractor Clevecon, Inc., plaintiff-appellee, timely cross-appeals and assigns the following error:

“The trial court erred in refusing to give a jury instruction based on tortious interference with contract.”

Having reviewed the record of the proceedings and the legal arguments presented by the parties, we find that the assignments of error of Jenny are not well taken, and we find Clevecon’s cross-assignment of error equally not well taken. The decision of the trial court is affirmed, and the apposite facts follow.

The Northeast Ohio Regional Sewer District (“NEORSD”) entered into a contract with Clevecon, Inc. for a tunnel construction project. NEORSD entered into a contract with John David Jones and Associates as its lead architect and administrator of the design team. Jones entered into a contract with Alden Stilson and Associates to plan the profile of the tunnel and design structural and *219 surface work. Stilson entered into a contract with Jenny, defendant-appellant, to design the sewer tunnel. Jenny’s design included a two-part lining. The primary lining was to be made of concrete segmental rings. The final liner was to be made of concrete poured inside the primary liner.

During the course of construction, problems began with the segmental rings. During installation, some of the rings were damaged. While Clevecon maintained that the damage was merely cosmetic, Jenny’s engineers insisted on the removal and replacement of the rings. Later, another problem arose when Jenny’s engineers expressed concern about the watertightness of the tunnel. Clevecon informed Jenny that, although the tunnel was not completely watertight, Clevecon was building the tunnel according to Jenny’s specifications. Jenny insisted that Clevecon do additional caulking on the tunnel in an attempt to improve watertightness. A dispute also arose concerning the use of compressed air. Clevecon disagreed with Jenny’s claim that the use of compressed air was necessary.

During the construction of the tunnel, representatives from Jenny were present on the construction site and repeatedly gave orders regarding the construction of the tunnel. Despite arguments from Clevecon that Jenny’s design for the tunnel liner was unbuildable, Jenny continued to resist efforts by Clevecon to propose alternatives. This interference caused Clevecon to experience many delays and to incur additional expenses in completing the contract.

On February 23, 1987, Clevecon sued NEORSD, Jones, Stilson, Jenny, and Woodward-Clyde. Clevecon settled its claims against NEORSD for $1.5 million. Clevecon dismissed its complaint against Woodward-Clyde on November 2, 1987. After its settlement with NEORSD, Clevecon filed an amended and supplemental complaint which omitted its claims against NEORSD. The amended complaint set forth tort claims against Stilson, Jones, and Jenny. Summary judgment was entered in favor of Jones and Stilson on July 8, 1991. Jenny’s motion for summary judgment was denied and the case proceeded to trial.

Clevecon alleged that Jenny negligently prepared the plans and specifications for the project, which resulted in delays and cost overruns. Clevecon also claimed that Jenny breached warranties of constructability of its plans and specifications.

At the end of Clevecon’s case in chief and again at the close of the evidence, Jenny moved for a directed verdict. Both motions were denied. A jury ruled in favor of Clevecon and found Jenny negligent in the preparation and drafting of its plans and specifications as well as in the administration of the project. They also found that Jenny breached warranties in the preparation and drafting of the plans and specifications. Jenny was found to be sixty percent *220 responsible for Clevecon’s loss. Clevecon was found to be forty percent contributorily negligent. The jury awarded Clevecon $1,035,000. Jenny moved for judgment notwithstanding the verdict and for a new trial. Jenny also moved for setoff of the verdict based on the settlement between Clevecon and NEORSD. These motions were denied on January 30, 1992. In resolving the issue of whether lack of privity of contract is an absolute bar in this case, we must look to the Ohio Supreme Court’s decision in Floor Craft Floor Covering, Inc. v. Parma Community Gen. Hosp. Assn. (1990), 54 Ohio St.3d 1, 560 N.E.2d 206. Jenny argues that there is no liability because of the Supreme Court’s syllabus in Floor Craft, which specifically states that in the absence of privity of contract, no cause of action exists to recover economic damages against design professionals involved in drafting plans and specifications. In its oral argument, Clevecon urged that we should look beyond the facts of Floor Craft to the Floor Craft dictum which strongly suggests that where there is a nexus that serves as a substitute for contractual privity, liability for economic loss exists in a malpractice action against a design professional. We agree with Clevecon’s argument. Therefore, we hold that lack of privity is not an absolute bar to a design professional’s malpractice action when there is a nexus that can serve as a substitute for privity.

In reaching our conclusion, we necessarily look to the Floor Craft decision.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Atwood v. UC Health
S.D. Ohio, 2019
CSX Transp., Inc. v. Columbus Downtown Dev. Corp.
307 F. Supp. 3d 719 (S.D. Ohio, 2018)
Balfour Beatty Infrastructure, Inc. v. Rummel Klepper & Kahl, LLP
155 A.3d 445 (Court of Appeals of Maryland, 2017)
Snowden v. Ekeh
2016 Ohio 4976 (Ohio Court of Appeals, 2016)
Balfour Beatty Infrastructure, Inc. v. Rummel Klepper & Kahl, LLP
130 A.3d 1024 (Court of Special Appeals of Maryland, 2016)
Vanatta v. Akers, Unpublished Decision (12-11-2003)
2003 Ohio 6615 (Ohio Court of Appeals, 2003)
Laurent v. Flood Data Services, Inc.
766 N.E.2d 221 (Ohio Court of Appeals, 2001)
Sito v. Jackshaw Pontiac, Inc.
713 N.E.2d 40 (Ohio Court of Appeals, 1998)
Nicholson v. turner/cargile
669 N.E.2d 529 (Ohio Court of Appeals, 1995)
National Steel Erection, Inc. v. J.A. Jones Construction Co.
899 F. Supp. 268 (N.D. West Virginia, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
628 N.E.2d 143, 90 Ohio App. 3d 215, 1993 Ohio App. LEXIS 4255, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clevecon-inc-v-northeast-ohio-regional-sewer-district-ohioctapp-1993.