City of Westminster v. MOA, INC.

867 P.2d 137, 17 Brief Times Rptr. 1559, 1993 Colo. App. LEXIS 299, 1993 WL 409854
CourtColorado Court of Appeals
DecidedOctober 14, 1993
Docket91CA1226, 92CA0117
StatusPublished
Cited by10 cases

This text of 867 P.2d 137 (City of Westminster v. MOA, INC.) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Westminster v. MOA, INC., 867 P.2d 137, 17 Brief Times Rptr. 1559, 1993 Colo. App. LEXIS 299, 1993 WL 409854 (Colo. Ct. App. 1993).

Opinions

Opinion by

Judge JONES.

In this action for damages allegedly resulting from defects in the design and construction of its city hall, plaintiff, City of Westminster, appeals from a judgment in favor of defendants, MOA, Inc. (MOA), Carrier Corporation, and Parker Electronics, Inc. (Carrier/Parker). Westminster settled its claims with certain other defendants before the filing of this appeal, and the claims against the general contractor and its surety and the general contractor’s cross-appeal were settled subsequent to the filing of the appeal. We reverse and remand for a new trial.

In 1986, Westminster contracted with MOA to provide architectural services for the design and construction of a new city hall. Carrier/Parker manufactured components for the heating, ventilation, and air-conditioning system.

In February 1988, Westminster occupied the building, and in May 1988, it discovered that rain water was penetrating into the building through a brick cavity wall, causing interior damage. MOA and the general contractor agreed to remedy the problem and further agreed to mediation on the issue of allocation of costs for these repairs. The city was not a party to this mediation.

In preparation for the mediation, MOA contacted John Reins, an employee of Mad-sen, Kneppers and Associates (Madsen), to act as an expert. Reins declined to act as MOA’s expert and, instead, recommended Lee Farrell, also an employee of Madsen. Farrell was retained by MOA and, during mediation, acted as an expert on MOA’s be[139]*139half on the issue of rainwater penetration of the building.

Subsequently, the city discovered other defects in the design and construction of the building. The heating, ventilation, and air conditioning system was not performing as expected, and movement of the foundation piers of the building was causing interior and exterior building damage. Several firms studied the foundation movement problem, and three firms, in March, August, and October 1989, issued reports to Westminster.

Prior to the filing of its complaint, Westminster retained Reins, and, beginning early in 1990, he began to study building movement for the city. When Westminster endorsed Reins as an expert witness in its initial disclosure certificate in September 1990, MOA moved to have Reins disqualified from testifying. On December 31, 1990, the court, finding that a conflict of interest existed and that it would be prejudicial, unfair, and inappropriate to allow Reins to testify as an expert, granted MOA’s motion.

On January 17, 1991, Westminster moved to clarify the court’s order disqualifying Reins and for an extension of time within which to identify new experts to testify on the structural problems of the building. On February 11, Westminster filed its supplemental disclosure certificate, listing four new expert witnesses, including an architect, a heating and air conditioning expert, an engineer, and a certified public accountant, as well as several new fact witnesses. However, on February 13, 1991, the court denied Westminster’s motion.

Prior to trial, Westminster settled with two defendants named in the complaint, a mechanical engineer and a supplier. Also, it settled its heating, ventilation, and air conditioning claims against MOA. The supplier paid $20,000, the mechanical engineer paid $40,000, and MOA paid $60,000 in these settlements. The engineer and the supplier were later designated as non-parties at fault.

The defendants objected to the endorsement of the new witnesses, as well as to other parts of the supplemental disclosure certificates, and the court sustained the objections, striking the certificate. Westminster’s counsel advised the court that, given its previous order and without waiving any right, Westminster would not pursue those claims. Thus, Westminster did not present evidence on these claims at trial, and MOA was dismissed from the case.

The jury found that Westminster had suffered damages in the amount of $135,000. It allocated responsibility at 60% to the general contractor, 0% to Carrier/Parker, 20% to the non-party mechanical engineer, and 20% to the non-party supplier. The trial court then reduced the general contractor’s liability to $21,000.

I.

Westminster first asserts that the trial court abused its discretion in disqualifying its expert from testifying on issues of structural defects and rainwater intrusion. Although Westminster concedes that MOA discussed the issue of rainwater intrusion with Farrell, it contends that there is no evidence that MOA disclosed confidential information to anyone from Madsen concerning the structural movement of city hall. The city also asserts that Reins’ long-term observations of the building movement made him unique and that no other expert would have been able to duplicate Reins’ observations at the time that the court issued its order on disqualification. According to Westminster, the trial court’s order would have precluded any new expert from relying on Reins’ survey data in formulating his opinions and that it was placed at a serious disadvantage by being prevented from presenting Reins’ testimony about his observations and conclusions. We reject these arguments.

The question of disqualification of an expert for a conflict of interest was addressed in Wang Laboratories, Inc. v. Toshiba Corp., 762 F.Supp. 1246 (E.D.Va.1991). There, the court stated that, in cases in which the parties dispute whether retention and passage of confidential information occurred, the courts should undertake a two part inquiry:

First, was it objectively reasonable for the first party who claims to have retained the consultant ... to conclude that a confidential relationship existed?
[140]*140Second, was any confidential or privileged information disclosed by the first party to the consultant?
[[Image here]]
Affirmative answers to both inquiries compel disqualification. But disqualification is likely inappropriate if either inquiry yields a negative response.

Wang Laboratories, Inc. v. Toshiba Corp., supra, at 1248.

The court further acknowledged that the inherent power of the courts to disqualify experts exists in furtherance of the judicial duty to protect the integrity of the adversary process and to promote public confidence in the fairness and integrity of the legal process.

Disqualification ordinarily should not occur when a confidential relationship existed but no privileged information was communicated or, alternatively, when no confidential relationship existed but privileged information was nonetheless disclosed. The party seeking disqualification bears the burden of establishing both the existence of a privilege and its non-waiver. Mayer v. Dell, 139 F.R.D. 1 (D.D.C.1991).

Asserting that Reins received no information from his associate as to the rainwater penetration issue and because there is no need to hold expert witnesses to the strict standards applied to attorneys, Westminster contends that its expert should not have been disqualified from testifying as to any issue. Westminster asserts that it does not appear that Farrell was in possession of any confidential information not waived by MOA’s endorsement of Farrell as an expert in the mediation and that Farrell and Reins did not communicate concerning the brick cavity wall issue. We reject these arguments.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Empire Surplus Lines Insurance v. Care Centers, Inc.
484 F. Supp. 2d 855 (N.D. Illinois, 2007)
State ex rel. Billups v. Clawges
620 S.E.2d 162 (West Virginia Supreme Court, 2005)
Matthews v. Commonwealth
163 S.W.3d 11 (Kentucky Supreme Court, 2005)
City of Springfield v. Rexnord Corp.
111 F. Supp. 2d 71 (D. Massachusetts, 2000)
Mitchell v. Wilmore
981 P.2d 172 (Supreme Court of Colorado, 1999)
J.P. v. District Court in & for the 2nd Judicial District of Denver
873 P.2d 745 (Supreme Court of Colorado, 1994)
City of Westminster v. MOA, INC.
867 P.2d 137 (Colorado Court of Appeals, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
867 P.2d 137, 17 Brief Times Rptr. 1559, 1993 Colo. App. LEXIS 299, 1993 WL 409854, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-westminster-v-moa-inc-coloctapp-1993.