Mosser Constr. v. W. Waterproofing Co., Unpublished Decision (7-14-2006)

2006 Ohio 3607
CourtOhio Court of Appeals
DecidedJuly 14, 2006
DocketCourt of Appeals No. L-05-1164, Trial Court No. CI-04-3085.
StatusUnpublished

This text of 2006 Ohio 3607 (Mosser Constr. v. W. Waterproofing Co., Unpublished Decision (7-14-2006)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mosser Constr. v. W. Waterproofing Co., Unpublished Decision (7-14-2006), 2006 Ohio 3607 (Ohio Ct. App. 2006).

Opinion

DECISION AND JUDGMENT ENTRY
{¶ 1} This is an appeal from a judgment of the Lucas County Court of Common Pleas that granted the summary judgment motion of defendant-appellee, Munger Munger Associates Architects, Inc. ("Munger") in an action filed by plaintiff-appellants, Mosser Construction, Inc. and St. Paul Fire and Marine Insurance Company ("St. Paul").

{¶ 2} This case involves the construction of the Howard L. Collier Nursing Allied Health Building for the Medical College of Ohio ("MCO") in Toledo, Ohio ("the project"). The relevant and undisputed facts of this case are as follows. In 1993, Munger entered into an agreement, titled the Associate Architect's Agreement, with the state of Ohio, Department of Administrative Services, through the Deputy Director for the Division of Public Works ("deputy director"). Under the terms of the agreement, Munger was named the Associate Architect for the project and was responsible for, among other things, preparing the project's drawings and specifications for the approval of the deputy director, assisting the deputy director in obtaining bids and awarding construction contracts for the project, and administering the construction contracts for the benefit of the deputy director and MCO.

{¶ 3} In 1995, Mosser entered into a contract with the state of Ohio, through the Director of Administrative Services, under which Mosser was to act as the lead contractor on the MCO project ("Contractor's Agreement"). Under the terms of that contract, Mosser's primary responsibility was to construct the building in accordance with Munger's design and contract drawing specifications as well as to supervise subcontractors working under it.

{¶ 4} After the building was completed, water infiltration, moisture and mold were discovered inside the building. An investigation revealed that one of the major causes of the water infiltration was the faulty design and construction of a trench drain. Munger designed the trench drain, Mosser installed it, and Western Waterproofing, a subcontractor of Mosser, installed a waterproofing membrane lining known as EPDM in the trench drain.

{¶ 5} After the water problems were discovered, the deputy director assigned Munger's agreement and Mosser's contract to MCO. Munger and Mosser then worked with MCO to remediate the water problems. On April 28, 2003, Munger and MCO signed an amendment to the Associate Architect's Agreement, through which Munger agreed to certain redesigns and repairs to the building at no cost to MCO, and MCO agreed to waive all claims it had against Munger. Similarly, in May 2003, Mosser and MCO signed an amendment to the Contractor's Agreement. Under the terms of that amendment, Mosser agreed to execute enumerated repairs to the building at no cost to MCO and MCO waived all claims that it had against Mosser. Mosser also waived any claims it may have had against MCO arising out of the building project. Subsequently, Mosser allegedly spent $1,046,012 to rebuild the trench drain according to new specifications and designs provided by Munger.

{¶ 6} On May 12, 2004, Mosser and St. Paul Fire, as subrogee, filed suit against Munger and other subcontractors involved in the project to recover the costs of rebuilding the trench drain. As against Munger, Mosser and St. Paul asserted claims for implied indemnification, negligence and contribution. In particular, they alleged that the water problems were caused by a number of deficiencies including defective architectural design plans and specifications, and that Munger was negligent in its design of the building, its preparation of the building's plans and specifications, and in its supervision of the construction of the building, all of which caused and/or contributed to the subject water infiltration and damage to the building. Munger filed an answer and counterclaim for indemnification. Munger's claim for indemnification against Mosser was based on the general conditions of Mosser's contract with the state which reads in Article 16.1.1 as follows:

{¶ 7} "To the fullest extent permitted by laws and regulations, the Contractor [Mosser] shall indemnify and hold harmless the Director, the Owner and the Associate [Munger], their respective officers, consultants, agents and employees, in both individual and official capacities, from and against all claims, damages, losses and expenses, direct, indirect or consequential arising out of or resulting from the Work."

