Clark v. United States

167 Ct. Cl. 197, 1964 U.S. Ct. Cl. LEXIS 121, 1964 WL 8610
United States Court of Claims·Decided July 17, 1964·No. Cong. No. 10-58·Published·Cited by 6 cases

Opinion

Laramore, Judge,

delivered the opinion of the court:

Pursuant to 28 U.S.C. §§ 1492 and 2509, the United States Senate, through Senate Resolution 344,1 has asked us to pass upon the question of whether or not plaintiff is legally or equitably entitled to be additionally compensated for transportation services rendered by plaintiff for defendant during the period 1944 to 1946 at the Atomic Energy Commission installation at Oak Ridge, Tennessee.

At the outset it is pointed out that no legal liability would exist against the United States, for plaintiff’s cause of action would be barred by limitations under 28 U.S.C. § 2501. The petition was filed in this court on December 23, 1958; the resolution of the U.S. Senate which referred the matter to us (S. Res. 344, 85th Cong., 2d Sess.) was adopted on July 28, 1958; the bill for plaintiff’s relief (S. 2394) was introduced on June 26,1957. All these dates are considerably more than six years after the last date on which plaintiff’s claim could have accrued since the subject contracts were completed in 1946. Consequently, even if plaintiff had a legal claim within the jurisdiction of this court, such claim would be time barred by our 6-year statute of limitations.

[199] We turn now to the question of plaintiff’s equitable entitlement. There appear good reasons for lifting the bar of limitations in the instant case. Defendant’s administrative consideration of plaintiff’s claim did not end until 1955. The bill for plaintiff’s relief (S. 2394) was introduced just two years after this administrative determination of plaintiff’s claim. Under these circumstances, we believe that plaintiff’s delay in seeking a prompt judicial determination of his claim should be forgiven and we go on and consider the merits of plaintiff’s claim. See, S.N.T. Fratelli Gondrand v. United States, 166 Ct. Cl. 473, 484 (1964); Ralph Feffer and Sons v. United States, 166 Ct. Cl. 506, 508 (1964).

Commissioner Arens has rendered a most comprehensive, careful and detailed report in which he has concluded that the mileage rates which defendant “negotiated” with plaintiff were below the rates supported by defendant’s audits and formula for mileage rate determination, since defendant did not take into account the extra operating costs of plaintiff as compared to the costs of other operators. We have examined the record and agree with Commissioner Arens that the weight of the credible evidence compels such a conclusion.2 We accept and adopt the findings of the Commissioner and make them the basis of our legal determination that plaintiff has an “equitable claim” within the meaning of 28 U.S.C. § 2509. It is our belief that under the facts of the instant case, as demonstrated below, the conscience and honor of the sovereign dictates that plaintiff be recompensed for the losses he has suffered. See, O'Donell v. United States, 166 Ct. Cl. 107, 118 (1964).

The operations involved in this action revolve around four contracts, their supplements and amendments, entered into between plaintiff and defendant’s agents.3 Under the sub[200] contracts, plaintiff operated commuter bus service for employees at the Atomic Energy Commission installation at Oak Ridge, Tennessee. Prior to that time plaintiff operated a bus line on routes between Maryville and Lenoir City, Tennessee, and on routes between Lenoir City and different points in Oak Ridge. These bus line operations were profitable to plaintiff.

Plaintiff’s first two subcontracts (14 and 14-A) were with Roane-Anderson Company. Number 14 provided that plaintiff would operate buses to and from Oak Ridge by the use of rented government-owned buses at a designated rate per mile. Contract No. 14-A provided for the same services except with buses owned by plaintiff. On February 15,1945, American Industrial Transit succeeded Roane-Anderson as a government contractor to manage the bus transportation subcontracts. American Industrial Transit then negotiated two new subcontracts (8 and 8-A) which replaced but contained substantially the same provisions as subcontracts 14 and 14-A.4

[201] Plaintiff began operations under his subcontracts on February 14, 1944. Following a series of supplemental agreements in which the subcontracts were extended and mileage rates were “negotiated,” plaintiff’s subcontracts were terminated in May of 1946, but he was allowed to continue operations under the terms of the subcontracts until August 31, 1946. Thereafter, plaintiff continued to operate his franchise on runs to Oak Ridge for several months because contractual arrangements with defendant were then no longer required as a prerequisite to carrying passengers within the reservation. Due principally to reduced passenger requirements and the financial strain of the time payments on the buses which plaintiff was buying, he was unable to pay his bills. The mortgagors foreclosed the mortgages on his buses with the result that he was forced out of business.

The facts show that plaintiff’s net worth at the time he purchased his first bus in 1942 was between $20,000 and $30,000. When plaintiff entered into the subcontracts with defendant his net worth was about $40,000. At the conclusion of plaintiff’s subcontracts with defendant he was in debt between $40,000 and $50,000. It is stipulated by the parties that plaintiff suffered a net operating loss during the period of the subcontract operations of $18,818.76.

After plaintiff’s subcontracts were terminated, the Atomic Energy Commission arrived at a settlement -unilaterally. [202] The settlement took into account $7,879.95 asserted to be due the Federal government by reason of taxes due from plaintiff. On the unilateral settlement plaintiff was allowed a total of $5,745.02, which amount was sent to the Internal Revenue Service as payment on plaintiff’s account. This left due the Federal government from plaintiff the amount of $1,634.93.

Plaintiff contends that the losses he incurred -under the contract were due to defendant’s failure and refusal to negotiate and raise his mileage rate to conform to the provisions of the contracts. Defendant argues that plaintiff’s losses resulted from the inefficient manner in which he conducted his operations.

Free access — add to your briefcase to read the full text and ask questions with AI

Clark v. United States, 167 Ct. Cl. 197, 1964 U.S. Ct. Cl. LEXIS 121, 1964 WL 8610 (cc 1964).

167 Ct. Cl. 197 (Clark v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Banfi Products Corp. v. United States
40 Fed. Cl. 107 (Federal Claims, 1997)
Bear Claw Tribe, Inc. v. United States
36 Fed. Cl. 181 (Federal Claims, 1996)
INSLAW, Inc. v. United States
41 Cont. Cas. Fed. 76,979 (Federal Claims, 1996)
California Canners & Growers Ass'n v. United States
7 Cl. Ct. 69 (Court of Claims, 1984)
Aurex Corp. v. United States
175 Ct. Cl. 1 (Court of Claims, 1966)
Elmers v. United States
172 Ct. Cl. 226 (Court of Claims, 1965)