City of Lexington v. Dawson County Public Power District

504 N.W.2d 532, 244 Neb. 62, 1993 Neb. LEXIS 213
CourtNebraska Supreme Court
DecidedAugust 20, 1993
DocketS-91-450
StatusPublished
Cited by34 cases

This text of 504 N.W.2d 532 (City of Lexington v. Dawson County Public Power District) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Lexington v. Dawson County Public Power District, 504 N.W.2d 532, 244 Neb. 62, 1993 Neb. LEXIS 213 (Neb. 1993).

Opinion

Hastings, C.J.

The Dawson County Public Power District (Dawson) appeals from an order of the Nebraska Power Review Board (Board) which determined the total economic impact of transferring an electrical service area from Dawson to the City of Lexington (Lexington) under the provisions of Neb. Rev. Stat. § 70-1010 (Reissue 1990) and ordered the payment by Lexington to Dawson of $596,809. Lexington cross-appeals.

Neb. Rev. Stat. § 70-1016 (Reissue 1990) provided that an *63 appeal may be taken to the Supreme Court from any final action of the Board in the same manner as appeals are taken from decisions of the Public Service Commission.

In the case In re Complaint of Federal Land Bank of Omaha, 223 Neb. 897, 395 N.W.2d 488 (1986), this court held that an action of the Public Service Commission will be affirmed on appeal if it is supported by evidence in the record and is not arbitrary, capricious, or otherwise illegal; and thus, the same standard of review applies to decisions of the Board, i.e., if they are supported by the evidence and are reasonable and not arbitrary, they are to be affirmed. It is quite apparent from that rule that this court cannot set itself up as a super-administrative body and reach its own conclusion without regard to that made by the Board.

On January 22, 1990, Lexington, pursuant to Neb. Rev. Stat. § 70-1008 (Reissue 1990), filed an application with the Board to transfer newly annexed territory to its electric service area. That section provides in part that a municipally owned electric system serving such municipality at retail shall have the right upon application to and approval by the Board to serve newly annexed areas of such municipality. An annexation of a certain area has taken place, and there is no dispute as to Lexington’s right to serve this annexed area.

However, the parties unsuccessfully attempted to agree, under the provisions of § 70-1010, upon the value of the annexed certified service area, distribution facilities, and customers of Dawson being transferred to Lexington.

Therefore, further application was made by Lexington to have the Board determine the total economic impact which transferring the territory would have on the area’s current electric supplier, Dawson. Dawson joined in that application. The Board requested that, pursuant to § 70-1010, the parties submit information as to what costs would be incurred by Dawson if the transfer of the area in question took place.

Section 70-1010(2) provides:

In the event of a proposed transfer of customers and facilities from one supplier to another in accordance with this section or section 70-1008 or 70-1009, the parties shall attempt to agree upon the value of the certified service *64 area and distribution facilities and customers being transferred. If the parties cannot agree upon the value, then the board shall determine the total economic impact on the selling supplier and establish the price accordingly based on, but not limited to, the following guidelines: The supplier acquiring the certified service area, distribution facilities, and customers shall purchase the electric distribution facilities of the supplier located within the affected area, together with the supplier’s rights to serve within such area, for cash consideration which shall consist of (a) the current reproduction cost if the facilities being acquired were new, less depreciation computed on a straight-line basis at three percent per year not to exceed seventy percent, plus (b) an amount equal to the nonbetterment cost of constructing any facilities necessary to reintegrate the system of the supplier outside the area being transferred after detaching the portion to be sold, plus (c) an amount equal to two and one-half times the annual revenue received from power sales to existing customers of electric power within the area being transferred .... After the board has determined the price in accordance with such guidelines, the acquiring supplier may acquire such distribution facilities and customers by payment of the established price within one year of the final order.

Lexington and Dawson entered into a stipulation agreeing on the value of two components of the above valuation. They agreed that the appropriate figure for the current reproduction cost of facilities being acquired, in accordance with § 70-1010(2)(a), was $92,423 and that the nonbetterment cost of reintegration, under subsection (2)(b) of the statute, was $21,873.

Lexington and Dawson also agreed that the annual revenue from the customers in the area to be transferred was $108,660.83, but were unable to agree upon how this figure was to be applied. At a hearing before the Board, Lexington’s expert testified that multiplying the annual revenue figure by 2V2, pursuant to subsection (2)(c) of § 70-1010, would produce a figure which when added to the figures determined under *65 § 70-1010(2)(a) and (b) would represent the total economic impact of the acquisition of the service area by Lexington. However, Dawson adduced testimony that this figure would not provide adequate compensation.

Economist Donald Macke testified that he had considered potential growth in the area in calculating present and future net revenue losses and determined that the necessary lump-sum payment to compensate Dawson for that loss would, be $653,345. In addition, Dawson’s general manager, Phillip Darby, testified that a transmission line substation and feeder circuits which provided service to the area would be partly idled by the loss of the load of the annexed area, requiring compensation of $97,271. Darby also testified in regard to the increased cost of power due to the loss of the load in the annexed area, referred to as the “ratchet impact.” As explained by Darby, the ratchet impact in this case results from the fact that Dawson must build and maintain a system capable of supplying electric service to more than 3,800 irrigation customers for 2 or 3 months of the year. The ratchet charge is a component of the wholesale power contract under which Dawson purchases power, requiring that a percentage of the maximum peak established during the period of high usage must be purchased for the remaining months of the year. Darby stated that because the annexed area is a winter-peaking load, the loss of that load would substantially and materially affect the ratchet cost Dawson pays, resulting in additional annual ratchet costs of $ 13,030, or a total of $196,679.

Following the hearing, the Board issued an order that Lexington should pay Dawson the sum of $596,809 for the service area and facilities which would be acquired.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Application of City of Neligh
299 Neb. 517 (Nebraska Supreme Court, 2018)
Opinion No. (2000)
Nebraska Attorney General Reports, 2000
Dawson County Public Power District v. City of North Platte
599 N.W.2d 218 (Nebraska Supreme Court, 1999)
Association of Commonwealth v. Moylan
517 N.W.2d 94 (Nebraska Supreme Court, 1994)
Rosse v. Rosse
510 N.W.2d 73 (Nebraska Supreme Court, 1994)
State on Behalf of Matchett v. Dunkle
508 N.W.2d 580 (Nebraska Supreme Court, 1993)
Malzahn v. Transit Authority
507 N.W.2d 289 (Nebraska Supreme Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
504 N.W.2d 532, 244 Neb. 62, 1993 Neb. LEXIS 213, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-lexington-v-dawson-county-public-power-district-neb-1993.