{¶ 8} On January 3, 2005, Munger filed a motion for summary judgment on all of appellants' claims against it. Appellants filed a response and the court subsequently held an oral hearing on the matter. At that hearing, Mosser conceded that Munger was entitled to summary judgment on Count VI of the complaint, Mosser's claim for contribution. On April 19, 2005, the lower court issued a judgment entry granting Munger summary judgment on all of appellants' claims against it. It is from that judgment that appellants now appeal.

{¶ 9} Appellants challenge the trial court's judgment through the following assignments of error:

{¶ 10} "1. The trial court erred as a matter of law in granting defendant/appellee, Munger Munger Associates Architects, Inc.'s, motion for summary judgment on plaintiffs/appellants' negligence claim because a lack of privity of contract is not an absolute bar to recovery for purely economic losses where there is a sufficient nexus that can serve as a substitute for privity, and a genuine issue of material fact exists in this case as to whether defendant Munger Munger Associates Architects, Inc. exercised control over plaintiff Mosser Construction Inc. during construction so as to create a sufficient nexus between the parties to serve as a substitute for privity.

{¶ 11} "2. The trial court erred as a matter of law in granting defendant Munger Munger Associates Architects, Inc.'s motion for summary judgment on plaintiff's claim for indemnification because Ohio law recognizes a right of one who is only passively negligent, or secondarily liable, to recover from one who is actively negligent, or primarily liable, and a genuine issue of material fact exists as to whether Munger Munger Associates Architects, Inc. was actively negligent and whether Mosser Construction, Inc. was only passively negligent, whereby a cognizable cause of action for indemnification exists."

{¶ 12} Because both of appellants' assignments of error challenge various aspects of the lower court's order granting Munger summary judgment, we will apply the same standard of review to our discussion of those issues. Appellate review of a trial court's grant of summary judgment is de novo. Grafton v.Ohio Edison Co. (1996), 77 Ohio St.3d 102, 105. Summary judgment will be granted only when there remains no genuine issue of material fact and, when construing the evidence most strongly in favor of the nonmoving party, reasonable minds can only conclude that the moving party is entitled to judgment as a matter of law.Harless v. Willis Day Warehousing Co. (1978), 54 Ohio St.2d 64,66; Civ.R. 56(C).

{¶ 13} Appellants' first assignment of error addresses the trial court's granting of summary judgment to Munger on appellants' claim of negligence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Franklin Park Mall, Inc. v. Wtvg, Inc.
655 N.E.2d 1378 (Ohio Court of Appeals, 1995)
Clevecon, Inc. v. Northeast Ohio Regional Sewer District
628 N.E.2d 143 (Ohio Court of Appeals, 1993)
Globe Indemnity Co. v. Schmitt
53 N.E.2d 790 (Ohio Supreme Court, 1944)
Maryland Casualty Co. v. Frederick Co.
53 N.E.2d 795 (Ohio Supreme Court, 1944)
Losito v. Kruse, Jr.
24 N.E.2d 705 (Ohio Supreme Court, 1940)
Inglis v. American Motors Corp.
209 N.E.2d 583 (Ohio Supreme Court, 1965)
Travelers Indemnity Co. v. Trowbridge
321 N.E.2d 787 (Ohio Supreme Court, 1975)
Harless v. Willis Day Warehousing Co.
375 N.E.2d 46 (Ohio Supreme Court, 1978)
Reynolds v. Physicians Insurance
623 N.E.2d 30 (Ohio Supreme Court, 1993)
Village of Grafton v. Ohio Edison Co.
77 Ohio St. 3d 102 (Ohio Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
2006 Ohio 3607, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mosser-constr-v-w-waterproofing-co-unpublished-decision-7-14-2006-ohioctapp-2006.