Clarke's Allied, Incorporated v. Rail Source Fuel

662 F. App'x 248
CourtCourt of Appeals for the Fifth Circuit
DecidedOctober 5, 2016
Docket15-41492
StatusUnpublished
Cited by1 cases

This text of 662 F. App'x 248 (Clarke's Allied, Incorporated v. Rail Source Fuel) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clarke's Allied, Incorporated v. Rail Source Fuel, 662 F. App'x 248 (5th Cir. 2016).

Opinion

PER CURIAM: *

Plaintiff-Appellant Clarke’s Allied, Inc. (“Clarke’s”) brought a suit in federal district court, seeking to vacate or modify an arbitration award granted in favor of Defendant-Appellee Rail Source Fuel, L.L.C. (“RSF”). On RSF’s motion, the district court confirmed the award in full. Clarke’s now appeals. We AFFIRM.

I. BACKGROUND

In 2011, RSF contracted with Clarke’s to convert its tie-grinding operation from a diesel to an electric-powered system. A short while after the conversion project began, several problems arose and many component parts needed to be either repaired or replaced. Dissatisfied with Clarke’s service and equipment, RSF decided to use another company for its conversion project, ultimately paying Clarke’s only $916,850.77 of the $1,072,351.18 contract price. As a result, Clarke’s brought a mechanic’s lien enforcement action in a Texas state court for the remaining $155,500.41. RSF then removed the case to the U.S. District Court for the Eastern District of Texas. Once in federal district court, citing the contract’s arbitration clause and bringing breach of contract, fraud, lost profits, and negligent misrepresentation counterclaims, RSF moved for the ease to be sent to arbitration. Pursuant to the contract, the district court transferred the case to the American Arbitration Association (“AAA”) for consideration.

After reviewing the contract’s provisions, several affidavits, and the relevant case law, the AAA arbitrator found in favor of RSF, awarding it $916,850.77, the price paid under the contract, but denied RSF’s fraud, lost profits, and negligent misrepresentation claims. Moreover, in awarding this amount, the arbitrator denied Clarke’s mechanic’s lien, finding it lacked merit. Thereafter, RSF moved for Clarke’s to pay attorney’s fees and costs. Finding that RSF had failed to provide him with contemporaneous time records, the arbitrator concluded that RSF was not entitled to attorney’s fees. The arbitrator did, however, find that RSF was entitled to $193,352.59, the reasonable costs associated with defending against Clarke’s mechanic’s lien claim.

On January 6, 2015, RSF moved for the federal district court to confirm the arbitration award. On February 6, 2015, Clarke’s moved to vacate or modify the *250 award. The district court granted RSF’s motion in full, denying Clarke’s. Clarke’s appealed. We affirm.

II. STANDARD OF REVIEW

This court reviews a district court’s confirmation of an arbitrator’s award de novo. Timegate Studios, Inc. v. Southpeak Interactive, L.L.C., 713 F.3d 797, 802 (5th Cir. 2013). In reviewing the district court’s •judgment, however, we afford the arbitrator’s award great deference. Id. (quoting Executone Info. Sys., Inc. v. Davis, 26 F.3d 1314, 1320 (5th Cir. 1994)). The court must refrain from analyzing an arbitrator’s decision on the merits. Major League Baseball Players Ass’n v. Garvey, 532 U.S. 504, 509, 121 S.Ct. 1724, 149 L.Ed.2d 740 (2001) (citing Paperworkers v. Misco, Inc., 484 U.S. 29, 36, 108 S.Ct. 364, 98 L.Ed.2d 286 (1987)). Similarly, even if the arbitrator applied the governing law incorrectly, that alone is not grounds for setting the award aside. Kergosien v. Ocean Energy, Inc., 390 F.3d 346, 356 (5th Cir. 2004). If the “ ‘arbitrator is even arguably construing or applying the contract and acting within the scope of his authority,’ the fact that ‘a court is convinced he committed serious error does not suffice to overturn his decision.’ ” Garvey, 532 U.S. at 509,121 S.Ct. 1724 (quoting E. Associated Coal Corp. v. United Mine Workers of Am., 531 U.S. 57, 62, 121 S.Ct. 462, 148 L.Ed.2d 354 (2000)). To vacate or modify an arbitration award, the arbitrator’s award must be “so unfounded in reason and fact, so unconnected with the wording and purpose of the [contract,] as to ‘manifest an infidelity to the obligation of the arbitrator.’ ” Timegate Studios, 713 F.3d at 803 (quoting Bhd. of R.R. Trainmen v. Cent. of Ga. Ry., 415 F.2d 403, 415 (5th Cir. 1969)).

III. DISCUSSION

• Clarke’s raises three issues on appeal: that the arbitrator exceeded his authority by granting RSF (1) an unauthorized rescission remedy, (2) a remedy that conflicted with the terms of the underlying contract, and (3) unsegregated costs. 1 We address each issue in turn.

A.

Clarke’s argues that by awarding what it characterizes as a “rescission remedy,” the arbitrator awarded damages for which RSF did not ask, thereby exceeding his authority in violation of .9 U.S.C. §§ 10(a)(4) and 11(b). RSF counters by asserting that the arbitrator’s award was not a rescission remedy, but rather damages “consisting of the undisputed amounts paid to Clarke’s,” a point the-arbitrator stressed in his final award. RSF further notes that, although it did not request a rescission, it did request damages for Clarke’s breach of contract, including any amounts RSF paid to Clarke’s.

in making his final award, the arbitrator found that, because Clarke’s work was in *251 many ways defective, RSF rightfully rejected the work as a whole, citing to OR. Rev. Stat. § 72.3160(2) and noting that RSF had not waived the warranty of merchantability. In rendering his $916,850.77 award, the arbitrator noted that this was the total amount RSF paid Clarke’s. Thus, the arbitrator did not award an improper rescission remedy, but rather damages that “arguably constru[e] or appl[y] the contract.” Garvey, 532 U.S. at 509, 121 S.Ct. 1724 (quoting E. Associated Coal Corp., 531 U.S. at 62, 121 S.Ct. 462). Accordingly, we will not overturn the award on this ground.

B.

The second issue Clarke’s raises is that the arbitrator’s damages award directly conflicts with the terms of Clarke’s agreement with RSF, which limits damages for breach of warranty to the repair and replacement of any defective equipment. Further, Clarke’s contends that Oregon law regarding construction contracts, not the Oregon Uniform Commercial Code (“UCC”), should govern here.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
662 F. App'x 248, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clarkes-allied-incorporated-v-rail-source-fuel-ca5-2016.