City Utilities of Springfield, Missouri v. FERC

Court of Appeals for the D.C. Circuit·Decided August 11, 2026·No. 24-1270·Published

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued December 2, 2025 Decided August 11, 2026

No. 24-1270

CITY UTILITIES OF SPRINGFIELD, MISSOURI, ET AL., PETITIONERS

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

BASIN ELECTRIC POWER COOPERATIVE, ET AL., INTERVENORS

Consolidated with 24-1282, 24-1283, 24-1285, 24-1372, 25-1007, 25-1023

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

Charlotte Taylor argued the cause for petitioners. With her on the briefs were James C. Beh, Christopher R. Jones, Shereen J. Panahi, Charles D. Wallace III, John P. Coyle, Natalie M. Karas, Heather H. Starnes, Dana Shelton, Justin A. Swaim, and Ashley Bond. Carrie L. Bumgarner and Timothy T. Mastrogiacomo entered appearances.

Carol J. Banta, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With her on the brief were David L. Morenoff, Deputy General Counsel, and Robert H. Solomon, Solicitor.

Erin Murphy argued the cause for intervenors. With her on the brief were Adrienne E. Clair, Nicholas A. Aquart, Jesse Halpern, Rebecca L. Shelton, Kimberly B. Frank, Matthew J. Binette, and Ruth M. Porter.

Before: SRINIVASAN, Chief Judge, HENDERSON and GARCIA, Circuit Judges.

Opinion for the Court filed by Circuit Judge GARCIA. GARCIA, Circuit Judge: Southwest Power Pool, Inc.

operates the electric transmission grid covering much of the central United States. SPP proposed to shift the costs of four electric-transmission facilities, which had been borne primarily by the facilities’ local zone, across the broader SPP region. The Federal Energy Regulatory Commission approved that proposal based on evidence that the four facilities are primarily serving and benefiting customers outside of that local zone. Petitioners—utilities, transmission owners, and a state regulator representing affected ratepayers whose costs would increase as a result—argue that FERC’s approval was inadequately reasoned and unsupported by substantial evidence. We disagree and deny the petitions for review.

I

A

The Federal Power Act (FPA) gives FERC authority over the rates governing the interstate transmission of electricity. 16 U.S.C. § 824(b). All such rates must be “just and reasonable” and may not grant any “undue preference or advantage.” Id. § 824d(a)–(b). The just and reasonable standard “incorporate[s] a ‘cost-causation principle.’” Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1255 (D.C. Cir.

2018) (quoting Ala. Elec. Co-op, Inc. v. FERC, 684 F.2d 20, 27 (D.C. Cir. 1982)). That principle requires rates to “reflect to some degree the costs actually caused by the customer who must pay them.” KN Energy Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992).

Under Section 205 of the FPA, public utilities may propose “rates and charges.” 16 U.S.C. § 824d(c); see Atl. City Elec. Co. v. FERC, 295 F.3d 1, 9 (D.C. Cir. 2002). Those rates and charges are collected in a filing known as a “tariff.” 18 C.F.R. § 35.2(c)(1). The utility proposing a rate change bears the burden of showing that it is “just and reasonable.” Advanced Energy Mgmt. All. v. FERC, 860 F.3d 656, 662 (D.C. Cir. 2017) (quoting 16 U.S.C. § 824d(e)). When presented with such a proposal, FERC plays “an essentially passive and reactive role.” Id. (quoting City of Winnfield v. FERC, 744 F.2d 871, 875–76 (D.C. Cir. 1984)). FERC asks whether the new rate would be reasonable, not whether it is “‘more or less reasonable’ than other possible rate designs.” N.Y. State Pub. Serv. Comm’n v. FERC, 104 F.4th 886, 891 (D.C. Cir. 2024) (quoting City of Bethany v. FERC, 727 F.2d 1131, 1136 (D.C. Cir. 1984)). So long as the proposal falls within the “zone of reasonableness,” FERC must accept it. Id.

