City of Milford v. Coppola Const. Co., Inc.

891 A.2d 31, 93 Conn. App. 704, 2006 Conn. App. LEXIS 66
CourtConnecticut Appellate Court
DecidedFebruary 14, 2006
DocketAC 26106
StatusPublished
Cited by9 cases

This text of 891 A.2d 31 (City of Milford v. Coppola Const. Co., Inc.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Milford v. Coppola Const. Co., Inc., 891 A.2d 31, 93 Conn. App. 704, 2006 Conn. App. LEXIS 66 (Colo. Ct. App. 2006).

Opinion

Opinion

FLYNN, J.

The plaintiff, the city of Milford, appeals from the judgment of the trial court denying its application to modify and correct the arbitration award and confirming the award of $136,787.50 in favor of the defendant, Coppola Construction Company, Inc. The plaintiff claims that the court should have modified the arbitrator’s award pursuant to General Statutes § 52-419 (a) 1 because the award (1) failed to conform to the *706 submission and (2) contained material miscalculations. The defendant claims that the submission to arbitration was unrestricted because the plaintiff rescinded the contract that contained the limiting provisions, and that the award conforms to the submission. The court determined that because the contract between the parties provided that not all types of damages were amenable to arbitration, the parties made a restricted submission but that the award conformed to that submission. We affirm the judgment of the trial court.

Resolution of the plaintiffs appeal requires us to determine first whether the submission to the arbitrator was restricted or unrestricted. We conclude that the court correctly determined that the submission was restricted because, as stated in the arbitration clause, the parties waived claims against each other for consequential damages, with the exception of anticipated lost profit arising directly from the work, and, therefore, claims for such waived damages were not arbitrable. The scope of the trial court’s review and our review on appeal, however, is only as broad as the nature of the restrictions allow. We conclude that the trial court’s determinations that no prohibited consequential damages were awarded and that the award conformed to the submission were within the scope of that court’s review and were proper given the nature of the restrictions at issue, and we decline to go beyond that to review de novo the evidence before the arbitrator.

The following facts are relevant to our resolution of this appeal. On December 11, 2000, the plaintiff entered into a contract with the defendant to elevate six private residential structures in Milford for $294,000. Paragraph 9.10.4 of the contract provided, in part, that claims and disputes arising out of the contract would be resolved by arbitration, except, however, according to paragraph 9.11, the parties waived claims against each other for consequential damages, excepting only anticipated lost *707 profits arising directly from the work. After seven months of delay caused by issues regarding code requirements that had arisen between the plaintiff and the office of the state building inspector, the defendant began lifting the first house and discovered that the house had a type of framing different from what was anticipated. The defendant negotiated a change order that increased the contract price to $309,000 to compensate the defendant for the condition it encountered. The change order was confirmed by the defendant’s October 1, 2001 letter. Thereafter, it was discovered that the other five houses also had this type of different framing, and the city ordered that work stop until the parties could be agreed on a price. On May 17, 2002, the plaintiff wrote a letter to the defendant stating: “Inasmuch as [the defendant] is unwilling or unable to resume and complete the work at the price set forth in the contract, or at any mutually agreed upon price, the [plaintiff] has no choice but to cancel the contract.” At that point, one house was complete, one had been withdrawn from the project by its private owner and four remained to be elevated.

The submission the parties made to arbitration was invoked by the following demand, which we summarize. On March 27, 2003, the defendant submitted what it termed an arbitration statement. In that statement, the defendant alleged that the plaintiff had rescinded the contract and that the contract provisions, except for dispute resolution, were null and void because the plaintiff had abandoned them. The defendant alleged that the plaintiff “attempted to concoct reasons for the rescission such as [that the defendant] defaulted on its obligations under the contract. There was no default by [the defendant] for the reason stated by [the plaintiff] that it was unable to complete the project because the parties were unable to fix a price for the changed condition.” The defendant further alleged that it had *708 bought specialized equipment for the project, which sat idle for seven months “while [the plaintiff] corrected the plans to allow a permit to be obtained.” The defendant stated that it had a cause of action for wrongful termination and for bad faith against the plaintiff and therefore was entitled to damages for idle equipment, demobilization costs, field costs, lost profit and attorney’s fees. The plaintiff, in its April 8, 2003 answer, denied all causes of action and all claimed damages. The plaintiff alleged, inter alia, as special defenses that the defendant persistently failed to carry out work in accordance with the contract, that the defendant refused to perform work at the contract price, that the purpose of the contract was being frustrated at a time when the project was less than 20 percent complete and grant moneys were ending, and that, under such circumstances, on May 17, 2002, the plaintiff terminated the contract, directing the defendant not to resume work and to leave the project. The parties submitted their dispute to arbitration. On August 11, 2003, an arbitrator awarded the defendant $136,787.50 in damages for lost profits, idle equipment and materials, plus interest. 2 The *709 plaintiff filed an application to modify and correct the arbitration award. The court denied the plaintiffs motion on December 1,2004, confirming the arbitrator’s award with 10 percent interest per year from August 1, 2002. This appeal followed.

I

We first set forth our standard of review. If the parties choose to set limits on the arbitrator’s powers, then the parties will be bound by those limits. Carroll v. Aetna Casualty & Surety Co., 189 Conn. 16, 20, 453 A.2d 1158 (1983). “The process which governs the confirmation of arbitral awards is well settled by our cases. If the parties have agreed in the underlying contract that their disputes shall be resolved by arbitration, the arbitration clause in the contract is a written submission to arbitration. . . . This submission can be invoked by a demand for arbitration by one or both parties when a dispute arises. The agreement for submission constitutes the charter for the entire ensuing arbitration proceedings.” (Citations omitted.) Vail v. American Way Homes, Inc., 181 Conn. 449, 451, 435 A.2d 993 (1980).

“[Our Supreme Court] has for many years wholeheartedly endorsed arbitration as an effective alternative method of settling disputes ‘intended to avoid the formalities, delay, expense and vexation of ordinary litigation.’ Bridgeport v. Bridgeport Police Local 1159, 183 Conn.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Toland v. Toland
182 A.3d 651 (Connecticut Appellate Court, 2018)
Department of Transportation v. White Oak Corp.
62 A.3d 599 (Connecticut Appellate Court, 2013)
Levinson v. Westport National Bank
900 F. Supp. 2d 143 (D. Connecticut, 2012)
Cruz v. Visual Perceptions, LLC
46 A.3d 209 (Connecticut Appellate Court, 2012)
Between Rounds Franchise Corp. v. EDGR Real Estate, LLC
40 A.3d 833 (Connecticut Superior Court, 2011)
Dupont v. Tobin, Carberry, O'malley, Riley, Selinger, PC
322 F. App'x 66 (Second Circuit, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
891 A.2d 31, 93 Conn. App. 704, 2006 Conn. App. LEXIS 66, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-milford-v-coppola-const-co-inc-connappct-2006.