B

SPP is a regional transmission organization that operates a large electric-transmission system across the central United States. It divides its region into eighteen local price zones. Transmission facilities (such as power lines) move electricity throughout the SPP grid. A transmission facility’s location does not necessarily determine who benefits from its use—an individual facility, for example, might serve power to local customers and to other parts of the SPP region. These cases concern SPP’s efforts to equitably allocate the costs of such facilities throughout the region.

Since 2010, SPP has used the “Highway/Byway” method

to allocate the costs of transmission facilities. See Sw. Power Pool, 131 FERC ¶ 61,252, at P 62 (2010), order on reh’g, 137 FERC ¶ 61,075 (2011). Highway/Byway uses operating voltage to determine the assignment of facility costs. Facilities operating at 300 kilovolts or above are designated “Highway” facilities—their costs are allocated entirely on a regional basis. See Sw. Power Pool, 131 FERC ¶ 61,252, at PP 10, 23. Those operating between 100 and 300 kilovolts are “Byway” facilities—33 percent of their costs are allocated regionwide and 67 percent to the host zone. Id. at PP 10, 12, 23. Any remaining facilities operating at or below 100 kilovolts have their costs allocated entirely to the local host zone. See id. at P 10. FERC found that method consistent with the cost-causation principle because evidence showed that higher-voltage facilities “tend to support regional power flows” across multiple zones, while lower-voltage facilities “tend to support local power flows within a single . . . SPP zone.” Id. at P 73.

The Highway/Byway method also includes a periodic review process known as the Regional Cost Allocation Review (RCAR). This process evaluates whether the method continues to produce appropriate long-term benefit-to-cost ratios across SPP’s zones. See Sw. Power Pool, 189 FERC ¶ 61,128, at P 48 (2024) (“Rehearing Order”). RCAR assesses the Highway/Byway cost allocation at a systemwide and zonal level; the latter serves “to indicate that a zone’s benefits are roughly commensurate with the costs allocated to the zone.” Id. at P 4. RCAR does not assess the costs and benefits of individual facilities. See id. at P 48.

The four facilities at issue here lie in the Sunflower Zone, which covers central and western Kansas. SPP originally classified these facilities as Byways based on their operating voltages. See Sw. Power Pool, 187 FERC ¶ 61,123, at PP 2, 7 (2024) (“Initial Order”). Later, SPP concluded that, despite that classification, the facilities were increasingly serving a

regional function due to expanding wind generation in the zone. Unlike gas or coal generation, which can typically be sited near the customers it serves, wind generation can be built at scale only where wind resources are abundant. See Southwest Power Pool, Inc. Submission of Tariff Revisions, Docket No. ER24-1583-000, at 9 (Mar. 20, 2024) (“March 2024 Filing”). Wind-rich areas therefore may generate more electricity than local demand requires, and some of that surplus electricity ends up being transmitted to customers elsewhere in the region. See id. at 9, 11. According to SPP, that is what happened here: Over time, the four facilities increasingly carried power generated in the Sunflower Zone to serve users elsewhere in the SPP region. See id. at 11, 28. SPP concluded that, despite their Byway designation, these facilities were providing regional benefits more characteristic of Highway facilities. See id. at 28.

Free access — add to your briefcase to read the full text and ask questions with AI

City Utilities of Springfield, Missouri v. FERC, (D.C. Cir. 2026).

City Utilities of Springfield, Missouri v. FERC (City Utilities of Springfield, Missouri v. FERC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Maine v. Federal Energy Regulatory Commission
854 F.3d 9 (D.C. Circuit, 2017)
SFPP LP v. FERC
967 F.3d 788 (D.C. Circuit, 2020)
East Texas Electric Cooperative, Inc. v. FERC
90 F.4th 579 (D.C. Circuit, 2024)
New York State Public Service Commission v. FERC
104 F.4th 886 (D.C. Circuit, 2024)